Work Sanctioned
सडक सुरक्षा के अंतर्गत विधानसभा क्षेत्र कपकोट में निर्माण खण्ड कपकोट के समस्त अन्य जिला मार्गों (बैडा पाखड दोफाड मो0मा0 में सड़क सुरक्षा का कार्य।
on Thursday, January 11th 2024, 6:30:00 pm
2%
Physical Progress
Physical Progress Reported at 1st time
on Saturday, January 20th 2024, 8:07:53 am
PWD UttarakahndPhoto (ID 35058) from Site Received
Uploader : Gayatri Arya, Additional Assistant Engineer Civil ,CD Almora
Landmark : Km2
Remark : Crush barier work progress
on Saturday, January 20th 2024, 9:14:18 am
PWD UttarakahndPhoto (ID 35062) from Site Received
Uploader : Gayatri Arya, Additional Assistant Engineer Civil ,CD Almora
Landmark : Km3
Remark : Km3
on Sunday, January 28th 2024, 6:51:04 am
PWD UttarakahndPhoto (ID 35312) from Site Received
Uploader : Gayatri Arya, Additional Assistant Engineer Civil ,CD Almora
Landmark : Km 2
Remark : Section 150x75x5 hence ok
on Tuesday, January 30th 2024, 6:30:00 pm
58.70%
Financial Progress
1st Expenditure
of ₹ 3540000 (35.40 Lacs ) done.
Cummulative ₹ 35.40Lacs ( against 60.31Lacs )
on Monday, February 5th 2024, 6:30:00 pm
25%
Physical Progress
Physical Progress Reported at 2nd time
on Sunday, February 11th 2024, 6:30:00 pm
45%
Physical Progress
Physical Progress Reported at 3rd time
on Tuesday, February 27th 2024, 6:30:00 pm
58.90%
Financial Progress
2nd Expenditure
of ₹ 12396 (0.12 Lacs ) done.
Cummulative ₹ 35.52Lacs ( against 60.31Lacs )
on Wednesday, May 1st 2024, 6:30:00 pm
60%
Physical Progress
Physical Progress Reported at 4th time
on Thursday, May 30th 2024, 6:30:00 pm
60.15%
Financial Progress
3rd Expenditure
of ₹ 75000 (0.75 Lacs ) done.
Cummulative ₹ 36.27Lacs ( against 60.31Lacs )
on Thursday, July 4th 2024, 6:30:00 pm
80%
Physical Progress
Physical Progress Reported at 5th time
on Friday, July 12th 2024, 6:30:00 pm
90%
Physical Progress
Physical Progress Reported at 6th time
on Wednesday, September 18th 2024, 6:30:00 pm
100%
Physical Progress
Physical Progress Reported at 7th time
on Tuesday, December 10th 2024, 6:30:00 pm
95.27%
Financial Progress
4th Expenditure
of ₹ 2118410 (21.18 Lacs ) done.
Cummulative ₹ 57.46Lacs ( against 60.31Lacs )
on Monday, December 30th 2024, 6:30:00 pm
95.27%
Financial Progress
5th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 57.46Lacs ( against 60.31Lacs )