on Thursday, September 2nd 2021, 6:30:00 pm
Work Sanctioned
मा0 मुख्यमंत्री घोषणा सं0 468/2020 के अन्तर्गत विधानसभा क्षेत्र यमकेष्वर के चैलूसैण-देवीखेत मोटर मार्ग के किमी0 6 से 10 के मध्य एस0डी0बी0सी0 एवं क्षतिग्रस्त दीवार एवं स्कपर का निर्माण कार्य
on Thursday, January 6th 2022, 9:20:13 am
Technical Sanction
of ₹ 112.19 Lacs
1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. TS VIDE 27(TS)/16C
on Sunday, March 13th 2022, 6:30:00 pm
17.85%
Financial Progress
1st Expenditure
of ₹ 2003000 (20.03 Lacs ) done.
Cummulative ₹ 20.03Lacs ( against 112.19Lacs )
on Thursday, March 24th 2022, 6:30:00 pm
18.39%
Financial Progress
2nd Expenditure
of ₹ 60000 (0.60 Lacs ) done.
Cummulative ₹ 20.63Lacs ( against 112.19Lacs )
on Saturday, April 9th 2022, 6:40:44 am
PWD UttarakahndPhoto (ID 5233) from Site Received
Uploader : Vipin Dhuliya, Additional Assistant Engineer Civil ,PD Lansdown
Landmark : 6.800
Remark : C/o parapet
on Monday, July 18th 2022, 6:30:00 pm
20%
Physical Progress
Physical Progress Reported at 1st time
on Tuesday, November 29th 2022, 6:30:00 pm
28.84%
Financial Progress
3rd Expenditure
of ₹ 1172000 (11.72 Lacs ) done.
Cummulative ₹ 32.35Lacs ( against 112.19Lacs )
on Monday, January 30th 2023, 6:30:00 pm
45.87%
Financial Progress
4th Expenditure
of ₹ 1911706 (19.12 Lacs ) done.
Cummulative ₹ 51.47Lacs ( against 112.19Lacs )
on Monday, January 29th 2024, 6:30:00 pm
46.19%
Financial Progress
5th Expenditure
of ₹ 35400 (0.35 Lacs ) done.
Cummulative ₹ 51.82Lacs ( against 112.19Lacs )
on Monday, March 25th 2024, 6:30:00 pm
88.16%
Financial Progress
6th Expenditure
of ₹ 4708200 (47.08 Lacs ) done.
Cummulative ₹ 98.90Lacs ( against 112.19Lacs )
on Wednesday, March 27th 2024, 6:30:00 pm
40%
Physical Progress
Physical Progress Reported at 2nd time
on Tuesday, May 7th 2024, 6:30:00 pm
90%
Physical Progress
Physical Progress Reported at 3rd time
on Tuesday, May 21st 2024, 6:30:00 pm
100%
Physical Progress
Physical Progress Reported at 4th time
on Sunday, March 23rd 2025, 6:30:00 pm
98.44%
Financial Progress
7th Expenditure
of ₹ 1153269 (11.53 Lacs ) done.
Cummulative ₹ 110.44Lacs ( against 112.19Lacs )