10 months ago

on Tuesday, November 5th 2024, 6:30:00 pm
Work Sanctioned
सड़क सुरक्षा के अन्तर्गत घट्टूगाड-सिलोगी-गुमखाल-लैन्सडौन-रिखणीखाल-बीरोंखाल राज्य मार्ग सं0-51 पर अवशेष भाग में सुरक्षात्मक कार्य (किमी0 100.00 से किमी0 115.00 तक) ।

9 months ago

on Monday, December 16th 2024, 7:34:50 am

Technical Sanction
of ₹ 497.28 Lacs

1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. TS VIDE 6723/12(285) YATA-(LANSDOWNE) PAURI/2024 dated 16-12-2024

6 months ago

on Wednesday, February 26th 2025, 6:30:00 pm
10%

Physical Progress
Physical Progress Reported at 1st time

5 months ago

on Saturday, March 29th 2025, 6:30:00 pm
80.44%
Financial Progress

1st Expenditure
of ₹ 40000000 (400.00 Lacs ) done.
Cummulative ₹ 400.00Lacs ( against 497.28Lacs )

5 months ago

on Wednesday, April 9th 2025, 6:30:00 pm
100%

Physical Progress
Physical Progress Reported at 2nd time

3 months ago

on Tuesday, May 27th 2025, 6:30:00 pm
98.69%
Financial Progress

2nd Expenditure
of ₹ 9078419 (90.78 Lacs ) done.
Cummulative ₹ 490.78Lacs ( against 497.28Lacs )

2 months ago

on Wednesday, June 25th 2025, 6:30:00 pm
98.79%
Financial Progress

3rd Expenditure
of ₹ 46374 (0.46 Lacs ) done.
Cummulative ₹ 491.25Lacs ( against 497.28Lacs )

a month ago

on Wednesday, July 23rd 2025, 6:30:00 pm
98.83%
Financial Progress

4th Expenditure
of ₹ 19323 (0.19 Lacs ) done.
Cummulative ₹ 491.44Lacs ( against 497.28Lacs )