on Monday, December 16th 2024, 6:30:00 pm
Work Sanctioned
राज्य योजना 2024-25 के अन्तर्गत जनपद हरिद्वार के वि0स0 क्षेत्र हरिद्वार में वार्ड नं0-16 में शिवलोक में मार्ग का निर्माण कार्य।
on Tuesday, December 24th 2024, 9:55:47 am
Technical Sanction
of ₹ 87.76 Lacs
1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. TS VIDE EE Approved Register Sl.no.59
on Thursday, February 27th 2025, 6:30:00 pm
1%
Physical Progress
Physical Progress Reported at 1st time
on Friday, March 14th 2025, 6:30:00 pm
0.13%
Financial Progress
1st Expenditure
of ₹ 11419 (0.11 Lacs ) done.
Cummulative ₹ 0.11Lacs ( against 87.76Lacs )
on Tuesday, May 20th 2025, 6:30:00 pm
2.87%
Financial Progress
2nd Expenditure
of ₹ 240720 (2.41 Lacs ) done.
Cummulative ₹ 2.52Lacs ( against 87.76Lacs )
on Wednesday, May 28th 2025, 6:30:00 pm
30%
Physical Progress
Physical Progress Reported at 2nd time
on Thursday, May 29th 2025, 6:30:00 pm
32.32%
Financial Progress
3rd Expenditure
of ₹ 2584672 (25.85 Lacs ) done.
Cummulative ₹ 28.37Lacs ( against 87.76Lacs )
on Monday, June 30th 2025, 6:30:00 pm
33.76%
Financial Progress
4th Expenditure
of ₹ 125742 (1.26 Lacs ) done.
Cummulative ₹ 29.63Lacs ( against 87.76Lacs )
on Sunday, July 27th 2025, 6:30:00 pm
35.05%
Financial Progress
5th Expenditure
of ₹ 113107 (1.13 Lacs ) done.
Cummulative ₹ 30.76Lacs ( against 87.76Lacs )
on Sunday, July 27th 2025, 6:30:00 pm
57.12%
Financial Progress
6th Expenditure
of ₹ 1936996 (19.37 Lacs ) done.
Cummulative ₹ 50.13Lacs ( against 87.76Lacs )
on Tuesday, July 29th 2025, 6:30:00 pm
80%
Physical Progress
Physical Progress Reported at 3rd time