Technical Sanction
of ₹ 203.85 Lacs
1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. 114/1507 yata-12/2022
on Thursday, December 30th 2021, 6:30:00 pm
Work Sanctioned
मा0 मुख्यमंत्री घोषणा सं0-601/2015 के अन्तर्गत जनपद पौड़ी गढ़वाल के विधान सभा क्षेत्र यमकेश्वर में दुगड्डा-जुवा मोटर मार्ग के कि0मी0 1 में लंगूरीगाड़ पर 30 मी0 स्पान स्टील गर्डर सेतु का निर्माण।
on Sunday, February 27th 2022, 6:30:00 pm
0.09%
Financial Progress
1st Expenditure
of ₹ 18000 (0.18 Lacs ) done.
Cummulative ₹ 0.18Lacs ( against 203.85Lacs )
on Thursday, January 12th 2023, 12:56:38 am
PWD UttarakahndPhoto (ID 15441) from Site Received
Uploader : Satya Prakash, Assistant Engineer Civil ,CD Dugadda
Landmark : 00
Remark : Raft casting
on Thursday, January 12th 2023, 1:20:56 am
PWD UttarakahndPhoto (ID 15448) from Site Received
Uploader : Santosh Kumar, Additional Assistant Engineer Civil ,CD Dugadda
Landmark : 0.00 of juwa purankot motor road
Remark : C/o 30 mtr span steelgirder bridge
on Thursday, January 12th 2023, 1:22:53 am
PWD UttarakahndPhoto (ID 15442) from Site Received
Uploader : Satya Prakash, Assistant Engineer Civil ,CD Dugadda
Landmark : Juwa bridge raft casting
Remark : Raft casting
on Monday, January 16th 2023, 12:26:09 am
PWD UttarakahndPhoto (ID 15499) from Site Received
Uploader : Santosh Kumar, Additional Assistant Engineer Civil ,CD Dugadda
Landmark : 0.050 of Dugadda juwa motor road
Remark : C/o 30 mtr span steel girder bridge in Dugadda juwa motor road
on Monday, January 16th 2023, 12:32:53 am
PWD UttarakahndPhoto (ID 15500) from Site Received
Uploader : Santosh Kumar, Additional Assistant Engineer Civil ,CD Dugadda
Landmark : 0.050
Remark : C/0 30 mtr span steel girder bridge in Dugadda juwa motor road
on Monday, January 30th 2023, 6:30:00 pm
12.67%
Financial Progress
2nd Expenditure
of ₹ 2565000 (25.65 Lacs ) done.
Cummulative ₹ 25.83Lacs ( against 203.85Lacs )
on Wednesday, February 1st 2023, 12:33:01 am
PWD UttarakahndPhoto (ID 15910) from Site Received
Uploader : Santosh Kumar, Additional Assistant Engineer Civil ,CD Dugadda
Landmark : Km 0.050 in Dugadda juwa motor road
Remark : 2nd layer concreting in R/S abutment
on Thursday, March 30th 2023, 6:30:00 pm
24.48%
Financial Progress
3rd Expenditure
of ₹ 2408000 (24.08 Lacs ) done.
Cummulative ₹ 49.91Lacs ( against 203.85Lacs )
on Saturday, April 22nd 2023, 6:30:00 pm
24%
Physical Progress
Physical Progress Reported at 1st time
on Thursday, June 29th 2023, 6:30:00 pm
31.24%
Financial Progress
4th Expenditure
of ₹ 1378000 (13.78 Lacs ) done.
Cummulative ₹ 63.69Lacs ( against 203.85Lacs )
on Friday, June 30th 2023, 6:30:00 pm
35%
Physical Progress
Physical Progress Reported at 2nd time
on Sunday, July 30th 2023, 6:30:00 pm
37.63%
Financial Progress
5th Expenditure
of ₹ 1302000 (13.02 Lacs ) done.
Cummulative ₹ 76.71Lacs ( against 203.85Lacs )
on Wednesday, August 2nd 2023, 6:30:00 pm
50%
Physical Progress
Physical Progress Reported at 3rd time
on Tuesday, August 29th 2023, 6:30:00 pm
50.38%
Financial Progress
6th Expenditure
of ₹ 2599000 (25.99 Lacs ) done.
Cummulative ₹ 102.70Lacs ( against 203.85Lacs )
on Friday, September 29th 2023, 6:30:00 pm
56.76%
Financial Progress
7th Expenditure
of ₹ 1300000 (13.00 Lacs ) done.
Cummulative ₹ 115.70Lacs ( against 203.85Lacs )
on Monday, October 30th 2023, 6:30:00 pm
62.75%
Financial Progress
8th Expenditure
of ₹ 1221000 (12.21 Lacs ) done.
Cummulative ₹ 127.91Lacs ( against 203.85Lacs )
on Monday, October 30th 2023, 6:30:00 pm
55%
Physical Progress
Physical Progress Reported at 4th time
on Tuesday, January 30th 2024, 6:30:00 pm
67.26%
Financial Progress
9th Expenditure
of ₹ 919000 (9.19 Lacs ) done.
Cummulative ₹ 137.10Lacs ( against 203.85Lacs )
on Sunday, February 18th 2024, 6:30:00 pm
78.45%
Financial Progress
10th Expenditure
of ₹ 2282000 (22.82 Lacs ) done.
Cummulative ₹ 159.92Lacs ( against 203.85Lacs )
on Friday, March 1st 2024, 6:30:00 pm
90%
Physical Progress
Physical Progress Reported at 5th time
on Saturday, March 30th 2024, 6:30:00 pm
88.75%
Financial Progress
11th Expenditure
of ₹ 2100000 (21.00 Lacs ) done.
Cummulative ₹ 180.92Lacs ( against 203.85Lacs )
on Friday, April 5th 2024, 6:30:00 pm
100%
Physical Progress
Physical Progress Reported at 6th time
on Tuesday, January 14th 2025, 6:30:00 pm
93.39%
Financial Progress
12th Expenditure
of ₹ 945386 (9.45 Lacs ) done.
Cummulative ₹ 190.37Lacs ( against 203.85Lacs )