4 years ago

on Tuesday, August 10th 2021, 6:30:00 pm
Work Sanctioned
रा0यो0 वर्ष 2021-22 के अन्तर्गत झबरेड़ा में बन्दाखेड़ी से कमेलपुर तक सी0सी0 इण्टरलोकिंग टाईल्स द्वारा सड़क मार्ग निर्माण का कार्य

4 years ago

on Sunday, September 5th 2021, 10:10:01 am

Technical Sanction
of ₹ 114.93 Lacs

1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. 2107/20C-Civil Circle/2021

3 years ago

on Thursday, December 30th 2021, 6:30:00 pm
28.64%
Financial Progress

1st Expenditure
of ₹ 3538000 (35.38 Lacs ) done.
Cummulative ₹ 35.38Lacs ( against 123.55Lacs )

3 years ago

on Sunday, January 9th 2022, 6:30:00 pm
25%

Physical Progress
Physical Progress Reported at 1st time

3 years ago

on Sunday, January 30th 2022, 6:30:00 pm
28.68%
Financial Progress

2nd Expenditure
of ₹ 6000 (0.06 Lacs ) done.
Cummulative ₹ 35.44Lacs ( against 123.55Lacs )

3 years ago

on Sunday, February 27th 2022, 6:30:00 pm
28.68%
Financial Progress

3rd Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 35.44Lacs ( against 123.55Lacs )

3 years ago

on Wednesday, March 30th 2022, 6:30:00 pm
80.96%
Financial Progress

4th Expenditure
of ₹ 6459000 (64.59 Lacs ) done.
Cummulative ₹ 100.03Lacs ( against 123.55Lacs )

3 years ago

on Thursday, March 31st 2022, 6:30:00 pm
32%

Physical Progress
Physical Progress Reported at 2nd time

3 years ago

on Sunday, May 8th 2022, 6:30:00 pm
65%

Physical Progress
Physical Progress Reported at 3rd time

3 years ago

on Thursday, June 16th 2022, 6:30:00 pm
82%

Physical Progress
Physical Progress Reported at 4th time

3 years ago

on Monday, July 4th 2022, 6:30:00 pm
100%

Physical Progress
Physical Progress Reported at 5th time

3 years ago

on Thursday, September 29th 2022, 6:30:00 pm
91.76%
Financial Progress

5th Expenditure
of ₹ 1334000 (13.34 Lacs ) done.
Cummulative ₹ 113.37Lacs ( against 123.55Lacs )

2 years ago

on Tuesday, November 29th 2022, 6:30:00 pm
92.26%
Financial Progress

6th Expenditure
of ₹ 62000 (0.62 Lacs ) done.
Cummulative ₹ 113.99Lacs ( against 123.55Lacs )

2 years ago

on Thursday, March 30th 2023, 6:30:00 pm
93.02%
Financial Progress

7th Expenditure
of ₹ 94000 (0.94 Lacs ) done.
Cummulative ₹ 114.93Lacs ( against 123.55Lacs )

6 months ago

on Sunday, October 27th 2024, 6:30:00 pm
94.27%
Financial Progress

8th Expenditure
of ₹ 153459 (1.53 Lacs ) done.
Cummulative ₹ 116.46Lacs ( against 123.55Lacs )