@
Refresh data
Refresh data

7 years ago

on Sunday, February 10th 2019, 6:30:00 pm
Work Sanctioned
राज्य योजना के अन्तर्गत जनपद बागेश्वर के विधानसभा क्षेत्र-बागेश्वर के अन्तर्गत पगना से शक्तेश्वर तक मोटर मार्ग में डामरीकरण का कार्य।

6 years ago

on Thursday, February 28th 2019, 6:30:00 pm
0.09%
Financial Progress

1st Expenditure
of ₹ 9880 (0.10 Lacs ) done.
Cummulative ₹ 0.10Lacs ( against 106.12Lacs )

4 years ago

on Thursday, August 19th 2021, 5:47:07 am

Technical Sanction
of ₹ 106.12 Lacs

1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. 5080/247C-01/2021-22

4 years ago

on Sunday, January 30th 2022, 6:30:00 pm
4.41%
Financial Progress

2nd Expenditure
of ₹ 457820 (4.58 Lacs ) done.
Cummulative ₹ 4.68Lacs ( against 106.12Lacs )

3 years ago

on Friday, March 4th 2022, 6:00:15 am
<span class="4">Picture Id:4706</span>
PWD Uttarakahnd
Photo (ID 4706) from Site Received
Uploader : Lalit Singh Seradi, Junior Engineer Civil ,CD Ranikhet
Landmark : Km 2 hm 8-10
Remark : W.b.m G1 stacking stone ballast.

3 years ago

on Saturday, March 26th 2022, 5:45:24 am
<span class="4">Picture Id:5025</span>
PWD Uttarakahnd
Photo (ID 5025) from Site Received
Uploader : Lalit Singh Seradi, Junior Engineer Civil ,CD Ranikhet
Landmark : Chainage 1/4
Remark : R.c.c scupper work.

3 years ago

on Saturday, March 26th 2022, 6:10:23 am
<span class="4">Picture Id:5026</span>
PWD Uttarakahnd
Photo (ID 5026) from Site Received
Uploader : Lalit Singh Seradi, Junior Engineer Civil ,CD Ranikhet
Landmark : 1/15
Remark : Wbm g-2 work in progress.

3 years ago

on Wednesday, March 30th 2022, 6:30:00 pm
4.87%
Financial Progress

3rd Expenditure
of ₹ 48930 (0.49 Lacs ) done.
Cummulative ₹ 5.17Lacs ( against 106.12Lacs )

3 years ago

on Tuesday, May 31st 2022, 6:30:00 pm
6.15%
Financial Progress

4th Expenditure
of ₹ 135660 (1.36 Lacs ) done.
Cummulative ₹ 6.52Lacs ( against 106.12Lacs )

3 years ago

on Monday, June 27th 2022, 6:30:00 pm
25%

Physical Progress
Physical Progress Reported at 1st time

3 years ago

on Sunday, October 30th 2022, 6:30:00 pm
34.06%
Financial Progress

5th Expenditure
of ₹ 2961733 (29.62 Lacs ) done.
Cummulative ₹ 36.14Lacs ( against 106.12Lacs )

3 years ago

on Friday, December 23rd 2022, 6:30:00 pm
40%

Physical Progress
Physical Progress Reported at 2nd time

3 years ago

on Monday, January 30th 2023, 6:30:00 pm
47.35%
Financial Progress

6th Expenditure
of ₹ 1410242 (14.10 Lacs ) done.
Cummulative ₹ 50.24Lacs ( against 106.12Lacs )

2 years ago

on Thursday, March 2nd 2023, 5:30:32 am
<span class="4">Picture Id:17562</span>
PWD Uttarakahnd
Photo (ID 17562) from Site Received
Uploader : Kailash Chandra Arya, Assistant Engineer Civil ,CD Lohaghat
Landmark : 0/39
Remark : Collection of top coat (G3)

2 years ago

on Monday, March 27th 2023, 6:30:00 pm
70.23%
Financial Progress

7th Expenditure
of ₹ 2428688 (24.29 Lacs ) done.
Cummulative ₹ 74.53Lacs ( against 106.12Lacs )

2 years ago

on Friday, June 2nd 2023, 6:30:00 pm
50%

Physical Progress
Physical Progress Reported at 3rd time

2 years ago

on Friday, June 23rd 2023, 6:30:00 pm
80%

Physical Progress
Physical Progress Reported at 4th time

2 years ago

on Thursday, July 27th 2023, 6:30:00 pm
99.55%
Financial Progress

8th Expenditure
of ₹ 3110950 (31.11 Lacs ) done.
Cummulative ₹ 105.64Lacs ( against 106.12Lacs )

AI layer

AI Road
AI Bridge
10000 km
5000 mi
Unavailable
refresh data by PWD Uttarakhand Engineeres | View code by HandsOnDataViz with Leaflet | © OpenStreetMap contributors