Work Sanctioned
राज्य योजना के अन्तर्गत जनपद पौड़ी गढ़वाल के विधानसभा क्षेत्र यमकेश्वर के विकासखण्ड द्वारीखाल के अन्तर्गत सिलोगी -घनसाली मोटर मार्ग का किमी0 4 से 8 तक विस्तार कार्य हेतु (द्वितीय चरण)।
on Friday, January 31st 2020, 6:30:00 pm
1.26%
Financial Progress
1st Expenditure
of ₹ 375200 (3.75 Lacs ) done.
Cummulative ₹ 3.75Lacs ( against 296.67Lacs )
on Thursday, May 14th 2020, 6:30:00 pm
Technical Sanction
of ₹ 296.67 Lacs
1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. 901/12(453)Yata-Pauri/2020
on Sunday, May 31st 2020, 6:30:00 pm
1.43%
Financial Progress
2nd Expenditure
of ₹ 49640 (0.50 Lacs ) done.
Cummulative ₹ 4.25Lacs ( against 296.67Lacs )
on Friday, July 31st 2020, 6:30:00 pm
2.13%
Financial Progress
3rd Expenditure
of ₹ 207389 (2.07 Lacs ) done.
Cummulative ₹ 6.32Lacs ( against 296.67Lacs )
on Saturday, October 31st 2020, 6:30:00 pm
4.86%
Financial Progress
4th Expenditure
of ₹ 809337 (8.09 Lacs ) done.
Cummulative ₹ 14.42Lacs ( against 296.67Lacs )
on Thursday, December 31st 2020, 6:30:00 pm
7.00%
Financial Progress
5th Expenditure
of ₹ 634200 (6.34 Lacs ) done.
Cummulative ₹ 20.76Lacs ( against 296.67Lacs )
on Sunday, January 31st 2021, 6:30:00 pm
9.18%
Financial Progress
6th Expenditure
of ₹ 648532 (6.49 Lacs ) done.
Cummulative ₹ 27.24Lacs ( against 296.67Lacs )
on Sunday, February 28th 2021, 6:30:00 pm
14.62%
Financial Progress
7th Expenditure
of ₹ 1614233 (16.14 Lacs ) done.
Cummulative ₹ 43.39Lacs ( against 296.67Lacs )
on Tuesday, June 29th 2021, 6:30:00 pm
15.51%
Financial Progress
8th Expenditure
of ₹ 264000 (2.64 Lacs ) done.
Cummulative ₹ 46.03Lacs ( against 296.67Lacs )
on Wednesday, July 28th 2021, 6:30:00 pm
25%
Physical Progress
Physical Progress Reported at 1st time
on Friday, July 30th 2021, 6:30:00 pm
18.99%
Financial Progress
9th Expenditure
of ₹ 1030000 (10.30 Lacs ) done.
Cummulative ₹ 56.33Lacs ( against 296.67Lacs )
on Sunday, March 6th 2022, 6:50:10 am
PWD UttarakahndPhoto (ID 4730) from Site Received
Uploader : Vipin Dhuliya, Additional Assistant Engineer Civil ,PD Lansdown
Landmark : 3.400
Remark : Part 2 work
on Tuesday, March 8th 2022, 6:30:00 pm
21.71%
Financial Progress
10th Expenditure
of ₹ 809000 (8.09 Lacs ) done.
Cummulative ₹ 64.42Lacs ( against 296.67Lacs )
on Thursday, March 24th 2022, 6:30:00 pm
21.71%
Financial Progress
11th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 64.42Lacs ( against 296.67Lacs )
on Thursday, March 24th 2022, 6:30:00 pm
34.57%
Financial Progress
12th Expenditure
of ₹ 3814000 (38.14 Lacs ) done.
Cummulative ₹ 102.56Lacs ( against 296.67Lacs )
on Thursday, March 24th 2022, 6:30:00 pm
41.27%
Financial Progress
13th Expenditure
of ₹ 1989469 (19.89 Lacs ) done.
Cummulative ₹ 122.45Lacs ( against 296.67Lacs )
on Tuesday, July 12th 2022, 6:30:00 pm
43.68%
Financial Progress
14th Expenditure
of ₹ 713000 (7.13 Lacs ) done.
Cummulative ₹ 129.58Lacs ( against 296.67Lacs )
on Tuesday, July 19th 2022, 6:30:00 pm
40%
Physical Progress
Physical Progress Reported at 2nd time
on Tuesday, August 30th 2022, 6:30:00 pm
45.15%
Financial Progress
15th Expenditure
of ₹ 437000 (4.37 Lacs ) done.
