Refresh data
on Monday, December 4th 2023, 6:30:00 pm
Work Sanctioned
सडक सुरक्षा के अंतर्गत विधानसभा क्षेत्र कपकोट के निर्माण खण्ड कपकोट में विभिन्न ग्रामीण मार्गों में दुर्घटना संभावित क्षेत्रों में क्रश बैरियर, डैलीनेटर, पैरापिट एवं साइन बोर्ड लगाए जाने का कार्य
on Tuesday, March 19th 2024, 6:30:00 pm
33.08%
Financial Progress
1st Expenditure
of ₹ 21775588 (217.76 Lacs ) done.
Cummulative ₹ 217.76Lacs ( against 658.22Lacs )
on Wednesday, March 20th 2024, 6:30:00 pm
10%
Physical Progress
Physical Progress Reported at 1st time
on Wednesday, May 1st 2024, 6:30:00 pm
20%
Physical Progress
Physical Progress Reported at 2nd time
on Tuesday, July 30th 2024, 4:34:16 am
PWD UttarakahndPhoto (ID 51363) from Site Received
Uploader : Deepak Chandra Upreti, Additional Assistant Engineer Civil ,CD Kapkot
Landmark : O
Remark : Parapet casting
on Tuesday, July 30th 2024, 4:47:18 am
PWD UttarakahndPhoto (ID 51364) from Site Received
Uploader : Deepak Chandra Upreti, Additional Assistant Engineer Civil ,CD Kapkot
Landmark : 2/15
Remark : Post punching
on Tuesday, July 30th 2024, 4:51:45 am
PWD UttarakahndPhoto (ID 51365) from Site Received
Uploader : Deepak Chandra Upreti, Additional Assistant Engineer Civil ,CD Kapkot
Landmark : 2/15
Remark : Thickness checking
on Tuesday, July 30th 2024, 4:54:35 am
PWD UttarakahndPhoto (ID 51366) from Site Received
Uploader : Deepak Chandra Upreti, Additional Assistant Engineer Civil ,CD Kapkot
Landmark : 2/15
Remark : Depth Checking
on Sunday, August 4th 2024, 12:29:42 pm
PWD UttarakahndPhoto (ID 51584) from Site Received
Uploader : Deepak Chandra Upreti, Additional Assistant Engineer Civil ,CD Kapkot
Landmark : 4/30
Remark : Road safety work in progress
on Sunday, August 4th 2024, 12:30:58 pm
PWD UttarakahndPhoto (ID 51585) from Site Received
Uploader : Deepak Chandra Upreti, Additional Assistant Engineer Civil ,CD Kapkot
Landmark : 4/10
Remark : Road safety work at dooni sukanda mr
on Sunday, August 4th 2024, 12:32:29 pm
PWD UttarakahndPhoto (ID 51586) from Site Received
Uploader : Deepak Chandra Upreti, Additional Assistant Engineer Civil ,CD Kapkot
Landmark : 3/10
Remark : Dooni sukanda mr crash barrier
on Wednesday, August 14th 2024, 6:30:50 am
PWD UttarakahndPhoto (ID 51897) from Site Received
Uploader : Suman Arya, JE Civil (Samvida) ,CD Kapkot
Landmark : Km.4 h 4-6
Remark : Road safety work in Kapkot Poling motor road
on Wednesday, August 14th 2024, 6:32:56 am
PWD UttarakahndPhoto (ID 51898) from Site Received
Uploader : Suman Arya, JE Civil (Samvida) ,CD Kapkot
Landmark : Km 4
Remark : Km.4 road safety work
on Saturday, August 24th 2024, 9:50:21 am
PWD UttarakahndPhoto (ID 52175) from Site Received
Uploader : Suman Arya, JE Civil (Samvida) ,CD Kapkot
Landmark : Km.7 h 8-10
Remark : Crush berrier work at bhayu guler motor road km.7
on Saturday, August 24th 2024, 9:58:05 am
PWD UttarakahndPhoto (ID 52176) from Site Received
Uploader : Suman Arya, JE Civil (Samvida) ,CD Kapkot
Landmark : Km.7 h (0-2
Remark : Crush berrier work at km.7
on Saturday, August 24th 2024, 10:03:22 am
PWD UttarakahndPhoto (ID 52177) from Site Received
Uploader : Suman Arya, JE Civil (Samvida) ,CD Kapkot
Landmark : Km. 6 h 8-10
Remark : Road safety work at Km.6 h 8-10 in bhayu guler motor road
on Thursday, September 5th 2024, 6:30:00 pm
30%
Physical Progress
Physical Progress Reported at 3rd time
on Wednesday, September 18th 2024, 5:52:01 am
PWD UttarakahndPhoto (ID 52938) from Site Received
Uploader : Deepak Chandra Upreti, Additional Assistant Engineer Civil ,CD Kapkot
Landmark : 0/5
Remark : Post size
on Thursday, September 19th 2024, 4:30:17 am
PWD UttarakahndPhoto (ID 52977) from Site Received
Uploader : Deepak Chandra Upreti, Additional Assistant Engineer Civil ,CD Kapkot
Landmark : 1/28
Remark : Dooni sukanda mr
on Thursday, September 19th 2024, 4:31:31 am
PWD UttarakahndPhoto (ID 52978) from Site Received
Uploader : Deepak Chandra Upreti, Additional Assistant Engineer Civil ,CD Kapkot
Landmark : 1/28
Remark : 1/28
on Thursday, September 19th 2024, 4:32:24 am
