Refresh data
on Sunday, May 30th 2021, 6:30:00 pm
Work Sanctioned
राज्य योजना के अन्तर्गत जनपद पौड़ी गढ़वाल के विधानसभा क्षेत्र लैन्सडौन के विकासखण्ड जयहरीखाल के अन्तर्गत पालकोट बरस्वार मोटर मार्ग से ग्राम जडियाना तक मोटर मार्ग का नव निर्माण। (प्रथम चरण)।
on Tuesday, November 30th 2021, 6:30:00 pm
0.22%
Financial Progress
1st Expenditure
of ₹ 7762 (0.08 Lacs ) done.
Cummulative ₹ 0.08Lacs ( against 34.55Lacs )
on Friday, April 1st 2022, 6:30:00 pm
0.22%
Financial Progress
2nd Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 0.08Lacs ( against 34.55Lacs )
on Tuesday, November 15th 2022, 6:30:00 pm
0.22%
Financial Progress
3rd Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 0.08Lacs ( against 34.55Lacs )
on Wednesday, May 10th 2023, 5:08:04 am
Technical Sanction
of ₹ 6.5 Lacs
1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. TS VIDE 18(TS)/16C dated 10-05-2023
on Friday, June 2nd 2023, 6:30:00 pm
10%
Physical Progress
Physical Progress Reported at 1st time
on Thursday, September 28th 2023, 6:30:00 pm
17.71%
Financial Progress
4th Expenditure
of ₹ 604057 (6.04 Lacs ) done.
Cummulative ₹ 6.12Lacs ( against 34.55Lacs )
on Tuesday, February 27th 2024, 6:30:00 pm
22.52%
Financial Progress
5th Expenditure
of ₹ 166118 (1.66 Lacs ) done.
Cummulative ₹ 7.78Lacs ( against 34.55Lacs )
on Wednesday, March 27th 2024, 6:30:00 pm
15%
Physical Progress
Physical Progress Reported at 2nd time
on Monday, July 22nd 2024, 6:30:00 pm
20%
Physical Progress
Physical Progress Reported at 3rd time
on Tuesday, February 25th 2025, 6:30:00 pm
22.66%
Financial Progress
6th Expenditure
of ₹ 5000 (0.05 Lacs ) done.
Cummulative ₹ 7.83Lacs ( against 34.55Lacs )