19 years ago

on Tuesday, November 21st 2006, 6:30:00 pm
Work Sanctioned
जनपद बागेश्वर में जल्थाकोट चमडथल-किमोली मोटर मार्ग का निर्माण।

17 years ago

on Saturday, February 28th 2009, 6:30:00 pm
0.70%
Financial Progress

1st Expenditure
of ₹ 100000 (1.00 Lacs ) done.
Cummulative ₹ 1.00Lacs ( against 142Lacs )

14 years ago

on Sunday, July 31st 2011, 6:30:00 pm
0.84%
Financial Progress

2nd Expenditure
of ₹ 18620 (0.19 Lacs ) done.
Cummulative ₹ 1.19Lacs ( against 142Lacs )

5 years ago

on Sunday, February 28th 2021, 6:30:00 pm
1.50%
Financial Progress

3rd Expenditure
of ₹ 93810 (0.94 Lacs ) done.
Cummulative ₹ 2.12Lacs ( against 142Lacs )

4 years ago

on Monday, April 19th 2021, 9:56:59 am

Technical Sanction
of ₹ 142 Lacs

1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. SE Alm latter no 1508/3C-01/2021

4 years ago

on Tuesday, June 29th 2021, 6:30:00 pm
30.70%
Financial Progress

4th Expenditure
of ₹ 4147211 (41.47 Lacs ) done.
Cummulative ₹ 43.60Lacs ( against 142Lacs )

3 years ago

on Monday, June 27th 2022, 6:30:00 pm
5%

Physical Progress
Physical Progress Reported at 1st time

3 years ago

on Monday, December 19th 2022, 6:30:00 pm
15%

Physical Progress
Physical Progress Reported at 2nd time

3 years ago

on Tuesday, January 3rd 2023, 6:30:00 pm
20%

Physical Progress
Physical Progress Reported at 3rd time

3 years ago

on Monday, January 30th 2023, 6:30:00 pm
33.96%
Financial Progress

5th Expenditure
of ₹ 462408 (4.62 Lacs ) done.
Cummulative ₹ 48.22Lacs ( against 142Lacs )

2 years ago

on Monday, March 27th 2023, 6:30:00 pm
45.06%
Financial Progress

6th Expenditure
of ₹ 1577108 (15.77 Lacs ) done.
Cummulative ₹ 63.99Lacs ( against 142Lacs )

2 years ago

on Saturday, April 15th 2023, 6:30:00 pm
30%

Physical Progress
Physical Progress Reported at 4th time

2 years ago

on Thursday, July 27th 2023, 6:30:00 pm
58.63%
Financial Progress

7th Expenditure
of ₹ 1926593 (19.27 Lacs ) done.
Cummulative ₹ 83.26Lacs ( against 142Lacs )

2 years ago

on Sunday, August 27th 2023, 6:30:00 pm
60.01%
Financial Progress

8th Expenditure
of ₹ 196186 (1.96 Lacs ) done.
Cummulative ₹ 85.22Lacs ( against 142Lacs )

2 years ago

on Sunday, September 24th 2023, 6:30:00 pm
63.66%
Financial Progress

9th Expenditure
of ₹ 517589 (5.18 Lacs ) done.
Cummulative ₹ 90.40Lacs ( against 142Lacs )

2 years ago

on Thursday, November 23rd 2023, 6:30:00 pm
65.21%
Financial Progress

10th Expenditure
of ₹ 220445 (2.20 Lacs ) done.
Cummulative ₹ 92.60Lacs ( against 142Lacs )

2 years ago

on Tuesday, December 26th 2023, 6:30:00 pm
66.47%
Financial Progress

11th Expenditure
of ₹ 178532 (1.79 Lacs ) done.
Cummulative ₹ 94.39Lacs ( against 142Lacs )

2 years ago

on Monday, January 22nd 2024, 6:30:00 pm
74.13%
Financial Progress

12th Expenditure
of ₹ 1087416 (10.87 Lacs ) done.
Cummulative ₹ 105.26Lacs ( against 142Lacs )

a year ago

on Sunday, March 24th 2024, 6:30:00 pm
74.29%
Financial Progress

13th Expenditure
of ₹ 23890 (0.24 Lacs ) done.
Cummulative ₹ 105.50Lacs ( against 142Lacs )

a year ago

on Monday, April 1st 2024, 6:30:00 pm
45%

Physical Progress
Physical Progress Reported at 5th time

a year ago

on Friday, May 24th 2024, 6:30:00 pm
75.85%
Financial Progress

14th Expenditure
of ₹ 220896 (2.21 Lacs ) done.
Cummulative ₹ 107.71Lacs ( against 142Lacs )

a year ago

on Sunday, May 26th 2024, 6:30:00 pm
79.29%
Financial Progress

15th Expenditure
of ₹ 489101 (4.89 Lacs ) done.
Cummulative ₹ 112.60Lacs ( against 142Lacs )

9 months ago

on Saturday, November 30th 2024, 6:30:00 pm
55%

Physical Progress
Physical Progress Reported at 6th time

6 months ago

on Thursday, February 20th 2025, 6:30:00 pm
79.34%
Financial Progress

16th Expenditure
of ₹ 7137 (0.07 Lacs ) done.
Cummulative ₹ 112.67Lacs ( against 142Lacs )

5 months ago

on Thursday, March 20th 2025, 6:30:00 pm
79.47%
Financial Progress

17th Expenditure
of ₹ 17837 (0.18 Lacs ) done.
Cummulative ₹ 112.85Lacs ( against 142Lacs )

3 months ago

on Sunday, May 25th 2025, 6:30:00 pm
79.86%
Financial Progress

18th Expenditure
of ₹ 55039 (0.55 Lacs ) done.
Cummulative ₹ 113.40Lacs ( against 142Lacs )