Cummulative ₹ 133.95Lacs ( against 296.67Lacs )
on Tuesday, September 20th 2022, 6:30:00 pm
46.74%
Financial Progress
16th Expenditure
of ₹ 470000 (4.70 Lacs ) done.
Cummulative ₹ 138.65Lacs ( against 296.67Lacs )
on Wednesday, October 19th 2022, 6:30:00 pm
49.35%
Financial Progress
17th Expenditure
of ₹ 777000 (7.77 Lacs ) done.
Cummulative ₹ 146.42Lacs ( against 296.67Lacs )
on Tuesday, November 15th 2022, 6:30:00 pm
50.82%
Financial Progress
18th Expenditure
of ₹ 435056 (4.35 Lacs ) done.
Cummulative ₹ 150.77Lacs ( against 296.67Lacs )
on Friday, December 30th 2022, 6:30:00 pm
57.40%
Financial Progress
19th Expenditure
of ₹ 1952143 (19.52 Lacs ) done.
Cummulative ₹ 170.29Lacs ( against 296.67Lacs )
on Monday, January 30th 2023, 6:30:00 pm
60.97%
Financial Progress
20th Expenditure
of ₹ 1058952 (10.59 Lacs ) done.
Cummulative ₹ 180.88Lacs ( against 296.67Lacs )
on Friday, February 3rd 2023, 6:30:00 pm
60%
Physical Progress
Physical Progress Reported at 3rd time
on Monday, February 27th 2023, 6:30:00 pm
68.79%
Financial Progress
21st Expenditure
of ₹ 2319917 (23.20 Lacs ) done.
Cummulative ₹ 204.08Lacs ( against 296.67Lacs )
on Thursday, March 30th 2023, 6:30:00 pm
89.50%
Financial Progress
22nd Expenditure
of ₹ 6144378 (61.44 Lacs ) done.
Cummulative ₹ 265.52Lacs ( against 296.67Lacs )
on Tuesday, April 4th 2023, 6:30:00 pm
80%
Physical Progress
Physical Progress Reported at 4th time
on Saturday, July 29th 2023, 6:30:00 pm
89.51%
Financial Progress
23rd Expenditure
of ₹ 1274 (0.01 Lacs ) done.
Cummulative ₹ 265.54Lacs ( against 296.67Lacs )
on Friday, August 18th 2023, 6:30:00 pm
100%
Physical Progress
Physical Progress Reported at 5th time
on Tuesday, August 29th 2023, 6:30:00 pm
91.17%
Financial Progress
24th Expenditure
of ₹ 492907 (4.93 Lacs ) done.
Cummulative ₹ 270.47Lacs ( against 296.67Lacs )
on Thursday, September 28th 2023, 6:30:00 pm
92.05%
Financial Progress
25th Expenditure
of ₹ 261574 (2.62 Lacs ) done.
Cummulative ₹ 273.08Lacs ( against 296.67Lacs )
on Friday, November 3rd 2023, 6:30:00 pm
90%
Physical Progress
Physical Progress Reported at 6th time
on Thursday, December 28th 2023, 6:30:00 pm
94.23%
Financial Progress
26th Expenditure
of ₹ 646229 (6.46 Lacs ) done.
Cummulative ₹ 279.54Lacs ( against 296.67Lacs )
on Thursday, January 11th 2024, 6:30:00 pm
95%
Physical Progress
Physical Progress Reported at 7th time
on Tuesday, February 27th 2024, 6:30:00 pm
96.07%
Financial Progress
27th Expenditure
of ₹ 548067 (5.48 Lacs ) done.
Cummulative ₹ 285.02Lacs ( against 296.67Lacs )
on Sunday, March 17th 2024, 6:30:00 pm
97.40%
Financial Progress
28th Expenditure
of ₹ 392014 (3.92 Lacs ) done.
Cummulative ₹ 288.95Lacs ( against 296.67Lacs )
on Sunday, March 24th 2024, 6:30:00 pm
97.40%
Financial Progress
29th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 288.95Lacs ( against 296.67Lacs )
on Sunday, April 28th 2024, 6:30:00 pm
100%
Physical Progress
Physical Progress Reported at 8th time
on Wednesday, December 25th 2024, 6:30:00 pm
98.68%
Financial Progress
30th Expenditure
of ₹ 380282 (3.80 Lacs ) done.
Cummulative ₹ 292.75Lacs ( against 296.67Lacs )
on Tuesday, January 28th 2025, 6:30:00 pm
99.05%
Financial Progress
31st Expenditure
of ₹ 108897 (1.09 Lacs ) done.
Cummulative ₹ 293.84Lacs ( against 296.67Lacs )