Work Sanctioned
राज्य योजना के अन्तर्गत जनपद पौड़ी गढ़वाल के विधानसभा क्षेत्र यमकेश्वर में गंगा नदी में कोटी माला के समीप डेढ़ लेन क्लास ‘ए‘ लोडिंग सेतु का नवनिर्माण कार्य (प्रथम चरण)।
on Thursday, February 29th 2024, 7:13:12 am
Technical Sanction
of ₹ 30 Lacs
1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. 80(T.S.)/16C
on Wednesday, March 27th 2024, 6:30:00 pm
10%
Physical Progress
Physical Progress Reported at 1st time
on Wednesday, July 17th 2024, 6:30:00 pm
20%
Physical Progress
Physical Progress Reported at 2nd time
on Tuesday, October 22nd 2024, 6:30:00 pm
0.26%
Financial Progress
1st Expenditure
of ₹ 7762 (0.08 Lacs ) done.
Cummulative ₹ 0.08Lacs ( against 30Lacs )
on Wednesday, February 12th 2025, 6:30:00 pm
0.40%
Financial Progress
2nd Expenditure
of ₹ 4251 (0.04 Lacs ) done.
Cummulative ₹ 0.12Lacs ( against 30Lacs )
on Sunday, March 23rd 2025, 6:30:00 pm
15.22%
Financial Progress
3rd Expenditure
of ₹ 444697 (4.45 Lacs ) done.
Cummulative ₹ 4.57Lacs ( against 30Lacs )
on Monday, March 24th 2025, 6:30:00 pm
28.56%
Financial Progress
4th Expenditure
of ₹ 400000 (4.00 Lacs ) done.
Cummulative ₹ 8.57Lacs ( against 30Lacs )
on Monday, March 24th 2025, 6:30:00 pm
15.22%
Financial Progress
5th Expenditure
of ₹ -400000 (-4.00 Lacs ) done.
Cummulative ₹ 4.57Lacs ( against 30Lacs )
on Monday, April 7th 2025, 7:40:37 am
PWD UttarakahndPhoto (ID 67077) from Site Received
Uploader : Manoj Singh Panwar, Assistant Engineer Civil ,8th Circle Tehri
Landmark : Bridge site
Remark : Site selection
on Tuesday, May 27th 2025, 6:30:00 pm
30.05%
Financial Progress
6th Expenditure
of ₹ 444697 (4.45 Lacs ) done.
Cummulative ₹ 9.01Lacs ( against 30Lacs )