on Wednesday, December 8th 2021, 6:30:00 pm
Work Sanctioned
राज्य योजना के अन्तर्गत जनपद पौड़ी गढ़वाल के विधान सभा क्षेत्र कोटद्वार के विकास खण्ड दुगड्डा के अन्तर्गत तेलीस्रोत से राजपूत चैक तक मोटर मार्ग का सुदृढीकरण कार्य।
on Thursday, January 6th 2022, 7:27:06 am
Technical Sanction
of ₹ 52.42 Lacs
1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. 116/8C
on Tuesday, November 29th 2022, 6:30:00 pm
5.21%
Financial Progress
1st Expenditure
of ₹ 273000 (2.73 Lacs ) done.
Cummulative ₹ 2.73Lacs ( against 52.42Lacs )
on Tuesday, January 3rd 2023, 6:30:00 pm
10%
Physical Progress
Physical Progress Reported at 1st time
on Monday, January 30th 2023, 6:30:00 pm
15.66%
Financial Progress
2nd Expenditure
of ₹ 548000 (5.48 Lacs ) done.
Cummulative ₹ 8.21Lacs ( against 52.42Lacs )
on Monday, February 27th 2023, 6:30:00 pm
18.96%
Financial Progress
3rd Expenditure
of ₹ 173000 (1.73 Lacs ) done.
Cummulative ₹ 9.94Lacs ( against 52.42Lacs )
on Thursday, March 30th 2023, 6:30:00 pm
51.58%
Financial Progress
4th Expenditure
of ₹ 1710000 (17.10 Lacs ) done.
Cummulative ₹ 27.04Lacs ( against 52.42Lacs )
on Saturday, April 22nd 2023, 6:30:00 pm
65%
Physical Progress
Physical Progress Reported at 2nd time
on Friday, September 29th 2023, 6:30:00 pm
100%
Physical Progress
Physical Progress Reported at 3rd time
on Wednesday, November 29th 2023, 6:30:00 pm
60.02%
Financial Progress
5th Expenditure
of ₹ 442000 (4.42 Lacs ) done.
Cummulative ₹ 31.46Lacs ( against 52.42Lacs )
on Saturday, December 30th 2023, 6:30:00 pm
84.66%
Financial Progress
6th Expenditure
of ₹ 1292000 (12.92 Lacs ) done.
Cummulative ₹ 44.38Lacs ( against 52.42Lacs )
on Thursday, September 12th 2024, 6:30:00 pm
84.85%
Financial Progress
7th Expenditure
of ₹ 10000 (0.10 Lacs ) done.
Cummulative ₹ 44.48Lacs ( against 52.42Lacs )