PWD UttarakahndPhoto (ID 52979) from Site Received
Uploader : Deepak Chandra Upreti, Additional Assistant Engineer Civil ,CD Kapkot
Landmark : 1/28
Remark : Dooni sukanda mr
on Thursday, September 19th 2024, 5:55:49 am
PWD UttarakahndPhoto (ID 52993) from Site Received
Uploader : Deepak Chandra Upreti, Additional Assistant Engineer Civil ,CD Kapkot
Landmark : Km 1 Hm 4-6
Remark : Pothing bhagwati mandir mr
on Thursday, September 19th 2024, 6:02:38 am
PWD UttarakahndPhoto (ID 52994) from Site Received
Uploader : Deepak Chandra Upreti, Additional Assistant Engineer Civil ,CD Kapkot
Landmark : 1/10
Remark : Pothing bhagwati mandir mr
on Thursday, September 19th 2024, 6:03:44 am
PWD UttarakahndPhoto (ID 52995) from Site Received
Uploader : Deepak Chandra Upreti, Additional Assistant Engineer Civil ,CD Kapkot
Landmark : 1/10
Remark : Pothing bhagwati mandir mr
on Friday, September 20th 2024, 9:28:42 am
PWD UttarakahndPhoto (ID 53080) from Site Received
Uploader : Santosh Kumar, Additional Assistant Engineer Civil ,CD Kapkot
Landmark : Km1(4-6)
Remark : Dhalan khunoli motor road work under road safety
on Tuesday, September 24th 2024, 9:22:36 am
PWD UttarakahndPhoto (ID 53247) from Site Received
Uploader : Santosh Kumar, Additional Assistant Engineer Civil ,CD Kapkot
Landmark : Ch 1.100
Remark : Dhalan khunoli motor road
on Saturday, September 28th 2024, 6:27:07 am
PWD UttarakahndPhoto (ID 53514) from Site Received
Uploader : Suman Arya, JE Civil (Samvida) ,CD Kapkot
Landmark : 0.400
Remark : Raod safety work at Harsila Nan Kanyalikot motor road 0.400
on Saturday, September 28th 2024, 6:29:22 am
PWD UttarakahndPhoto (ID 53515) from Site Received
Uploader : Suman Arya, JE Civil (Samvida) ,CD Kapkot
Landmark : 0.400
Remark : Road safety work at Harsila Nan Kanyalikot motor road 0.400
on Tuesday, October 22nd 2024, 6:30:00 pm
90%
Physical Progress
Physical Progress Reported at 4th time
on Sunday, October 27th 2024, 6:30:00 pm
33.15%
Financial Progress
2nd Expenditure
of ₹ 45867 (0.46 Lacs ) done.
Cummulative ₹ 218.21Lacs ( against 658.22Lacs )
on Sunday, October 27th 2024, 6:30:00 pm
33.16%
Financial Progress
3rd Expenditure
of ₹ 7167 (0.07 Lacs ) done.
Cummulative ₹ 218.29Lacs ( against 658.22Lacs )
on Sunday, October 27th 2024, 6:30:00 pm
33.80%
Financial Progress
4th Expenditure
of ₹ 419508 (4.20 Lacs ) done.
Cummulative ₹ 222.48Lacs ( against 658.22Lacs )
on Sunday, October 27th 2024, 6:30:00 pm
46.21%
Financial Progress
5th Expenditure
of ₹ 8165231 (81.65 Lacs ) done.
Cummulative ₹ 304.13Lacs ( against 658.22Lacs )
on Monday, December 30th 2024, 6:30:00 pm
46.21%
Financial Progress
6th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 304.13Lacs ( against 658.22Lacs )
on Saturday, January 4th 2025, 6:56:58 am
PWD UttarakahndPhoto (ID 62566) from Site Received
Uploader : Santosh Kumar, Additional Assistant Engineer Civil ,CD Kapkot
Landmark : Km2(0-2)
Remark : Road safety work at Ghinghartola devli v/r
on Saturday, January 4th 2025, 8:25:42 am
PWD UttarakahndPhoto (ID 62567) from Site Received
Uploader : Santosh Kumar, Additional Assistant Engineer Civil ,CD Kapkot
Landmark : Km 5(4-6)
Remark : Crush barrier work at Kamedidevi syacote v/r
on Sunday, January 19th 2025, 6:30:00 pm
64.13%
Financial Progress
7th Expenditure
of ₹ 11800000 (118.00 Lacs ) done.
Cummulative ₹ 422.13Lacs ( against 658.22Lacs )
on Tuesday, January 28th 2025, 6:30:00 pm
95%
Physical Progress
Physical Progress Reported at 5th time
on Sunday, March 23rd 2025, 6:30:00 pm
64.14%
Financial Progress
8th Expenditure
of ₹ 5000 (0.05 Lacs ) done.
Cummulative ₹ 422.18Lacs ( against 658.22Lacs )
on Sunday, June 8th 2025, 6:30:00 pm
100%
Physical Progress
Physical Progress Reported at 6th time
on Monday, June 16th 2025, 6:30:00 pm
70.52%
Financial Progress
9th Expenditure
of ₹ 4198069 (41.98 Lacs ) done.
Cummulative ₹ 464.16Lacs ( against 658.22Lacs )
on Sunday, July 13th 2025, 6:30:00 pm
85.04%
Financial Progress
10th Expenditure
of ₹ 9558000 (95.58 Lacs ) done.
Cummulative ₹ 559.74Lacs ( against 658.22Lacs )