Refresh data
on Friday, February 7th 2014, 6:30:00 pm
Work Sanctioned
जनपद पौड़ी के विधान सभा क्षेत्र श्रीनगर के अंतर्गत मैखुली-देवराडी मोटर मार्ग के किमी0 5 में मोटर लौह पुल का निर्माण (प्रथम चरण)
on Friday, February 28th 2014, 6:30:00 pm
2.86%
Financial Progress
1st Expenditure
of ₹ 6000 (0.06 Lacs ) done.
Cummulative ₹ 0.06Lacs ( against 2.1Lacs )
on Saturday, February 28th 2015, 6:30:00 pm
17.14%
Financial Progress
2nd Expenditure
of ₹ 30000 (0.30 Lacs ) done.
Cummulative ₹ 0.36Lacs ( against 2.1Lacs )
on Monday, February 29th 2016, 6:30:00 pm
100.00%
Financial Progress
3rd Expenditure
of ₹ 174000 (1.74 Lacs ) done.
Cummulative ₹ 2.10Lacs ( against 2.1Lacs )
on Wednesday, April 24th 2024, 6:30:00 pm
10%
Physical Progress
Physical Progress Reported at 1st time