2 years ago

on Wednesday, October 4th 2023, 6:30:00 pm
Work Sanctioned
राज्य योजना वर्ष 2023-24 के अन्तर्गत खानपुर के ढण्डेरा में सुरजन नगर कालोनी के आन्तरिक मार्गों का सी0सी0 इण्टरलोकिंग टाईल्स द्वारा निर्माण।

2 years ago

on Thursday, October 26th 2023, 9:55:24 am

Technical Sanction
of ₹ 29.69 Lacs

1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. 2170(i)/1C

a year ago

on Wednesday, March 20th 2024, 6:30:00 pm
1.67%
Financial Progress

1st Expenditure
of ₹ 49560 (0.50 Lacs ) done.
Cummulative ₹ 0.50Lacs ( against 29.69Lacs )

a year ago

on Friday, March 29th 2024, 6:30:00 pm
40%

Physical Progress
Physical Progress Reported at 1st time

a year ago

on Wednesday, April 24th 2024, 6:30:00 pm
48%

Physical Progress
Physical Progress Reported at 2nd time

a year ago

on Thursday, May 2nd 2024, 6:30:00 pm
78%

Physical Progress
Physical Progress Reported at 3rd time

a year ago

on Thursday, May 9th 2024, 6:30:00 pm
3.18%
Financial Progress

2nd Expenditure
of ₹ 44993 (0.45 Lacs ) done.
Cummulative ₹ 0.95Lacs ( against 29.69Lacs )

a year ago

on Thursday, May 23rd 2024, 6:30:00 pm
18.68%
Financial Progress

3rd Expenditure
of ₹ 460166 (4.60 Lacs ) done.
Cummulative ₹ 5.55Lacs ( against 29.69Lacs )

a year ago

on Monday, June 3rd 2024, 6:30:00 pm
88%

Physical Progress
Physical Progress Reported at 4th time

a year ago

on Friday, September 27th 2024, 6:30:00 pm
100%

Physical Progress
Physical Progress Reported at 5th time

10 months ago

on Sunday, October 27th 2024, 6:30:00 pm
84.40%
Financial Progress

4th Expenditure
of ₹ 1951079 (19.51 Lacs ) done.
Cummulative ₹ 25.06Lacs ( against 29.69Lacs )

3 months ago

on Sunday, May 18th 2025, 6:30:00 pm
93.98%
Financial Progress

6th Expenditure
of ₹ 261873 (2.62 Lacs ) done.
Cummulative ₹ 27.90Lacs ( against 29.69Lacs )

3 months ago

on Sunday, May 18th 2025, 6:30:00 pm
94.75%
Financial Progress

7th Expenditure
of ₹ 22679 (0.23 Lacs ) done.
Cummulative ₹ 28.13Lacs ( against 29.69Lacs )

3 months ago

on Sunday, May 18th 2025, 6:30:00 pm
85.16%
Financial Progress

5th Expenditure
of ₹ 22680 (0.23 Lacs ) done.
Cummulative ₹ 25.28Lacs ( against 29.69Lacs )

3 months ago

on Sunday, May 25th 2025, 6:30:00 pm
96.90%
Financial Progress

9th Expenditure
of ₹ 24900 (0.25 Lacs ) done.
Cummulative ₹ 28.77Lacs ( against 29.69Lacs )

3 months ago

on Sunday, May 25th 2025, 6:30:00 pm
96.06%
Financial Progress

8th Expenditure
of ₹ 38940 (0.39 Lacs ) done.
Cummulative ₹ 28.52Lacs ( against 29.69Lacs )

3 months ago

on Sunday, May 25th 2025, 6:30:00 pm
97.41%
Financial Progress

10th Expenditure
of ₹ 15220 (0.15 Lacs ) done.
Cummulative ₹ 28.92Lacs ( against 29.69Lacs )

2 months ago

on Wednesday, July 9th 2025, 6:30:00 pm
98.22%
Financial Progress

12th Expenditure
of ₹ 11800 (0.12 Lacs ) done.
Cummulative ₹ 29.16Lacs ( against 29.69Lacs )

2 months ago

on Wednesday, July 9th 2025, 6:30:00 pm
97.83%
Financial Progress

11th Expenditure
of ₹ 12390 (0.12 Lacs ) done.
Cummulative ₹ 29.04Lacs ( against 29.69Lacs )