9 years ago

on Thursday, December 15th 2016, 6:30:00 pm
Work Sanctioned
राष्ट्रीय सुरक्षा सलाहकार के गांव घिडी तक मोटर मार्ग का 0.500 कि0मी0 लम्बाई मंे नव निर्माण एंव 1.325 में पक्कीकरण/डामरीकरण का कार्य।

8 years ago

on Tuesday, February 28th 2017, 6:30:00 pm
0.09%
Financial Progress

1st Expenditure
of ₹ 10000 (0.10 Lacs ) done.
Cummulative ₹ 0.10Lacs ( against 111.87Lacs )

6 years ago

on Monday, March 4th 2019, 6:30:00 pm

Technical Sanction
of ₹ 111.87 Lacs

1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. TS vide SE letter no 972/1083yata&12/2018 dt 05-03-2019

6 years ago

on Saturday, August 31st 2019, 6:30:00 pm
1.14%
Financial Progress

2nd Expenditure
of ₹ 117250 (1.17 Lacs ) done.
Cummulative ₹ 1.27Lacs ( against 111.87Lacs )

6 years ago

on Thursday, October 31st 2019, 6:30:00 pm
1.81%
Financial Progress

3rd Expenditure
of ₹ 75114 (0.75 Lacs ) done.
Cummulative ₹ 2.02Lacs ( against 111.87Lacs )

5 years ago

on Sunday, May 31st 2020, 6:30:00 pm
1.90%
Financial Progress

4th Expenditure
of ₹ 9811 (0.10 Lacs ) done.
Cummulative ₹ 2.12Lacs ( against 111.87Lacs )

5 years ago

on Tuesday, June 30th 2020, 6:30:00 pm
2.10%
Financial Progress

5th Expenditure
of ₹ 22697 (0.23 Lacs ) done.
Cummulative ₹ 2.35Lacs ( against 111.87Lacs )

5 years ago

on Saturday, October 31st 2020, 6:30:00 pm
23.90%
Financial Progress

6th Expenditure
of ₹ 2439193 (24.39 Lacs ) done.
Cummulative ₹ 26.74Lacs ( against 111.87Lacs )

4 years ago

on Monday, November 29th 2021, 6:30:00 pm
31.04%
Financial Progress

7th Expenditure
of ₹ 798090 (7.98 Lacs ) done.
Cummulative ₹ 34.72Lacs ( against 111.87Lacs )

3 years ago

on Wednesday, March 30th 2022, 6:30:00 pm
42.24%
Financial Progress

8th Expenditure
of ₹ 1252806 (12.53 Lacs ) done.
Cummulative ₹ 47.25Lacs ( against 111.87Lacs )

3 years ago

on Monday, February 27th 2023, 6:30:00 pm
49.38%
Financial Progress

9th Expenditure
of ₹ 798834 (7.99 Lacs ) done.
Cummulative ₹ 55.24Lacs ( against 111.87Lacs )

2 years ago

on Sunday, April 16th 2023, 6:30:00 pm
80%

Physical Progress
Physical Progress Reported at 1st time

2 years ago

on Friday, September 29th 2023, 6:30:00 pm
78.93%
Financial Progress

10th Expenditure
of ₹ 3306336 (33.06 Lacs ) done.
Cummulative ₹ 88.30Lacs ( against 111.87Lacs )

2 years ago

on Sunday, February 18th 2024, 6:30:00 pm
81.72%
Financial Progress

11th Expenditure
of ₹ 311404 (3.11 Lacs ) done.
Cummulative ₹ 91.42Lacs ( against 111.87Lacs )

2 years ago

on Sunday, February 18th 2024, 6:30:00 pm
100%

Physical Progress
Physical Progress Reported at 2nd time

a year ago

on Saturday, March 30th 2024, 6:30:00 pm
92.53%
Financial Progress

12th Expenditure
of ₹ 1209971 (12.10 Lacs ) done.
Cummulative ₹ 103.52Lacs ( against 111.87Lacs )

a year ago

on Sunday, May 19th 2024, 6:30:00 pm
92.53%
Financial Progress

13th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 103.52Lacs ( against 111.87Lacs )

a year ago

on Monday, May 20th 2024, 6:30:00 pm
96.77%
Financial Progress

14th Expenditure
of ₹ 474456 (4.74 Lacs ) done.
Cummulative ₹ 108.26Lacs ( against 111.87Lacs )