on Tuesday, February 11th 2020, 6:30:00 pm
Work Sanctioned
राष्ट्रीय मार्ग सं0-121 (नया 309) रामनगर-बुआखाल मोटर रोड के कि0मी0 44 (पनोद नाला) पर 90 मीटर स्पान के पी0एस0सी0 ब्रिज का निर्माण कार्य।
on Wednesday, February 12th 2020, 6:07:10 am
Technical Sanction
of ₹ 829.23 Lacs
1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. Ro/uk/12014/89/annual plan/2019-20
on Friday, January 29th 2021, 6:30:00 pm
4.00%
Financial Progress
1st Expenditure
of ₹ 3317143 (33.17 Lacs ) done.
Cummulative ₹ 33.17Lacs ( against 829.23Lacs )
on Friday, July 16th 2021, 6:30:00 pm
10%
Physical Progress
Physical Progress Reported at 1st time
on Sunday, August 8th 2021, 7:45:47 am
PWD UttarakahndPhoto (ID 522) from Site Received
Uploader : Anil Kumar Pangty, Superintending Engineer Civil ,NH Circle Haldwani
Landmark : Panod
Remark : Well
on Sunday, August 8th 2021, 7:54:44 am
PWD UttarakahndPhoto (ID 523) from Site Received
Uploader : Anil Kumar Pangty, Superintending Engineer Civil ,NH Circle Haldwani
Landmark : Panod
Remark : Panod
on Thursday, August 19th 2021, 8:56:27 am
PWD UttarakahndPhoto (ID 1002) from Site Received
Uploader : Chetan Rawal, Additional Assistant Engineer Civil ,PD Ranikhet
Landmark : Km 44 ch.43.920 panod bridge
Remark : Concrete on well curb at Panod bridge A-2 , of M30 grade
(Name of work -Construction of 90 m span PSC box girder bridge over panot stream NH-121 (new NH-309) Ramnagar to Buwakhal motor road ),
And gave instruction to contracor for proper vibration for better finishing.
on Monday, August 30th 2021, 6:20:42 am
PWD UttarakahndPhoto (ID 1135) from Site Received
Uploader : Chetan Rawal, Additional Assistant Engineer Civil ,PD Ranikhet
Landmark : Km 44 ch. 43.720 of NH-309(old NH-121)
Remark : Concrete on third lift Panod bridge Abutment A-1 , of M35 grade
(Name of work -Construction of 90 m span PSC box girder bridge over panot stream NH-121 (new NH-309) Ramnagar to Buwakhal motor road ),
And gave instruction to contracor for proper vibration for better finishing
on Thursday, September 2nd 2021, 6:19:43 am
PWD UttarakahndPhoto (ID 1191) from Site Received
Uploader : Chetan Rawal, Additional Assistant Engineer Civil ,PD Ranikhet
Landmark : Km 44 ch 43.820
Remark : Concrete on second lift Panod bridge Abutment A-2 , of M35 grade
(Name of work -Construction of 90 m span PSC box girder bridge over panot stream NH-121 (new NH-309) Ramnagar to Buwakhal motor road ),
And gave instruction to contracor for proper vibration for better finishing
on Friday, September 3rd 2021, 6:30:00 pm
12%
Physical Progress
Physical Progress Reported at 2nd time
on Monday, September 6th 2021, 5:53:13 am
PWD UttarakahndPhoto (ID 1267) from Site Received
Uploader : Chetan Rawal, Additional Assistant Engineer Civil ,PD Ranikhet
Landmark : Km 44 ch 43.730
Remark : Concrete on fourth lift Panod bridge Abutment A-1 , of M35 grade
(Name of work -Construction of 90 m span PSC box girder bridge over panot stream NH-121 (new NH-309) Ramnagar to Buwakhal motor road ),
And gave instruction to contracor for proper vibration for better finishing.
on Friday, September 10th 2021, 5:01:21 am
PWD UttarakahndPhoto (ID 1344) from Site Received
Uploader : Chetan Rawal, Additional Assistant Engineer Civil ,PD Ranikhet
Landmark : Km 44 ch. 43.820
Remark : Concrete on second lift Panod bridge Abutment A-2 , of M35 grade
(Name of work -Construction of 90 m span PSC box girder bridge over panot stream NH-121 (new NH-309) Ramnagar to Buwakhal motor road ),
And gave instruction to contracor for proper vibration for better finishing
on Saturday, September 25th 2021, 5:02:57 am
PWD UttarakahndPhoto (ID 1624) from Site Received
Uploader : Chetan Rawal, Additional Assistant Engineer Civil ,PD Ranikhet
Landmark : KM 44 Ch. 43.765
Remark : Concrete on well curb on Panod bridge Pier , of M30 grade
(Name of work -Construction of 90 m span PSC box girder bridge over panot stream NH-121 (new NH-309) Ramnagar to Buwakhal motor road ),
And gave instruction to contracor for proper vibration for better finishing
on Sunday, October 3rd 2021, 6:30:00 pm
14%
Physical Progress
Physical Progress Reported at 3rd time
on Friday, October 8th 2021, 8:45:23 am
PWD UttarakahndPhoto (ID 2298) from Site Received
Uploader : Sunil Kumar, Executive Engineer Civil ,NHAI New Delhi
Landmark : Bridge at km 44 on NH 121
Remark : Inspection of panod bridge.P1 well stening is in progress
on Thursday, October 14th 2021, 1:26:51 pm
PWD UttarakahndPhoto (ID 2725) from Site Received
Uploader : Qamar Alam, Additional Assistant Engineer Civil ,NH Div Dhumakot
Landmark : Km 44 of NH 121(309)
Remark : M35 concrete stenining 2 lift of Pier continue.
on Thursday, October 28th 2021, 6:12:33 am
PWD UttarakahndPhoto (ID 2911) from Site Received
Uploader : Chetan Rawal, Additional Assistant Engineer Civil ,PD Ranikhet
Landmark : KM 44 ch. 43.180
Remark : Bottom plug With M25 concrete on A1 of Km 44 panod bridge
on Saturday, November 20th 2021, 7:46:05 am
PWD UttarakahndPhoto (ID 3536) from Site Received
Uploader : Qamar Alam, Additional Assistant Engineer Civil ,NH Div Dhumakot
Landmark : Km 44 of NH 121 (309)
Remark : M 35 concrete Pier Stenining concrete continue
on Saturday, November 27th 2021, 4:21:59 am
PWD UttarakahndPhoto (ID 3608) from Site Received
Uploader : Chetan Rawal, Additional Assistant Engineer Civil ,PD Ranikhet
Landmark : Km 44 ch 43.775
Remark : Concrete on forth lift Panod bridge Pier P-1 , of M35 grade
(Name of work -Construction of 90 m span PSC box girder bridge over panot stream NH-121 (new NH-309) Ramnagar to Buwakhal motor road ),
And gave instruction to contracor for proper vibration for better finishing