8 years ago

on Tuesday, August 22nd 2017, 6:30:00 pm
Work Sanctioned
राष्ट्रीय राजमार्ग संख्या -119 (534) के कि०मी० 139 से 196 में 4 लघु सेतुओं का निर्माण कार्य

8 years ago

on Wednesday, August 23rd 2017, 5:52:13 am

Technical Sanction
of ₹ 1530.16 Lacs

1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. एन० एच० 12014 /24/2017/यू० आर०/एन०एच० -02

7 years ago

on Tuesday, April 17th 2018, 6:30:00 pm
4.30%
Financial Progress

1st Expenditure
of ₹ 6572319 (65.72 Lacs ) done.
Cummulative ₹ 65.72Lacs ( against 1530.16Lacs )

6 years ago

on Sunday, January 6th 2019, 6:30:00 pm
10.15%
Financial Progress

2nd Expenditure
of ₹ 8951392 (89.51 Lacs ) done.
Cummulative ₹ 155.24Lacs ( against 1530.16Lacs )

6 years ago

on Thursday, April 4th 2019, 6:30:00 pm
15.26%
Financial Progress

3rd Expenditure
of ₹ 7819381 (78.19 Lacs ) done.
Cummulative ₹ 233.43Lacs ( against 1530.16Lacs )

6 years ago

on Wednesday, July 24th 2019, 6:30:00 pm
20.08%
Financial Progress

4th Expenditure
of ₹ 7376798 (73.77 Lacs ) done.
Cummulative ₹ 307.20Lacs ( against 1530.16Lacs )

6 years ago

on Tuesday, July 30th 2019, 6:30:00 pm
21.92%
Financial Progress

5th Expenditure
of ₹ 2825588 (28.26 Lacs ) done.
Cummulative ₹ 335.45Lacs ( against 1530.16Lacs )

5 years ago

on Thursday, September 19th 2019, 6:30:00 pm
27.12%
Financial Progress

6th Expenditure
of ₹ 7949685 (79.50 Lacs ) done.
Cummulative ₹ 414.95Lacs ( against 1530.16Lacs )

5 years ago

on Sunday, October 20th 2019, 6:30:00 pm
31.27%
Financial Progress

7th Expenditure
of ₹ 6354429 (63.54 Lacs ) done.
Cummulative ₹ 478.50Lacs ( against 1530.16Lacs )

5 years ago

on Tuesday, January 7th 2020, 6:30:00 pm
33.17%
Financial Progress

8th Expenditure
of ₹ 2908011 (29.08 Lacs ) done.
Cummulative ₹ 507.58Lacs ( against 1530.16Lacs )

5 years ago

on Tuesday, January 14th 2020, 6:30:00 pm
45.32%
Financial Progress

9th Expenditure
of ₹ 18584588 (185.85 Lacs ) done.
Cummulative ₹ 693.42Lacs ( against 1530.16Lacs )

5 years ago

on Wednesday, April 15th 2020, 6:30:00 pm
54.71%
Financial Progress

10th Expenditure
of ₹ 14374510 (143.75 Lacs ) done.
Cummulative ₹ 837.17Lacs ( against 1530.16Lacs )

4 years ago

on Sunday, October 4th 2020, 6:30:00 pm
55.36%
Financial Progress

11th Expenditure
of ₹ 993394 (9.93 Lacs ) done.
Cummulative ₹ 847.10Lacs ( against 1530.16Lacs )

4 years ago

on Tuesday, November 10th 2020, 6:30:00 pm
55.36%
Financial Progress

12th Expenditure
of ₹ 1416 (0.01 Lacs ) done.
Cummulative ₹ 847.12Lacs ( against 1530.16Lacs )

4 years ago

on Tuesday, November 10th 2020, 6:30:00 pm
55.38%
Financial Progress

13th Expenditure
of ₹ 23482 (0.23 Lacs ) done.
Cummulative ₹ 847.35Lacs ( against 1530.16Lacs )

4 years ago

on Tuesday, November 10th 2020, 6:30:00 pm
55.38%
Financial Progress

14th Expenditure
of ₹ 4856 (0.05 Lacs ) done.
Cummulative ₹ 847.40Lacs ( against 1530.16Lacs )

4 years ago

on Thursday, March 18th 2021, 6:30:00 pm
58.99%
Financial Progress

15th Expenditure
of ₹ 5521028 (55.21 Lacs ) done.
Cummulative ₹ 902.61Lacs ( against 1530.16Lacs )

4 years ago

on Thursday, July 15th 2021, 11:47:04 pm
<span class="4">Picture Id:351</span>
PWD Uttarakahnd
Photo (ID 351) from Site Received
Uploader : Ashish Sani, Junior Engineer Civil ,NH Div Dhumakot
Landmark : 156.610
Remark : CH 156.610 on NH 534(119) Bridge no. 2 is ready to traffic

4 years ago

on Friday, July 16th 2021, 12:32:29 am
<span class="4">Picture Id:353</span>
PWD Uttarakahnd
Photo (ID 353) from Site Received
Uploader : Ashish Sani, Junior Engineer Civil ,NH Div Dhumakot
Landmark : 178.070
Remark : CH -178. 070 on NH 534(119) Bridge no. 3 is ready to traffic

4 years ago

on Friday, July 16th 2021, 12:39:58 am
<span class="4">Picture Id:352</span>
PWD Uttarakahnd
Photo (ID 352) from Site Received
Uploader : Ashish Sani, Junior Engineer Civil ,NH Div Dhumakot
Landmark : 180.580
Remark : CH -180. 580 on NH 534(119) Bridge No. 4 is ready to traffic

4 years ago

on Monday, July 26th 2021, 6:30:00 pm
75%

Physical Progress
Physical Progress Reported at 1st time

4 years ago

on Wednesday, September 1st 2021, 6:30:00 pm
62.99%
Financial Progress

16th Expenditure
of ₹ 6126104 (61.26 Lacs ) done.
Cummulative ₹ 963.87Lacs ( against 1530.16Lacs )

a year ago

on Tuesday, April 2nd 2024, 6:30:00 pm
100%

Physical Progress
Physical Progress Reported at 2nd time