on Sunday, November 10th 2024, 6:30:00 pm
Work Sanctioned
राज्य योजना वर्ष 2024-25 के अन्तर्गत झबरेड़ा के ग्राम मुंडेट में आन्तरिक गलियों में इण्टरलोकिंग टाईल्स द्वारा निर्माण कार्य।
on Tuesday, November 12th 2024, 6:13:14 am
Technical Sanction
of ₹ 95.4 Lacs
1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. 52/2024-25
on Monday, February 3rd 2025, 6:30:00 pm
0.42%
Financial Progress
1st Expenditure
of ₹ 40238 (0.40 Lacs ) done.
Cummulative ₹ 0.40Lacs ( against 95.4Lacs )
on Thursday, March 20th 2025, 6:30:00 pm
2.27%
Financial Progress
2nd Expenditure
of ₹ 175938 (1.76 Lacs ) done.
Cummulative ₹ 2.16Lacs ( against 95.4Lacs )
on Monday, March 24th 2025, 6:30:00 pm
16%
Physical Progress
Physical Progress Reported at 1st time
on Tuesday, April 29th 2025, 6:30:00 pm
25%
Physical Progress
Physical Progress Reported at 2nd time
on Friday, May 2nd 2025, 6:30:00 pm
7.44%
Financial Progress
3rd Expenditure
of ₹ 494058 (4.94 Lacs ) done.
Cummulative ₹ 7.10Lacs ( against 95.4Lacs )
on Friday, May 2nd 2025, 6:30:00 pm
12.56%
Financial Progress
4th Expenditure
of ₹ 487711 (4.88 Lacs ) done.
Cummulative ₹ 11.98Lacs ( against 95.4Lacs )
on Thursday, May 8th 2025, 6:30:00 pm
15.26%
Financial Progress
5th Expenditure
of ₹ 258305 (2.58 Lacs ) done.
Cummulative ₹ 14.56Lacs ( against 95.4Lacs )
on Sunday, May 18th 2025, 6:30:00 pm
20.42%
Financial Progress
6th Expenditure
of ₹ 492239 (4.92 Lacs ) done.
Cummulative ₹ 19.48Lacs ( against 95.4Lacs )
on Thursday, May 29th 2025, 6:30:00 pm
45%
Physical Progress
Physical Progress Reported at 3rd time