on Tuesday, December 31st 2013, 6:30:00 pm
Work Sanctioned
मा0 मुख्यमंत्री जी की घोषणा सं0-460/2012 के अन्तर्गत जनपद देहरादून के विधान सभा क्षेत्र चकराता में हरिपुर-इच्छाडी-क्वानू मीनस मोटर मार्ग के (राज्य मार्ग सं0-21) के किमी0 1 से 30 में बी0एम0/एस0डी0बी0सी0 द्वारा सुदृढीकरण का कार्य।
on Friday, February 14th 2014, 6:30:00 pm
Technical Sanction
of ₹ 2393.06 Lacs
1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. TS VIDE CE 153/9(16)CM level-1/2014
on Friday, February 28th 2014, 6:30:00 pm
29.28%
Financial Progress
1st Expenditure
of ₹ 70064000 (700.64 Lacs ) done.
Cummulative ₹ 700.64Lacs ( against 2393.06Lacs )
on Wednesday, April 30th 2014, 6:30:00 pm
27.95%
Financial Progress
2nd Expenditure
of ₹ -3171000 (-31.71 Lacs ) done.
Cummulative ₹ 668.93Lacs ( against 2393.06Lacs )
on Saturday, May 31st 2014, 6:30:00 pm
44.77%
Financial Progress
3rd Expenditure
of ₹ 40245000 (402.45 Lacs ) done.
Cummulative ₹ 1071.38Lacs ( against 2393.06Lacs )
on Thursday, July 31st 2014, 6:30:00 pm
50.44%
Financial Progress
4th Expenditure
of ₹ 13569000 (135.69 Lacs ) done.
Cummulative ₹ 1207.07Lacs ( against 2393.06Lacs )
on Sunday, August 31st 2014, 6:30:00 pm
57.44%
Financial Progress
5th Expenditure
of ₹ 16746000 (167.46 Lacs ) done.
Cummulative ₹ 1374.53Lacs ( against 2393.06Lacs )
on Friday, October 31st 2014, 6:30:00 pm
61.74%
Financial Progress
6th Expenditure
of ₹ 10292000 (102.92 Lacs ) done.
Cummulative ₹ 1477.45Lacs ( against 2393.06Lacs )
on Sunday, November 30th 2014, 6:30:00 pm
69.00%
Financial Progress
7th Expenditure
of ₹ 17384000 (173.84 Lacs ) done.
Cummulative ₹ 1651.29Lacs ( against 2393.06Lacs )
on Saturday, January 31st 2015, 6:30:00 pm
69.05%
Financial Progress
8th Expenditure
of ₹ 106000 (1.06 Lacs ) done.
Cummulative ₹ 1652.35Lacs ( against 2393.06Lacs )
on Saturday, February 28th 2015, 6:30:00 pm
75.54%
Financial Progress
9th Expenditure
of ₹ 15532000 (155.32 Lacs ) done.
Cummulative ₹ 1807.67Lacs ( against 2393.06Lacs )
on Thursday, April 30th 2015, 6:30:00 pm
77.63%
Financial Progress
10th Expenditure
of ₹ 5011000 (50.11 Lacs ) done.
Cummulative ₹ 1857.78Lacs ( against 2393.06Lacs )
on Tuesday, June 30th 2015, 6:30:00 pm
77.63%
Financial Progress
11th Expenditure
of ₹ 7000 (0.07 Lacs ) done.
Cummulative ₹ 1857.85Lacs ( against 2393.06Lacs )
on Monday, August 31st 2015, 6:30:00 pm
79.67%
Financial Progress
12th Expenditure
of ₹ 4869000 (48.69 Lacs ) done.
Cummulative ₹ 1906.54Lacs ( against 2393.06Lacs )
on Wednesday, September 30th 2015, 6:30:00 pm
82.17%
Financial Progress
13th Expenditure
of ₹ 5973000 (59.73 Lacs ) done.
Cummulative ₹ 1966.27Lacs ( against 2393.06Lacs )
on Monday, November 30th 2015, 6:30:00 pm
81.35%
Financial Progress
14th Expenditure
of ₹ -1947000 (-19.47 Lacs ) done.
Cummulative ₹ 1946.80Lacs ( against 2393.06Lacs )
on Thursday, December 31st 2015, 6:30:00 pm
80.68%
Financial Progress
15th Expenditure
of ₹ -1598000 (-15.98 Lacs ) done.
Cummulative ₹ 1930.82Lacs ( against 2393.06Lacs )
on Sunday, January 31st 2016, 6:30:00 pm
81.29%
Financial Progress
16th Expenditure
of ₹ 1456000 (14.56 Lacs ) done.
