Work Sanctioned
सड़क सुरक्षा के अन्तर्गत घट्टूगाड-सिलोगी-गुमखाल-लैन्सडौन-रिखणीखाल-बीरोंखाल राज्य मार्ग ंस0-51 के किमी0 116.00 से 126.00 मे क्रैश बैरियर का कार्य।

9 months ago

on Monday, December 16th 2024, 7:36:20 am

Technical Sanction
of ₹ 484.3 Lacs

1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. TS VIDE 6722/22(287) YATA-(LANSDOWNE) PAURI/2024, DATED 16-12-2024

8 months ago

on Friday, January 17th 2025, 5:38:18 am
<span class="4">Picture Id:62864</span>
PWD Uttarakahnd
Photo (ID 62864) from Site Received
Uploader : Sonu Kumar, Additional Assistant Engineer Civil ,PD Lansdown
Landmark : 122.700
Remark : Road safety work in progress at SH 51

7 months ago

on Monday, February 17th 2025, 5:17:23 am
<span class="4">Picture Id:64549</span>
PWD Uttarakahnd
Photo (ID 64549) from Site Received
Uploader : Sonu Kumar, Additional Assistant Engineer Civil ,PD Lansdown
Landmark : 119.800
Remark : Road safety work at SH 51

6 months ago

on Monday, February 24th 2025, 6:30:00 pm
20%

Physical Progress
Physical Progress Reported at 1st time

5 months ago

on Tuesday, March 25th 2025, 4:51:55 am
<span class="4">Picture Id:66493</span>
PWD Uttarakahnd
Photo (ID 66493) from Site Received
Uploader : Sonu Kumar, Additional Assistant Engineer Civil ,PD Lansdown
Landmark : 123.925
Remark : Crash barrier work in progress

5 months ago

on Friday, March 28th 2025, 6:30:00 pm
100%

Physical Progress
Physical Progress Reported at 2nd time

5 months ago

on Saturday, March 29th 2025, 6:30:00 pm
0.05%
Financial Progress

1st Expenditure
of ₹ 23789 (0.24 Lacs ) done.
Cummulative ₹ 0.24Lacs ( against 484.3Lacs )

5 months ago

on Saturday, March 29th 2025, 6:30:00 pm
82.59%
Financial Progress

2nd Expenditure
of ₹ 39976211 (399.76 Lacs ) done.
Cummulative ₹ 400.00Lacs ( against 484.3Lacs )

3 months ago

on Thursday, June 19th 2025, 6:30:00 pm
93.99%
Financial Progress

3rd Expenditure
of ₹ 5517391 (55.17 Lacs ) done.
Cummulative ₹ 455.17Lacs ( against 484.3Lacs )

2 months ago

on Monday, July 14th 2025, 6:30:00 pm
96.48%
Financial Progress

4th Expenditure
of ₹ 1206297 (12.06 Lacs ) done.
Cummulative ₹ 467.24Lacs ( against 484.3Lacs )