Work Sanctioned
पीपलपानी से नौली धारकोट मोटर मार्ग के सुधारीकरण का कार्य।

2 years ago

on Thursday, October 5th 2023, 6:30:00 pm

Technical Sanction
of ₹ 160.48 Lacs

1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. 5968/1527yata-12/2023

2 years ago

on Tuesday, January 30th 2024, 6:30:00 pm
0.09%
Financial Progress

1st Expenditure
of ₹ 15227 (0.15 Lacs ) done.
Cummulative ₹ 0.15Lacs ( against 160.48Lacs )

2 years ago

on Sunday, February 4th 2024, 6:30:00 pm
5%

Physical Progress
Physical Progress Reported at 1st time

a year ago

on Saturday, March 30th 2024, 6:30:00 pm
12.40%
Financial Progress

2nd Expenditure
of ₹ 1974191 (19.74 Lacs ) done.
Cummulative ₹ 19.89Lacs ( against 160.48Lacs )

a year ago

on Friday, April 5th 2024, 6:30:00 pm
30%

Physical Progress
Physical Progress Reported at 2nd time

a year ago

on Sunday, May 19th 2024, 6:30:00 pm
12.40%
Financial Progress

3rd Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 19.89Lacs ( against 160.48Lacs )

a year ago

on Sunday, May 19th 2024, 6:30:00 pm
51.04%
Financial Progress

4th Expenditure
of ₹ 6201990 (62.02 Lacs ) done.
Cummulative ₹ 81.91Lacs ( against 160.48Lacs )

a year ago

on Sunday, May 19th 2024, 6:30:00 pm
70%

Physical Progress
Physical Progress Reported at 3rd time

a year ago

on Thursday, June 6th 2024, 6:30:00 pm
100%

Physical Progress
Physical Progress Reported at 4th time

a year ago

on Wednesday, June 26th 2024, 8:52:39 am
<span class="4">Picture Id:47035</span>
PWD Uttarakahnd
Photo (ID 47035) from Site Received
Uploader : Arvind Kumar Burman, Executive Engineer Civil ,Pauri Zone
Landmark : 9.100
Remark : P.c work satisfactory with drains

a year ago

on Wednesday, June 26th 2024, 8:58:22 am
<span class="4">Picture Id:47048</span>
PWD Uttarakahnd
Photo (ID 47048) from Site Received
Uploader : Arvind Kumar Burman, Executive Engineer Civil ,Pauri Zone
Landmark : 7.900
Remark : R.wall with Gabion and parapet completed

a year ago

on Friday, June 28th 2024, 6:30:00 pm
51.50%
Financial Progress

5th Expenditure
of ₹ 73750 (0.74 Lacs ) done.
Cummulative ₹ 82.65Lacs ( against 160.48Lacs )

a year ago

on Thursday, September 26th 2024, 6:30:00 pm
79.19%
Financial Progress

6th Expenditure
of ₹ 4443142 (44.43 Lacs ) done.
Cummulative ₹ 127.08Lacs ( against 160.48Lacs )

8 months ago

on Monday, December 16th 2024, 6:30:00 pm
79.47%
Financial Progress

7th Expenditure
of ₹ 44604 (0.45 Lacs ) done.
Cummulative ₹ 127.53Lacs ( against 160.48Lacs )

5 months ago

on Monday, March 17th 2025, 2:21:12 pm
<span class="4">Picture Id:65968</span>
PWD Uttarakahnd
Photo (ID 65968) from Site Received
Uploader : Mukesh Singh Parmar, Chief Engineer Level-II ,NH Zone
Landmark : At Thapli
Remark : PC is ok at starting pt.