Cummulative ₹ 1945.38Lacs ( against 2393.06Lacs )
on Thursday, June 30th 2016, 6:30:00 pm
83.84%
Financial Progress
17th Expenditure
of ₹ 6096000 (60.96 Lacs ) done.
Cummulative ₹ 2006.34Lacs ( against 2393.06Lacs )
on Tuesday, January 31st 2017, 6:30:00 pm
82.79%
Financial Progress
18th Expenditure
of ₹ -2503000 (-25.03 Lacs ) done.
Cummulative ₹ 1981.31Lacs ( against 2393.06Lacs )
on Wednesday, January 31st 2018, 6:30:00 pm
83.86%
Financial Progress
19th Expenditure
of ₹ 2540000 (25.40 Lacs ) done.
Cummulative ₹ 2006.71Lacs ( against 2393.06Lacs )
on Saturday, March 31st 2018, 6:30:00 pm
83.86%
Financial Progress
20th Expenditure
of ₹ 19486 (0.19 Lacs ) done.
Cummulative ₹ 2006.90Lacs ( against 2393.06Lacs )
on Monday, April 30th 2018, 6:30:00 pm
83.88%
Financial Progress
21st Expenditure
of ₹ 40543 (0.41 Lacs ) done.
Cummulative ₹ 2007.31Lacs ( against 2393.06Lacs )
on Thursday, May 31st 2018, 6:30:00 pm
83.90%
Financial Progress
22nd Expenditure
of ₹ 35158 (0.35 Lacs ) done.
Cummulative ₹ 2007.66Lacs ( against 2393.06Lacs )
on Tuesday, July 31st 2018, 6:30:00 pm
84.68%
Financial Progress
23rd Expenditure
of ₹ 1871792 (18.72 Lacs ) done.
Cummulative ₹ 2026.38Lacs ( against 2393.06Lacs )
on Sunday, September 30th 2018, 6:30:00 pm
84.68%
Financial Progress
24th Expenditure
of ₹ 8080 (0.08 Lacs ) done.
Cummulative ₹ 2026.46Lacs ( against 2393.06Lacs )
on Wednesday, October 31st 2018, 6:30:00 pm
85.70%
Financial Progress
25th Expenditure
of ₹ 2432019 (24.32 Lacs ) done.
Cummulative ₹ 2050.78Lacs ( against 2393.06Lacs )
on Monday, December 31st 2018, 6:30:00 pm
85.78%
Financial Progress
26th Expenditure
of ₹ 198084 (1.98 Lacs ) done.
Cummulative ₹ 2052.76Lacs ( against 2393.06Lacs )
on Thursday, January 31st 2019, 6:30:00 pm
85.82%
Financial Progress
27th Expenditure
of ₹ 88805 (0.89 Lacs ) done.
Cummulative ₹ 2053.65Lacs ( against 2393.06Lacs )
on Tuesday, April 30th 2019, 6:30:00 pm
86.95%
Financial Progress
28th Expenditure
of ₹ 2706393 (27.06 Lacs ) done.
Cummulative ₹ 2080.71Lacs ( against 2393.06Lacs )
on Friday, May 31st 2019, 6:30:00 pm
87.18%
Financial Progress
29th Expenditure
of ₹ 560994 (5.61 Lacs ) done.
Cummulative ₹ 2086.32Lacs ( against 2393.06Lacs )
on Sunday, June 30th 2019, 6:30:00 pm
87.48%
Financial Progress
30th Expenditure
of ₹ 713978 (7.14 Lacs ) done.
Cummulative ₹ 2093.46Lacs ( against 2393.06Lacs )
on Wednesday, July 31st 2019, 6:30:00 pm
87.90%
Financial Progress
31st Expenditure
of ₹ 1012221 (10.12 Lacs ) done.
Cummulative ₹ 2103.59Lacs ( against 2393.06Lacs )
on Saturday, August 31st 2019, 6:30:00 pm
88.15%
Financial Progress
32nd Expenditure
of ₹ 598054 (5.98 Lacs ) done.
Cummulative ₹ 2109.57Lacs ( against 2393.06Lacs )
on Monday, September 30th 2019, 6:30:00 pm
88.43%
Financial Progress
33rd Expenditure
of ₹ 664619 (6.65 Lacs ) done.
Cummulative ₹ 2116.21Lacs ( against 2393.06Lacs )
on Friday, January 31st 2020, 6:30:00 pm
89.37%
Financial Progress
34th Expenditure
of ₹ 2239315 (22.39 Lacs ) done.
Cummulative ₹ 2138.61Lacs ( against 2393.06Lacs )
on Sunday, May 31st 2020, 6:30:00 pm
89.41%
Financial Progress
35th Expenditure
of ₹ 109000 (1.09 Lacs ) done.
