on Sunday, June 18th 2023, 6:30:00 pm
Work Sanctioned
राज्य योजना के अन्तर्गत जनपद पौड़ी गढ़वाल के विधानसभा क्षेत्र चैबट्टाखाल के विकासखण्ड बीरोंखाल के अन्तर्गत ग्राम स्यूंसी होते हुये ग्राम आमकुलाऊ तक मोटर मार्ग का नव निर्माण कार्य (द्वितीय चरण स्टेज-1)
on Sunday, October 29th 2023, 6:30:00 pm
9.51%
Financial Progress
1st Expenditure
of ₹ 698000 (6.98 Lacs ) done.
Cummulative ₹ 6.98Lacs ( against 73.4Lacs )
on Wednesday, November 29th 2023, 6:30:00 pm
21.13%
Financial Progress
3rd Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 15.51Lacs ( against 73.4Lacs )
on Wednesday, November 29th 2023, 6:30:00 pm
21.13%
Financial Progress
2nd Expenditure
of ₹ 853000 (8.53 Lacs ) done.
Cummulative ₹ 15.51Lacs ( against 73.4Lacs )
on Monday, January 29th 2024, 6:30:00 pm
23.79%
Financial Progress
4th Expenditure
of ₹ 195000 (1.95 Lacs ) done.
Cummulative ₹ 17.46Lacs ( against 73.4Lacs )
on Wednesday, February 28th 2024, 6:30:00 pm
25.24%
Financial Progress
5th Expenditure
of ₹ 106256 (1.06 Lacs ) done.
Cummulative ₹ 18.52Lacs ( against 73.4Lacs )
on Monday, March 25th 2024, 6:30:00 pm
38.48%
Financial Progress
6th Expenditure
of ₹ 972118 (9.72 Lacs ) done.
Cummulative ₹ 28.24Lacs ( against 73.4Lacs )
on Tuesday, April 2nd 2024, 6:30:00 pm
40%
Physical Progress
Physical Progress Reported at 1st time
on Thursday, May 30th 2024, 6:30:00 pm
44.77%
Financial Progress
7th Expenditure
of ₹ 462000 (4.62 Lacs ) done.
Cummulative ₹ 32.86Lacs ( against 73.4Lacs )
on Tuesday, June 25th 2024, 6:30:00 pm
63.73%
Financial Progress
10th Expenditure
of ₹ 425478 (4.25 Lacs ) done.
Cummulative ₹ 46.78Lacs ( against 73.4Lacs )
on Tuesday, June 25th 2024, 6:30:00 pm
57.93%
Financial Progress
9th Expenditure
of ₹ 374819 (3.75 Lacs ) done.
Cummulative ₹ 42.52Lacs ( against 73.4Lacs )
on Tuesday, June 25th 2024, 6:30:00 pm
52.83%
Financial Progress
8th Expenditure
of ₹ 591161 (5.91 Lacs ) done.
Cummulative ₹ 38.78Lacs ( against 73.4Lacs )
on Tuesday, October 22nd 2024, 6:30:00 pm
77.46%
Financial Progress
12th Expenditure
of ₹ 759444 (7.59 Lacs ) done.
Cummulative ₹ 56.85Lacs ( against 73.4Lacs )
on Tuesday, October 22nd 2024, 6:30:00 pm
67.11%
Financial Progress
11th Expenditure
of ₹ 248082 (2.48 Lacs ) done.
Cummulative ₹ 49.26Lacs ( against 73.4Lacs )
on Friday, October 25th 2024, 6:30:00 pm
78.60%
Financial Progress
14th Expenditure
of ₹ 32000 (0.32 Lacs ) done.
Cummulative ₹ 57.69Lacs ( against 73.4Lacs )
on Friday, October 25th 2024, 6:30:00 pm
78.17%
Financial Progress
13th Expenditure
of ₹ 52000 (0.52 Lacs ) done.
Cummulative ₹ 57.37Lacs ( against 73.4Lacs )
on Wednesday, November 27th 2024, 6:30:00 pm
79.74%
Financial Progress
15th Expenditure
of ₹ 83898 (0.84 Lacs ) done.
Cummulative ₹ 58.53Lacs ( against 73.4Lacs )
on Thursday, November 28th 2024, 6:30:00 pm
100%
Physical Progress
Physical Progress Reported at 2nd time
on Sunday, March 23rd 2025, 6:30:00 pm
79.74%
Financial Progress
16th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 58.53Lacs ( against 73.4Lacs )
on Sunday, March 30th 2025, 6:30:00 pm
96.39%
Financial Progress
18th Expenditure
of ₹ 528366 (5.28 Lacs ) done.
Cummulative ₹ 70.75Lacs ( against 73.4Lacs )
on Sunday, March 30th 2025, 6:30:00 pm
89.19%
Financial Progress
17th Expenditure
of ₹ 693467 (6.93 Lacs ) done.
Cummulative ₹ 65.47Lacs ( against 73.4Lacs )
on Thursday, June 26th 2025, 6:30:00 pm
98.21%
Financial Progress
19th Expenditure
of ₹ 133373 (1.33 Lacs ) done.
Cummulative ₹ 72.08Lacs ( against 73.4Lacs )
on Tuesday, July 29th 2025, 6:30:00 pm
98.78%
Financial Progress
20th Expenditure
of ₹ 42110 (0.42 Lacs ) done.
Cummulative ₹ 72.51Lacs ( against 73.4Lacs )