2 years ago

on Sunday, June 18th 2023, 6:30:00 pm
Work Sanctioned
राज्य योजना के अन्तर्गत जनपद पौड़ी गढ़वाल के विधानसभा क्षेत्र चैबट्टाखाल के विकासखण्ड बीरोंखाल के अन्तर्गत ग्राम स्यूंसी होते हुये ग्राम आमकुलाऊ तक मोटर मार्ग का नव निर्माण कार्य (द्वितीय चरण स्टेज-1)

2 years ago

on Sunday, October 29th 2023, 6:30:00 pm
9.51%
Financial Progress

1st Expenditure
of ₹ 698000 (6.98 Lacs ) done.
Cummulative ₹ 6.98Lacs ( against 73.4Lacs )

2 years ago

on Wednesday, November 29th 2023, 6:30:00 pm
21.13%
Financial Progress

3rd Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 15.51Lacs ( against 73.4Lacs )

2 years ago

on Wednesday, November 29th 2023, 6:30:00 pm
21.13%
Financial Progress

2nd Expenditure
of ₹ 853000 (8.53 Lacs ) done.
Cummulative ₹ 15.51Lacs ( against 73.4Lacs )

2 years ago

on Monday, January 29th 2024, 6:30:00 pm
23.79%
Financial Progress

4th Expenditure
of ₹ 195000 (1.95 Lacs ) done.
Cummulative ₹ 17.46Lacs ( against 73.4Lacs )

2 years ago

on Wednesday, February 28th 2024, 6:30:00 pm
25.24%
Financial Progress

5th Expenditure
of ₹ 106256 (1.06 Lacs ) done.
Cummulative ₹ 18.52Lacs ( against 73.4Lacs )

a year ago

on Monday, March 25th 2024, 6:30:00 pm
38.48%
Financial Progress

6th Expenditure
of ₹ 972118 (9.72 Lacs ) done.
Cummulative ₹ 28.24Lacs ( against 73.4Lacs )

a year ago

on Tuesday, April 2nd 2024, 6:30:00 pm
40%

Physical Progress
Physical Progress Reported at 1st time

a year ago

on Thursday, May 30th 2024, 6:30:00 pm
44.77%
Financial Progress

7th Expenditure
of ₹ 462000 (4.62 Lacs ) done.
Cummulative ₹ 32.86Lacs ( against 73.4Lacs )

a year ago

on Tuesday, June 25th 2024, 6:30:00 pm
63.73%
Financial Progress

10th Expenditure
of ₹ 425478 (4.25 Lacs ) done.
Cummulative ₹ 46.78Lacs ( against 73.4Lacs )

a year ago

on Tuesday, June 25th 2024, 6:30:00 pm
57.93%
Financial Progress

9th Expenditure
of ₹ 374819 (3.75 Lacs ) done.
Cummulative ₹ 42.52Lacs ( against 73.4Lacs )

a year ago

on Tuesday, June 25th 2024, 6:30:00 pm
52.83%
Financial Progress

8th Expenditure
of ₹ 591161 (5.91 Lacs ) done.
Cummulative ₹ 38.78Lacs ( against 73.4Lacs )

10 months ago

on Tuesday, October 22nd 2024, 6:30:00 pm
77.46%
Financial Progress

12th Expenditure
of ₹ 759444 (7.59 Lacs ) done.
Cummulative ₹ 56.85Lacs ( against 73.4Lacs )

10 months ago

on Tuesday, October 22nd 2024, 6:30:00 pm
67.11%
Financial Progress

11th Expenditure
of ₹ 248082 (2.48 Lacs ) done.
Cummulative ₹ 49.26Lacs ( against 73.4Lacs )

10 months ago

on Friday, October 25th 2024, 6:30:00 pm
78.60%
Financial Progress

14th Expenditure
of ₹ 32000 (0.32 Lacs ) done.
Cummulative ₹ 57.69Lacs ( against 73.4Lacs )

10 months ago

on Friday, October 25th 2024, 6:30:00 pm
78.17%
Financial Progress

13th Expenditure
of ₹ 52000 (0.52 Lacs ) done.
Cummulative ₹ 57.37Lacs ( against 73.4Lacs )

9 months ago

on Wednesday, November 27th 2024, 6:30:00 pm
79.74%
Financial Progress

15th Expenditure
of ₹ 83898 (0.84 Lacs ) done.
Cummulative ₹ 58.53Lacs ( against 73.4Lacs )

9 months ago

on Thursday, November 28th 2024, 6:30:00 pm
100%

Physical Progress
Physical Progress Reported at 2nd time

5 months ago

on Sunday, March 23rd 2025, 6:30:00 pm
79.74%
Financial Progress

16th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 58.53Lacs ( against 73.4Lacs )

5 months ago

on Sunday, March 30th 2025, 6:30:00 pm
96.39%
Financial Progress

18th Expenditure
of ₹ 528366 (5.28 Lacs ) done.
Cummulative ₹ 70.75Lacs ( against 73.4Lacs )

5 months ago

on Sunday, March 30th 2025, 6:30:00 pm
89.19%
Financial Progress

17th Expenditure
of ₹ 693467 (6.93 Lacs ) done.
Cummulative ₹ 65.47Lacs ( against 73.4Lacs )

2 months ago

on Thursday, June 26th 2025, 6:30:00 pm
98.21%
Financial Progress

19th Expenditure
of ₹ 133373 (1.33 Lacs ) done.
Cummulative ₹ 72.08Lacs ( against 73.4Lacs )

a month ago

on Tuesday, July 29th 2025, 6:30:00 pm
98.78%
Financial Progress

20th Expenditure
of ₹ 42110 (0.42 Lacs ) done.
Cummulative ₹ 72.51Lacs ( against 73.4Lacs )