Cummulative ₹ 2139.70Lacs ( against 2393.06Lacs )
on Tuesday, June 30th 2020, 6:30:00 pm
89.50%
Financial Progress
36th Expenditure
of ₹ 214255 (2.14 Lacs ) done.
Cummulative ₹ 2141.84Lacs ( against 2393.06Lacs )
on Friday, July 31st 2020, 6:30:00 pm
89.56%
Financial Progress
37th Expenditure
of ₹ 134602 (1.35 Lacs ) done.
Cummulative ₹ 2143.18Lacs ( against 2393.06Lacs )
on Monday, August 31st 2020, 6:30:00 pm
89.84%
Financial Progress
38th Expenditure
of ₹ 680000 (6.80 Lacs ) done.
Cummulative ₹ 2149.98Lacs ( against 2393.06Lacs )
on Sunday, September 13th 2020, 6:30:00 pm
Technical Sanction
of ₹ 170.57 Lacs
2nd Technical Sanction of Work after survey,detailed design and analysis by Latter No. Proposal CE-2861/09(157)Yata-level-1(ZO)/2017
on Wednesday, September 30th 2020, 6:30:00 pm
89.88%
Financial Progress
39th Expenditure
of ₹ 85296 (0.85 Lacs ) done.
Cummulative ₹ 2150.84Lacs ( against 2393.06Lacs )
on Saturday, October 31st 2020, 6:30:00 pm
89.88%
Financial Progress
40th Expenditure
of ₹ 8500 (0.09 Lacs ) done.
Cummulative ₹ 2150.92Lacs ( against 2393.06Lacs )
on Monday, November 30th 2020, 6:30:00 pm
89.90%
Financial Progress
41st Expenditure
of ₹ 48000 (0.48 Lacs ) done.
Cummulative ₹ 2151.40Lacs ( against 2393.06Lacs )
on Thursday, December 31st 2020, 6:30:00 pm
91.43%
Financial Progress
42nd Expenditure
of ₹ 3652192 (36.52 Lacs ) done.
Cummulative ₹ 2187.92Lacs ( against 2393.06Lacs )
on Sunday, January 31st 2021, 6:30:00 pm
91.48%
Financial Progress
43rd Expenditure
of ₹ 125466 (1.25 Lacs ) done.
Cummulative ₹ 2189.18Lacs ( against 2393.06Lacs )
on Sunday, February 28th 2021, 6:30:00 pm
95.23%
Financial Progress
44th Expenditure
of ₹ 8967658 (89.68 Lacs ) done.
Cummulative ₹ 2278.86Lacs ( against 2393.06Lacs )
on Thursday, July 22nd 2021, 7:57:30 am
PWD UttarakahndPhoto (ID 1093) from Site Received
Uploader : Radhika Sharma, Assistant Engineer Civil ,TD Sahiya
Landmark : Km29
Remark : Instructions given for reconstruction !!
on Friday, July 30th 2021, 6:30:00 pm
97.27%
Financial Progress
45th Expenditure
of ₹ 4880929 (48.81 Lacs ) done.
Cummulative ₹ 2327.66Lacs ( against 2393.06Lacs )
on Wednesday, August 25th 2021, 11:45:44 pm
PWD UttarakahndPhoto (ID 1092) from Site Received
Uploader : Radhika Sharma, Assistant Engineer Civil ,TD Sahiya
Landmark : Km16
Remark : Marked by cross sign (because of poor quality -honeycombing)!!instructions given to the contractor to reconstruct marked paraphet !!
on Thursday, August 26th 2021, 1:23:48 am
PWD UttarakahndPhoto (ID 1094) from Site Received
Uploader : Radhika Sharma, Assistant Engineer Civil ,TD Sahiya
Landmark : Km16
Remark : Poor quality !! Instructions are given for reconstruction !!
on Thursday, August 26th 2021, 1:36:40 am
PWD UttarakahndPhoto (ID 1095) from Site Received
Uploader : Radhika Sharma, Assistant Engineer Civil ,TD Sahiya
Landmark : Km17
Remark : Will be constructed again!!
on Monday, August 30th 2021, 6:30:00 pm
97.28%
Financial Progress
46th Expenditure
of ₹ 21090 (0.21 Lacs ) done.
Cummulative ₹ 2327.88Lacs ( against 2393.06Lacs )
on Wednesday, September 29th 2021, 6:30:00 pm
99.30%
Financial Progress
47th Expenditure
of ₹ 4849000 (48.49 Lacs ) done.
Cummulative ₹ 2376.37Lacs ( against 2393.06Lacs )
on Wednesday, March 30th 2022, 6:30:00 pm
99.93%
Financial Progress
48th Expenditure
of ₹ 1490000 (14.90 Lacs ) done.
Cummulative ₹ 2391.27Lacs ( against 2393.06Lacs )