Refresh data
on Thursday, February 28th 2013, 6:30:00 pm
0.26%
Financial Progress
1st Expenditure
of ₹ 10000 (0.10 Lacs ) done.
Cummulative ₹ 0.10Lacs ( against 39.21Lacs )
on Sunday, March 3rd 2013, 6:30:00 pm
Work Sanctioned
जनपद पौड़़ी गढ़वाल में ग्राम क्यार कोे बड़ेथखाल -गूम-किन्सूर-बागी मोटर मार्ग का नवनिर्माण(3.00 किमी0 लम्बाई के मेाटर मार्ग किमी0 1.00 में 21 मी0 स्टील ब्रिज सहित)
on Wednesday, April 30th 2014, 6:30:00 pm
0.85%
Financial Progress
2nd Expenditure
of ₹ 23400 (0.23 Lacs ) done.
Cummulative ₹ 0.33Lacs ( against 39.21Lacs )
on Friday, October 31st 2014, 6:30:00 pm
0.92%
Financial Progress
3rd Expenditure
of ₹ 2500 (0.03 Lacs ) done.
Cummulative ₹ 0.36Lacs ( against 39.21Lacs )
on Saturday, January 31st 2015, 6:30:00 pm
1.23%
Financial Progress
4th Expenditure
of ₹ 12154 (0.12 Lacs ) done.
Cummulative ₹ 0.48Lacs ( against 39.21Lacs )
on Friday, November 24th 2017, 6:30:00 pm
Technical Sanction
of ₹ 14.12 Lacs
1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. 10/(T.S.)16C
on Thursday, May 31st 2018, 6:30:00 pm
4.84%
Financial Progress
5th Expenditure
of ₹ 141792 (1.42 Lacs ) done.
Cummulative ₹ 1.90Lacs ( against 39.21Lacs )
on Tuesday, April 4th 2023, 6:30:00 pm
10%
Physical Progress
Physical Progress Reported at 1st time
on Monday, July 22nd 2024, 6:30:00 pm
20%
Physical Progress
Physical Progress Reported at 2nd time
on Tuesday, October 22nd 2024, 6:30:00 pm
4.84%
Financial Progress
6th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 1.90Lacs ( against 39.21Lacs )
on Sunday, October 27th 2024, 6:30:00 pm
17.50%
Financial Progress
7th Expenditure
of ₹ 496302 (4.96 Lacs ) done.
Cummulative ₹ 6.86Lacs ( against 39.21Lacs )