Work Sanctioned
वित्तीय वर्ष 2022-23 में राज्य योजना के अन्तर्गत जनपद पौड़ी गढ़वाल के विधानसभा क्षेत्र श्रीनगर के विकास खण्ड खिर्सू में गजेली-सौड से खेडाखाल मोटर मार्ग को मंगलाकोटी तक विस्तार मार्ग में डामरीकरण एवं सुधारीकरण का कार्य। (गवाणा से कगडी मोटर मार्ग)
on Thursday, January 12th 2023, 6:35:15 am
Technical Sanction
of ₹ 116.35 Lacs
1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. SE Letter No. 324/1073 Yata-12/2022-23 Dated 12-01-2023
on Monday, June 5th 2023, 6:30:00 pm
55%
Physical Progress
Physical Progress Reported at 1st time
on Monday, July 3rd 2023, 6:30:00 pm
17.68%
Financial Progress
1st Expenditure
of ₹ 2156506 (21.57 Lacs ) done.
Cummulative ₹ 21.57Lacs ( against 121.94Lacs )
on Wednesday, October 4th 2023, 6:30:00 pm
34.09%
Financial Progress
2nd Expenditure
of ₹ 2000052 (20.00 Lacs ) done.
Cummulative ₹ 41.57Lacs ( against 121.94Lacs )
on Thursday, October 5th 2023, 6:30:00 pm
39%
Physical Progress
Physical Progress Reported at 2nd time
on Monday, January 1st 2024, 6:30:00 pm
34.42%
Financial Progress
3rd Expenditure
of ₹ 40600 (0.41 Lacs ) done.
Cummulative ₹ 41.97Lacs ( against 121.94Lacs )
on Friday, March 8th 2024, 6:30:00 pm
47.71%
Financial Progress
4th Expenditure
of ₹ 1620657 (16.21 Lacs ) done.
Cummulative ₹ 58.18Lacs ( against 121.94Lacs )
on Tuesday, March 19th 2024, 6:30:00 pm
54.59%
Financial Progress
5th Expenditure
of ₹ 838691 (8.39 Lacs ) done.
Cummulative ₹ 66.57Lacs ( against 121.94Lacs )
on Wednesday, June 5th 2024, 6:30:00 pm
54.89%
Financial Progress
6th Expenditure
of ₹ 36670 (0.37 Lacs ) done.
Cummulative ₹ 66.93Lacs ( against 121.94Lacs )
on Monday, June 24th 2024, 6:30:00 pm
76.50%
Financial Progress
7th Expenditure
of ₹ 2635102 (26.35 Lacs ) done.
Cummulative ₹ 93.28Lacs ( against 121.94Lacs )
on Sunday, June 30th 2024, 6:30:00 pm
85%
Physical Progress
Physical Progress Reported at 3rd time
on Friday, August 2nd 2024, 6:30:00 pm
100%
Physical Progress
Physical Progress Reported at 4th time
on Wednesday, October 2nd 2024, 6:30:00 pm
91.37%
Financial Progress
8th Expenditure
of ₹ 1813000 (18.13 Lacs ) done.
Cummulative ₹ 111.41Lacs ( against 121.94Lacs )
on Wednesday, November 13th 2024, 6:30:00 pm
91.56%
Financial Progress
9th Expenditure
of ₹ 23883 (0.24 Lacs ) done.
Cummulative ₹ 111.65Lacs ( against 121.94Lacs )
on Monday, January 13th 2025, 6:30:00 pm
91.82%
Financial Progress
10th Expenditure
of ₹ 31600 (0.32 Lacs ) done.
Cummulative ₹ 111.97Lacs ( against 121.94Lacs )
on Tuesday, February 25th 2025, 6:30:00 pm
92.72%
Financial Progress
11th Expenditure
of ₹ 109573 (1.10 Lacs ) done.
Cummulative ₹ 113.06Lacs ( against 121.94Lacs )