on Sunday, March 8th 2015, 6:30:00 pm
Work Sanctioned
रा0मा0शि0अभि0 के अन्तर्गत राजकीय इण्टर कालेज भगवतीतलैया का भवन निर्माण कार्य।
on Wednesday, December 30th 2015, 6:30:00 pm
Technical Sanction
of ₹ 52 Lacs
1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. EE 1780/18C
on Saturday, September 30th 2017, 6:30:00 pm
37.78%
Financial Progress
1st Expenditure
of ₹ 2620000 (26.20 Lacs ) done.
Cummulative ₹ 26.20Lacs ( against 69.34Lacs )
on Wednesday, February 28th 2018, 6:30:00 pm
37.28%
Financial Progress
2nd Expenditure
of ₹ -35000 (-0.35 Lacs ) done.
Cummulative ₹ 25.85Lacs ( against 69.34Lacs )
on Tuesday, June 15th 2021, 6:30:00 pm
45.91%
Financial Progress
3rd Expenditure
of ₹ 598572 (5.99 Lacs ) done.
Cummulative ₹ 31.84Lacs ( against 69.34Lacs )
on Monday, August 16th 2021, 5:14:14 am
PWD UttarakahndPhoto (ID 12672) from Site Received
Uploader : Devraj Singh Pokhriyal, Additional Assistant Engineer Civil ,CD Uttarkashi
Landmark : Library Building at GIC Bhagwatitallaiya, Bironkhal
Remark : Painting and colouring work of A library room at GIC Bhagwatitallaiya in progress.
on Sunday, March 27th 2022, 6:30:00 pm
56.92%
Financial Progress
4th Expenditure
of ₹ 763000 (7.63 Lacs ) done.
Cummulative ₹ 39.47Lacs ( against 69.34Lacs )
on Tuesday, December 27th 2022, 6:30:00 pm
100%
Physical Progress
Physical Progress Reported at 1st time