on Thursday, December 26th 2024, 6:30:00 pm
Work Sanctioned
सड़क सुरक्षा मद के अन्तर्गत जनपद-बागेश्वर के बागेश्वर-गिरेछीना मोटर मार्ग (राज्य मार्ग-58) के किमी0 1.00 से 19.00 एवं जिलाधिकारी कार्यालय पहुॅच मार्ग (अन्य जिला मार्ग) के लम्बाई 2.50 किमी0 में दुर्घटना सम्भावित स्थलों मेें सड़क सुरक्षा हेतु सुरक्षात्मक कार्य।
on Wednesday, April 23rd 2025, 12:04:09 pm
PWD UttarakahndPhoto (ID 67957) from Site Received
Uploader : VIKASH SINGH, Junior Engineer Civil ,PD Bageshwar
Landmark : 7+150
Remark : Installation and Assembly of crash barrier at ch 7+150 in bageshwar girechina mr under road safety
on Wednesday, April 23rd 2025, 12:13:38 pm
PWD UttarakahndPhoto (ID 67960) from Site Received
Uploader : VIKASH SINGH, Junior Engineer Civil ,PD Bageshwar
Landmark : 7+230 near bijauri village
Remark : Installation and Assembly work of crash barrier is in progress at chainage 7+230 in bageshwar girechina mr SH 58 under road safety
on Friday, April 25th 2025, 10:44:16 am
PWD UttarakahndPhoto (ID 68236) from Site Received
Uploader : Bijendra Singh Mehra, Assistant Engineer Civil ,PD Bageshwar
Landmark : Km 6
Remark : Installation of crash barrier work in progress
on Friday, April 25th 2025, 10:46:32 am
PWD UttarakahndPhoto (ID 68237) from Site Received
Uploader : Bijendra Singh Mehra, Assistant Engineer Civil ,PD Bageshwar
Landmark : Km 6
Remark : Installation of crash barrier work in progress
on Wednesday, April 30th 2025, 11:30:17 am
PWD UttarakahndPhoto (ID 68992) from Site Received
Uploader : VIKASH SINGH, Junior Engineer Civil ,PD Bageshwar
Landmark : 8+230
Remark : Installation of crash barrier in bageshwar girechina mr at chainage 8+230 under road safety work
on Thursday, May 1st 2025, 8:16:26 am
PWD UttarakahndPhoto (ID 69082) from Site Received
Uploader : VIKASH SINGH, Junior Engineer Civil ,PD Bageshwar
Landmark : 1+200
Remark : Inspection of Installation of crash barrier work in bageshwar girechina mr by EE sir and AE sir
on Thursday, May 1st 2025, 8:20:10 am
PWD UttarakahndPhoto (ID 69084) from Site Received
Uploader : Sanjay Kumar Pandey, Executive Engineer Civil ,PD Bageshwar
Landmark : Km 2
Remark : Road safety work is going on thickness found 5 mm
on Friday, May 2nd 2025, 11:51:12 am
PWD UttarakahndPhoto (ID 69260) from Site Received
Uploader : VIKASH SINGH, Junior Engineer Civil ,PD Bageshwar
Landmark : 7+750
Remark : Installation of crash barrier work is in progress in bageshwar girechina mr
on Monday, May 5th 2025, 8:10:45 am
PWD UttarakahndPhoto (ID 69657) from Site Received
Uploader : VIKASH SINGH, Junior Engineer Civil ,PD Bageshwar
Landmark : 1+200
Remark : Installation of crash barrier work is in progress in bageshwar girechina mr
on Tuesday, May 6th 2025, 9:22:15 am
PWD UttarakahndPhoto (ID 69808) from Site Received
Uploader : VIKASH SINGH, Junior Engineer Civil ,PD Bageshwar
Landmark : 1+650
Remark : Inspection of crash barrier work with AE sir
on Tuesday, May 6th 2025, 6:30:00 pm
47.59%
Financial Progress
1st Expenditure
of ₹ 30003713 (300.04 Lacs ) done.
