Work Sanctioned
राज्य योजना वर्ष 2023-24 के अन्तर्गत पिरान कलियर के ग्राम मरगूबपुर में ईदगाह के सामने से अस्पताल की ओर मरगूबपुर बाईपास सड़क का ईंट खडण्जा द्वारा सड़क निर्माण कार्य।
on Monday, August 21st 2023, 6:46:54 am
Technical Sanction
of ₹ 60.64 Lacs
1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. 1736/1C
on Sunday, March 17th 2024, 6:30:00 pm
0.28%
Financial Progress
1st Expenditure
of ₹ 17159 (0.17 Lacs ) done.
Cummulative ₹ 0.17Lacs ( against 60.64Lacs )
on Saturday, March 30th 2024, 6:30:00 pm
0.63%
Financial Progress
2nd Expenditure
of ₹ 21000 (0.21 Lacs ) done.
Cummulative ₹ 0.38Lacs ( against 60.64Lacs )
on Tuesday, September 17th 2024, 6:30:00 pm
2.74%
Financial Progress
3rd Expenditure
of ₹ 127959 (1.28 Lacs ) done.
Cummulative ₹ 1.66Lacs ( against 60.64Lacs )
on Sunday, September 22nd 2024, 6:30:00 pm
3.99%
Financial Progress
4th Expenditure
of ₹ 76010 (0.76 Lacs ) done.
Cummulative ₹ 2.42Lacs ( against 60.64Lacs )
on Sunday, September 29th 2024, 6:30:00 pm
25.21%
Financial Progress
5th Expenditure
of ₹ 1286412 (12.86 Lacs ) done.
Cummulative ₹ 15.29Lacs ( against 60.64Lacs )
on Wednesday, October 23rd 2024, 6:30:00 pm
25%
Physical Progress
Physical Progress Reported at 1st time
on Sunday, November 24th 2024, 6:30:00 pm
27.33%
Financial Progress
6th Expenditure
of ₹ 128697 (1.29 Lacs ) done.
Cummulative ₹ 16.57Lacs ( against 60.64Lacs )
on Thursday, November 28th 2024, 6:30:00 pm
30%
Physical Progress
Physical Progress Reported at 2nd time
on Monday, January 27th 2025, 6:30:00 pm
45%
Physical Progress
Physical Progress Reported at 3rd time
on Monday, February 3rd 2025, 6:30:00 pm
38.03%
Financial Progress
7th Expenditure
of ₹ 648720 (6.49 Lacs ) done.
Cummulative ₹ 23.06Lacs ( against 60.64Lacs )
on Tuesday, April 29th 2025, 6:30:00 pm
52%
Physical Progress
Physical Progress Reported at 4th time
on Sunday, May 25th 2025, 6:30:00 pm
46.18%
Financial Progress
9th Expenditure
of ₹ 5821 (0.06 Lacs ) done.
Cummulative ₹ 28.00Lacs ( against 60.64Lacs )
on Sunday, May 25th 2025, 6:30:00 pm
46.09%
Financial Progress
8th Expenditure
of ₹ 488677 (4.89 Lacs ) done.
Cummulative ₹ 27.95Lacs ( against 60.64Lacs )
on Thursday, May 29th 2025, 6:30:00 pm
90%
Physical Progress
Physical Progress Reported at 5th time
on Wednesday, June 25th 2025, 6:30:00 pm
54.17%
Financial Progress
10th Expenditure
of ₹ 484485 (4.84 Lacs ) done.
Cummulative ₹ 32.85Lacs ( against 60.64Lacs )
on Sunday, June 29th 2025, 6:30:00 pm
100%
Physical Progress
Physical Progress Reported at 6th time
on Sunday, July 20th 2025, 6:30:00 pm
70.85%
Financial Progress
11th Expenditure
of ₹ 1011145 (10.11 Lacs ) done.
Cummulative ₹ 42.96Lacs ( against 60.64Lacs )
on Monday, July 28th 2025, 6:30:00 pm
79.00%
Financial Progress
12th Expenditure
of ₹ 494205 (4.94 Lacs ) done.
Cummulative ₹ 47.90Lacs ( against 60.64Lacs )