9 years ago

on Sunday, June 26th 2016, 6:30:00 pm
Work Sanctioned
बडखोलू-साकणीखेत-रौतेला-काण्डा-बौसाल मोटर मार्ग का नव निर्माण कार्य।

8 years ago

on Tuesday, February 28th 2017, 6:30:00 pm
0.71%
Financial Progress

1st Expenditure
of ₹ 200000 (2.00 Lacs ) done.
Cummulative ₹ 2.00Lacs ( against 280.68Lacs )

7 years ago

on Wednesday, January 31st 2018, 6:30:00 pm
1.75%
Financial Progress

2nd Expenditure
of ₹ 291372 (2.91 Lacs ) done.
Cummulative ₹ 4.91Lacs ( against 280.68Lacs )

7 years ago

on Wednesday, February 28th 2018, 6:30:00 pm
2.15%
Financial Progress

3rd Expenditure
of ₹ 112796 (1.13 Lacs ) done.
Cummulative ₹ 6.04Lacs ( against 280.68Lacs )

7 years ago

on Monday, April 30th 2018, 6:30:00 pm
6.83%
Financial Progress

4th Expenditure
of ₹ 1313319 (13.13 Lacs ) done.
Cummulative ₹ 19.17Lacs ( against 280.68Lacs )

6 years ago

on Monday, December 31st 2018, 6:30:00 pm
7.97%
Financial Progress

5th Expenditure
of ₹ 319200 (3.19 Lacs ) done.
Cummulative ₹ 22.37Lacs ( against 280.68Lacs )

5 years ago

on Monday, June 29th 2020, 6:30:00 pm

Technical Sanction
of ₹ 280.68 Lacs

1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. Ts vide CE letter no 43/12(273)yata-pauri/2020-21 dt. 30-06-2020

5 years ago

on Saturday, October 31st 2020, 6:30:00 pm
8.04%
Financial Progress

6th Expenditure
of ₹ 18960 (0.19 Lacs ) done.
Cummulative ₹ 22.56Lacs ( against 280.68Lacs )

4 years ago

on Thursday, December 31st 2020, 6:30:00 pm
24.15%
Financial Progress

7th Expenditure
of ₹ 4523367 (45.23 Lacs ) done.
Cummulative ₹ 67.79Lacs ( against 280.68Lacs )

4 years ago

on Sunday, February 28th 2021, 6:30:00 pm
43.44%
Financial Progress

8th Expenditure
of ₹ 5414264 (54.14 Lacs ) done.
Cummulative ₹ 121.93Lacs ( against 280.68Lacs )

4 years ago

on Monday, May 31st 2021, 6:30:00 pm
52.36%
Financial Progress

9th Expenditure
of ₹ 2503435 (25.03 Lacs ) done.
Cummulative ₹ 146.97Lacs ( against 280.68Lacs )

4 years ago

on Friday, July 30th 2021, 6:30:00 pm
55.12%
Financial Progress

10th Expenditure
of ₹ 775746 (7.76 Lacs ) done.
Cummulative ₹ 154.72Lacs ( against 280.68Lacs )

4 years ago

on Monday, August 30th 2021, 6:30:00 pm
56.38%
Financial Progress

11th Expenditure
of ₹ 353302 (3.53 Lacs ) done.
Cummulative ₹ 158.26Lacs ( against 280.68Lacs )

4 years ago

on Wednesday, September 29th 2021, 6:30:00 pm
58.25%
Financial Progress

12th Expenditure
of ₹ 523061 (5.23 Lacs ) done.
Cummulative ₹ 163.49Lacs ( against 280.68Lacs )

4 years ago

on Saturday, October 30th 2021, 6:30:00 pm
65.07%
Financial Progress

13th Expenditure
of ₹ 1915726 (19.16 Lacs ) done.
Cummulative ₹ 182.65Lacs ( against 280.68Lacs )

3 years ago

on Monday, November 29th 2021, 6:30:00 pm
65.09%
Financial Progress

14th Expenditure
of ₹ 5941 (0.06 Lacs ) done.
Cummulative ₹ 182.70Lacs ( against 280.68Lacs )

3 years ago

on Thursday, December 30th 2021, 6:30:00 pm
65.32%
Financial Progress

15th Expenditure
of ₹ 62945 (0.63 Lacs ) done.
Cummulative ₹ 183.33Lacs ( against 280.68Lacs )

3 years ago

on Sunday, February 27th 2022, 6:30:00 pm
65.33%
Financial Progress

16th Expenditure
of ₹ 2060 (0.02 Lacs ) done.
Cummulative ₹ 183.35Lacs ( against 280.68Lacs )

3 years ago

on Wednesday, March 30th 2022, 6:30:00 pm
72.24%
Financial Progress

17th Expenditure
of ₹ 1940544 (19.41 Lacs ) done.
Cummulative ₹ 202.76Lacs ( against 280.68Lacs )

3 years ago

on Wednesday, June 29th 2022, 6:30:00 pm
72.50%
Financial Progress

18th Expenditure
of ₹ 72870 (0.73 Lacs ) done.
Cummulative ₹ 203.49Lacs ( against 280.68Lacs )

3 years ago

on Sunday, October 30th 2022, 6:30:00 pm
73.18%
Financial Progress

19th Expenditure
of ₹ 191804 (1.92 Lacs ) done.
Cummulative ₹ 205.41Lacs ( against 280.68Lacs )

2 years ago

on Monday, January 30th 2023, 6:30:00 pm
75.68%
Financial Progress

20th Expenditure
of ₹ 702426 (7.02 Lacs ) done.
Cummulative ₹ 212.43Lacs ( against 280.68Lacs )

2 years ago

on Thursday, March 30th 2023, 6:30:00 pm
86.97%
Financial Progress

21st Expenditure
of ₹ 3166225 (31.66 Lacs ) done.
Cummulative ₹ 244.09Lacs ( against 280.68Lacs )

2 years ago

on Monday, October 30th 2023, 6:30:00 pm
86.99%
Financial Progress

22nd Expenditure
of ₹ 5951 (0.06 Lacs ) done.
Cummulative ₹ 244.15Lacs ( against 280.68Lacs )

a year ago

on Wednesday, November 29th 2023, 6:30:00 pm
90.21%
Financial Progress

23rd Expenditure
of ₹ 903720 (9.04 Lacs ) done.
Cummulative ₹ 253.19Lacs ( against 280.68Lacs )

a year ago

on Saturday, December 30th 2023, 6:30:00 pm
91.63%
Financial Progress

24th Expenditure
of ₹ 398737 (3.99 Lacs ) done.
Cummulative ₹ 257.18Lacs ( against 280.68Lacs )

a year ago

on Wednesday, January 3rd 2024, 6:30:00 pm
100%

Physical Progress
Physical Progress Reported at 1st time

a year ago

on Wednesday, February 28th 2024, 6:30:00 pm
94.67%
Financial Progress

25th Expenditure
of ₹ 854026 (8.54 Lacs ) done.
Cummulative ₹ 265.72Lacs ( against 280.68Lacs )

a year ago

on Saturday, March 30th 2024, 6:30:00 pm
97.45%
Financial Progress

26th Expenditure
of ₹ 780794 (7.81 Lacs ) done.
Cummulative ₹ 273.53Lacs ( against 280.68Lacs )

4 months ago

on Monday, January 20th 2025, 6:30:00 pm
97.57%
Financial Progress

27th Expenditure
of ₹ 33837 (0.34 Lacs ) done.
Cummulative ₹ 273.86Lacs ( against 280.68Lacs )