on Thursday, December 26th 2024, 6:30:00 pm
Work Sanctioned
सड़क सुरक्षा मद के अन्तर्गत जनपद-बागेश्वर के बागेश्वर-कपकोट-तेजम मोटर मार्ग (राज्य मार्ग-40) के किमी0 1.00 से 2.80 में दुर्घटना सम्भावित क्षेत्रों का सड़क सुरक्षा हेतु सुरक्षात्मक कार्य।
on Monday, April 7th 2025, 7:21:33 am
PWD UttarakahndPhoto (ID 67072) from Site Received
Uploader : Bijendra Singh Mehra, Assistant Engineer Civil ,PD Bageshwar
Landmark : Km3
Remark : Crash barrier work in progress verified by EE height found 1.80 m
on Monday, April 7th 2025, 7:25:05 am
PWD UttarakahndPhoto (ID 67073) from Site Received
Uploader : Sanjay Kumar Pandey, Executive Engineer Civil ,PD Bageshwar
Landmark : Km 3
Remark : Crash barrier check 150x75x5 found
on Thursday, April 17th 2025, 4:04:00 am
PWD UttarakahndPhoto (ID 67411) from Site Received
Uploader : Bijendra Singh Mehra, Assistant Engineer Civil ,PD Bageshwar
Landmark : Km 1
Remark : Installation of crash barrier work in progress
on Tuesday, May 6th 2025, 6:30:00 pm
52.35%
Financial Progress
1st Expenditure
of ₹ 1942653 (19.43 Lacs ) done.
Cummulative ₹ 19.43Lacs ( against 37.11Lacs )
on Monday, May 12th 2025, 6:30:00 pm
100%
Physical Progress
Physical Progress Reported at 1st time
on Sunday, May 25th 2025, 6:06:44 pm
PWD UttarakahndPhoto (ID 72085) from Site Received
Uploader : NEHA SINGH, Junior Engineer Civil ,PD Bageshwar
Landmark : Km 1 HM 2-4
Remark : Marking of rumble strip using thermoplastic at bageshwar kapkote tejam motor road
on Thursday, June 12th 2025, 6:30:00 pm
52.46%
Financial Progress
2nd Expenditure
of ₹ 4269 (0.04 Lacs ) done.
Cummulative ₹ 19.47Lacs ( against 37.11Lacs )
on Wednesday, July 23rd 2025, 6:30:00 pm
80.61%
Financial Progress
3rd Expenditure
of ₹ 1044386 (10.44 Lacs ) done.
Cummulative ₹ 29.91Lacs ( against 37.11Lacs )