Cummulative ₹ 300.04Lacs ( against 630.47Lacs )
on Wednesday, May 7th 2025, 10:47:25 am
PWD UttarakahndPhoto (ID 69952) from Site Received
Uploader : VIKASH SINGH, Junior Engineer Civil ,PD Bageshwar
Landmark : 0+010
Remark : Bituminous concrete work is in progress in kanda saniudiyar rawatsera mr at ch 0+010
on Wednesday, May 7th 2025, 10:52:37 am
PWD UttarakahndPhoto (ID 69953) from Site Received
Uploader : VIKASH SINGH, Junior Engineer Civil ,PD Bageshwar
Landmark : 0+010
Remark : Inspection of Bituminous concrete work in kanda saniudiyar rawatsera mr with AE sir
on Monday, May 12th 2025, 6:30:00 pm
40%
Physical Progress
Physical Progress Reported at 1st time
on Wednesday, May 14th 2025, 9:33:11 am
PWD UttarakahndPhoto (ID 70851) from Site Received
Uploader : Sanjay Kumar Pandey, Executive Engineer Civil ,PD Bageshwar
Landmark : Km 12
Remark : Work progress
on Wednesday, June 11th 2025, 9:48:34 am
PWD UttarakahndPhoto (ID 74448) from Site Received
Uploader : VIKASH SINGH, Junior Engineer Civil ,PD Bageshwar
Landmark : Crash barrier work is in progress in bageshwar girechina mr
Remark : Inspection of crash barrier work with AE sir
on Thursday, June 12th 2025, 11:16:51 am
PWD UttarakahndPhoto (ID 74736) from Site Received
Uploader : VIKASH SINGH, Junior Engineer Civil ,PD Bageshwar
Landmark : 6+800
Remark : Rumble strip work is in progress in bageshwar girechina mr
on Friday, June 20th 2025, 6:40:00 am
PWD UttarakahndPhoto (ID 76882) from Site Received
Uploader : DIVYA VERMA, Junior Engineer Civil ,PD Bageshwar
Landmark : DM road
Remark : Road safety work
on Friday, June 20th 2025, 6:42:41 am
PWD UttarakahndPhoto (ID 76884) from Site Received
Uploader : DIVYA VERMA, Junior Engineer Civil ,PD Bageshwar
Landmark : DM road
Remark : Installation of post for crash barrier
on Friday, June 20th 2025, 6:30:00 pm
56.33%
Financial Progress
2nd Expenditure
of ₹ 5511035 (55.11 Lacs ) done.
Cummulative ₹ 355.15Lacs ( against 630.47Lacs )
on Monday, June 23rd 2025, 1:22:48 pm
PWD UttarakahndPhoto (ID 77889) from Site Received
Uploader : DIVYA VERMA, Junior Engineer Civil ,PD Bageshwar
Landmark : 5w1082
Remark : crash barrier in DM approach road
on Monday, June 23rd 2025, 1:34:00 pm
PWD UttarakahndPhoto (ID 77893) from Site Received
Uploader : DIVYA VERMA, Junior Engineer Civil ,PD Bageshwar
Landmark : Crash barrier work
Remark : Crash barrier in DM approach road
on Wednesday, July 9th 2025, 6:30:00 pm
100%
Physical Progress
Physical Progress Reported at 2nd time
on Thursday, July 10th 2025, 6:30:00 pm
66.35%
Financial Progress
3rd Expenditure
of ₹ 6320080 (63.20 Lacs ) done.
Cummulative ₹ 418.35Lacs ( against 630.47Lacs )
on Wednesday, July 23rd 2025, 6:30:00 pm
75.71%
Financial Progress
4th Expenditure
of ₹ 5898167 (58.98 Lacs ) done.
Cummulative ₹ 477.33Lacs ( against 630.47Lacs )