8 months ago

on Thursday, December 26th 2024, 6:30:00 pm
Work Sanctioned
सड़क सुरक्षा मद के अन्तर्गत जनपद-बागेश्वर के अन्तर्गत विकासखण्ड गरूड़ में अकुणाई-अणा-लोहारचैड़ा-गैरखेत मोटर मार्ग (अन्य जिला मार्ग) के किमी0 1.00 से 12.00 व राज्य अतिथि गृह कौसानी मोटर मार्ग (अन्य जिला मार्ग) के किमी0 2.20 में दुर्घटना सम्भावित स्थलों में सड़क सुरक्षा हेतु सुरक्षात्मक कार्य।

2 months ago

on Wednesday, July 9th 2025, 6:30:00 pm
70%

Physical Progress
Physical Progress Reported at 1st time

2 months ago

on Thursday, July 10th 2025, 6:30:00 pm
54.38%
Financial Progress

1st Expenditure
of ₹ 18856400 (188.56 Lacs ) done.
Cummulative ₹ 188.56Lacs ( against 346.77Lacs )

a month ago

on Sunday, July 13th 2025, 6:30:00 pm
74.01%
Financial Progress

2nd Expenditure
of ₹ 6809524 (68.10 Lacs ) done.
Cummulative ₹ 256.66Lacs ( against 346.77Lacs )