7 years ago

on Sunday, February 17th 2019, 6:30:00 pm
Work Sanctioned
रा0यो0 2018-19 के अन्तर्गत पनियाला से बलेलपुर होते हुए खाताखेड़ी तक सी0सी0 इन्टरलोकिंग टाईल्स एवं पी0सी0 द्वारा सड़क निर्माण कार्य।

7 years ago

on Thursday, February 28th 2019, 6:30:00 pm
0.01%
Financial Progress

1st Expenditure
of ₹ 1500 (0.01 Lacs ) done.
Cummulative ₹ 0.01Lacs ( against 193.97Lacs )

6 years ago

on Sunday, May 19th 2019, 6:30:00 pm

Technical Sanction
of ₹ 181.71 Lacs

1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. 904(5)/20C-Civil Circle/19

5 years ago

on Thursday, December 31st 2020, 6:30:00 pm
23.41%
Financial Progress

2nd Expenditure
of ₹ 4539000 (45.39 Lacs ) done.
Cummulative ₹ 45.41Lacs ( against 193.97Lacs )

5 years ago

on Sunday, January 31st 2021, 6:30:00 pm
35.44%
Financial Progress

3rd Expenditure
of ₹ 2334000 (23.34 Lacs ) done.
Cummulative ₹ 68.75Lacs ( against 193.97Lacs )

5 years ago

on Sunday, February 28th 2021, 6:30:00 pm
60.96%
Financial Progress

4th Expenditure
of ₹ 4949000 (49.49 Lacs ) done.
Cummulative ₹ 118.23Lacs ( against 193.97Lacs )

4 years ago

on Saturday, October 30th 2021, 6:30:00 pm
62.19%
Financial Progress

5th Expenditure
of ₹ 240000 (2.40 Lacs ) done.
Cummulative ₹ 120.64Lacs ( against 193.97Lacs )

3 years ago

on Wednesday, March 30th 2022, 6:30:00 pm
72.53%
Financial Progress

6th Expenditure
of ₹ 2006000 (20.06 Lacs ) done.
Cummulative ₹ 140.69Lacs ( against 193.97Lacs )

3 years ago

on Saturday, April 2nd 2022, 6:30:00 pm
100%

Physical Progress
Physical Progress Reported at 1st time

3 years ago

on Sunday, October 30th 2022, 6:30:00 pm
73.49%
Financial Progress

7th Expenditure
of ₹ 186000 (1.86 Lacs ) done.
Cummulative ₹ 142.56Lacs ( against 193.97Lacs )

3 years ago

on Tuesday, November 29th 2022, 6:30:00 pm
78.65%
Financial Progress

8th Expenditure
of ₹ 1000000 (10.00 Lacs ) done.
Cummulative ₹ 152.56Lacs ( against 193.97Lacs )

3 years ago

on Monday, February 27th 2023, 6:30:00 pm
82.29%
Financial Progress

9th Expenditure
of ₹ 706000 (7.06 Lacs ) done.
Cummulative ₹ 159.62Lacs ( against 193.97Lacs )

2 years ago

on Thursday, March 30th 2023, 6:30:00 pm
93.63%
Financial Progress

10th Expenditure
of ₹ 2200000 (22.00 Lacs ) done.
Cummulative ₹ 181.62Lacs ( against 193.97Lacs )

6 months ago

on Thursday, February 27th 2025, 6:30:00 pm
95.01%
Financial Progress

11th Expenditure
of ₹ 267000 (2.67 Lacs ) done.
Cummulative ₹ 184.28Lacs ( against 193.97Lacs )