on Monday, July 17th 2023, 6:30:00 pm
Work Sanctioned
कपकोट क्षेत्र से कपकोट बैंड तक मो0मा0 में पक्की नाली, पी0सी0सी0 एवं इंटर लाॅकिंग टाईल द्वारा सुधारीकरण का कार्य।
on Thursday, February 1st 2024, 6:30:00 pm
5%
Physical Progress
Physical Progress Reported at 1st time
on Friday, February 16th 2024, 5:06:22 am
PWD UttarakahndPhoto (ID 35967) from Site Received
Uploader : Deepak Chandra Upreti, Additional Assistant Engineer Civil ,CD Kapkot
Landmark : Near Kapkot bend
Remark : Excavation work
on Saturday, February 24th 2024, 2:26:51 am
PWD UttarakahndPhoto (ID 36232) from Site Received
Uploader : Deepak Chandra Upreti, Additional Assistant Engineer Civil ,CD Kapkot
Landmark : Km1.00
Remark : GSB work
on Saturday, February 24th 2024, 2:27:46 am
PWD UttarakahndPhoto (ID 36233) from Site Received
Uploader : Deepak Chandra Upreti, Additional Assistant Engineer Civil ,CD Kapkot
Landmark : Km1.00
Remark : GSB work
on Saturday, February 24th 2024, 4:48:19 am
PWD UttarakahndPhoto (ID 36263) from Site Received
Uploader : Deepak Chandra Upreti, Additional Assistant Engineer Civil ,CD Kapkot
Landmark : Km1.00
Remark : PCC work for base
on Sunday, February 25th 2024, 11:06:26 pm
PWD UttarakahndPhoto (ID 36275) from Site Received
Uploader : Deepak Chandra Upreti, Additional Assistant Engineer Civil ,CD Kapkot
Landmark : Km 1.00
Remark : PCC work in Base
on Monday, March 4th 2024, 5:43:37 am
PWD UttarakahndPhoto (ID 36548) from Site Received
Uploader : Deepak Chandra Upreti, Additional Assistant Engineer Civil ,CD Kapkot
Landmark : Km 0.00
Remark : Tile laying in progress
on Tuesday, March 5th 2024, 6:18:16 am
PWD UttarakahndPhoto (ID 36571) from Site Received
Uploader : Deepak Chandra Upreti, Additional Assistant Engineer Civil ,CD Kapkot
Landmark : Km0.00
Remark : Tiling work in progress...
on Tuesday, March 5th 2024, 6:19:54 am
PWD UttarakahndPhoto (ID 36572) from Site Received
Uploader : Deepak Chandra Upreti, Additional Assistant Engineer Civil ,CD Kapkot
Landmark : Kmo.100
Remark : Tiling work in progress
on Wednesday, March 27th 2024, 6:30:00 pm
59.55%
Financial Progress
1st Expenditure
of ₹ 476373 (4.76 Lacs ) done.
Cummulative ₹ 4.76Lacs ( against 8Lacs )
on Wednesday, April 3rd 2024, 6:30:00 pm
100%
Physical Progress
Physical Progress Reported at 2nd time
on Wednesday, September 11th 2024, 6:30:00 pm
98.66%
Financial Progress
2nd Expenditure
of ₹ 312936 (3.13 Lacs ) done.
Cummulative ₹ 7.89Lacs ( against 8Lacs )