Refresh data
on Monday, August 31st 2015, 6:30:00 pm
Work Sanctioned
माननीय मुख्यमंत्री जी घोषणा के अन्तर्गत जनपद पौड़ी गढ़वाल के विधानसभा क्षेत्र श्रीनगर के अन्तर्गत कफल्ट मुसेटी फरस्यूड़ी धांधणखेत मोटर मार्ग के कि0मी0 1 से 8 तक सुधार एवं डामरीकरण का कार्य।
on Monday, February 29th 2016, 6:30:00 pm
0.03%
Financial Progress
1st Expenditure
of ₹ 10000 (0.10 Lacs ) done.
Cummulative ₹ 0.10Lacs ( against 333.35Lacs )
on Wednesday, June 8th 2016, 6:30:00 pm
Technical Sanction
of ₹ 333.35 Lacs
1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. CE1409/12(235)YATA-PAURI/2016
on Wednesday, August 31st 2016, 6:30:00 pm
9.46%
Financial Progress
2nd Expenditure
of ₹ 3143000 (31.43 Lacs ) done.
Cummulative ₹ 31.53Lacs ( against 333.35Lacs )
on Friday, September 30th 2016, 6:30:00 pm
12.86%
Financial Progress
3rd Expenditure
of ₹ 1135000 (11.35 Lacs ) done.
Cummulative ₹ 42.88Lacs ( against 333.35Lacs )
on Tuesday, February 28th 2017, 6:30:00 pm
36.25%
Financial Progress
4th Expenditure
of ₹ 7796000 (77.96 Lacs ) done.
Cummulative ₹ 120.84Lacs ( against 333.35Lacs )
on Friday, June 30th 2017, 6:30:00 pm
49.70%
Financial Progress
5th Expenditure
of ₹ 4485000 (44.85 Lacs ) done.
Cummulative ₹ 165.69Lacs ( against 333.35Lacs )
on Thursday, November 30th 2017, 6:30:00 pm
56.90%
Financial Progress
6th Expenditure
of ₹ 2400000 (24.00 Lacs ) done.
Cummulative ₹ 189.69Lacs ( against 333.35Lacs )
on Sunday, December 31st 2017, 6:30:00 pm
70.64%
Financial Progress
7th Expenditure
of ₹ 4580000 (45.80 Lacs ) done.
Cummulative ₹ 235.49Lacs ( against 333.35Lacs )
on Wednesday, February 28th 2018, 6:30:00 pm
73.03%
Financial Progress
8th Expenditure
of ₹ 796000 (7.96 Lacs ) done.
Cummulative ₹ 243.45Lacs ( against 333.35Lacs )
on Saturday, June 30th 2018, 6:30:00 pm
84.06%
Financial Progress
9th Expenditure
of ₹ 3675000 (36.75 Lacs ) done.
Cummulative ₹ 280.20Lacs ( against 333.35Lacs )
on Tuesday, December 31st 2019, 6:30:00 pm
84.41%
Financial Progress
10th Expenditure
of ₹ 118000 (1.18 Lacs ) done.
Cummulative ₹ 281.38Lacs ( against 333.35Lacs )
on Thursday, December 30th 2021, 6:30:00 pm
84.42%
Financial Progress
11th Expenditure
of ₹ 2000 (0.02 Lacs ) done.
Cummulative ₹ 281.40Lacs ( against 333.35Lacs )
on Sunday, April 23rd 2023, 6:30:00 pm
51%
Physical Progress
Physical Progress Reported at 1st time
on Thursday, September 28th 2023, 6:30:00 pm
84.48%
Financial Progress
12th Expenditure
of ₹ 20000 (0.20 Lacs ) done.
Cummulative ₹ 281.60Lacs ( against 333.35Lacs )
on Wednesday, April 24th 2024, 6:30:00 pm
65%
Physical Progress
Physical Progress Reported at 2nd time
on Thursday, May 30th 2024, 6:30:00 pm
100.00%
Financial Progress
13th Expenditure
of ₹ 5175000 (51.75 Lacs ) done.
Cummulative ₹ 333.35Lacs ( against 333.35Lacs )
on Tuesday, July 2nd 2024, 6:30:00 pm
70%
Physical Progress
Physical Progress Reported at 3rd time
on Wednesday, July 24th 2024, 6:30:00 pm
93.56%
Financial Progress
14th Expenditure
of ₹ -2146863 (-21.47 Lacs ) done.
Cummulative ₹ 311.88Lacs ( against 333.35Lacs )
on Thursday, July 25th 2024, 6:30:00 pm
93.56%
Financial Progress
15th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 311.88Lacs ( against 333.35Lacs )
on Wednesday, December 11th 2024, 6:30:00 pm
97.38%
Financial Progress
16th Expenditure
of ₹ 1273574 (12.74 Lacs ) done.
Cummulative ₹ 324.62Lacs ( against 333.35Lacs )