Work Sanctioned
राज्य योजना के अन्तर्गत जनपद पौड़ी गढ़वाल के विधानसभा क्षेत्र चैबट्टाखाल के विकासखण्ड बीरोंखाल के अन्तर्गत सैन्धार- नेग्याणा- चोरखिण्डा मोटर मार्ग का सुधारीकरण एवं डामरीकरण कार्य। (द्वितीय चरण)
on Monday, October 21st 2024, 6:30:00 pm
0.00%
Financial Progress
1st Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 0.00Lacs ( against 158.34Lacs )
on Sunday, October 27th 2024, 6:30:00 pm
19.99%
Financial Progress
2nd Expenditure
of ₹ 3165158 (31.65 Lacs ) done.
Cummulative ₹ 31.65Lacs ( against 158.34Lacs )
on Monday, November 4th 2024, 6:30:00 pm
10%
Physical Progress
Physical Progress Reported at 1st time
on Sunday, December 1st 2024, 6:30:00 pm
19.99%
Financial Progress
3rd Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 31.65Lacs ( against 158.34Lacs )
on Sunday, December 1st 2024, 6:30:00 pm
22.85%
Financial Progress
4th Expenditure
of ₹ 452231 (4.52 Lacs ) done.
Cummulative ₹ 36.17Lacs ( against 158.34Lacs )
on Monday, December 9th 2024, 6:30:00 pm
22.85%
Financial Progress
5th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 36.17Lacs ( against 158.34Lacs )
on Thursday, December 26th 2024, 6:30:00 pm
31.79%
Financial Progress
6th Expenditure
of ₹ 1415707 (14.16 Lacs ) done.
Cummulative ₹ 50.33Lacs ( against 158.34Lacs )
on Wednesday, January 15th 2025, 6:30:00 pm
34.36%
Financial Progress
7th Expenditure
of ₹ 406678 (4.07 Lacs ) done.
Cummulative ₹ 54.40Lacs ( against 158.34Lacs )
on Monday, February 3rd 2025, 6:30:00 pm
51.90%
Financial Progress
8th Expenditure
of ₹ 2777779 (27.78 Lacs ) done.
Cummulative ₹ 82.18Lacs ( against 158.34Lacs )
on Thursday, February 13th 2025, 9:16:20 am
PWD UttarakahndPhoto (ID 64392) from Site Received
Uploader : Bharat Pal, Assistant Engineer Civil ,CD Baijro
Landmark : 0.600 couseway
Remark : G3 work is complete
on Thursday, February 13th 2025, 9:25:32 am
PWD UttarakahndPhoto (ID 64394) from Site Received
Uploader : Bharat Pal, Assistant Engineer Civil ,CD Baijro
Landmark : 0.750 km near couseway
Remark : G3 work completed
on Wednesday, February 19th 2025, 6:30:00 pm
60%
Physical Progress
Physical Progress Reported at 2nd time
on Monday, February 24th 2025, 6:30:00 pm
66.72%
Financial Progress
9th Expenditure
of ₹ 2347198 (23.47 Lacs ) done.
Cummulative ₹ 105.65Lacs ( against 158.34Lacs )
on Thursday, March 20th 2025, 6:30:00 pm
84.43%
Financial Progress
10th Expenditure
of ₹ 2803655 (28.04 Lacs ) done.
Cummulative ₹ 133.68Lacs ( against 158.34Lacs )
on Sunday, March 23rd 2025, 6:30:00 pm
83.82%
Financial Progress
11th Expenditure
of ₹ -96340 (-0.96 Lacs ) done.
Cummulative ₹ 132.72Lacs ( against 158.34Lacs )
on Wednesday, March 26th 2025, 6:30:00 pm
84.43%
Financial Progress
13th Expenditure
of ₹ 85713 (0.86 Lacs ) done.
Cummulative ₹ 133.68Lacs ( against 158.34Lacs )
on Wednesday, March 26th 2025, 6:30:00 pm
83.89%
Financial Progress
12th Expenditure
of ₹ 10627 (0.11 Lacs ) done.
Cummulative ₹ 132.83Lacs ( against 158.34Lacs )
on Tuesday, April 1st 2025, 6:30:00 pm
85%
Physical Progress
Physical Progress Reported at 3rd time
on Friday, April 4th 2025, 6:16:45 am
PWD UttarakahndPhoto (ID 66907) from Site Received
Uploader : Bharat Pal, Assistant Engineer Civil ,CD Baijro
Landmark : Km -01. 0.025
Remark : Work is 95% completed
on Friday, April 4th 2025, 6:27:31 am
PWD UttarakahndPhoto (ID 66909) from Site Received
Uploader : Bharat Pal, Assistant Engineer Civil ,CD Baijro
Landmark : 0.450 km
Remark : Crash barrier and p.c work completed
on Friday, April 4th 2025, 6:33:11 am
PWD UttarakahndPhoto (ID 66912) from Site Received
Uploader : Bharat Pal, Assistant Engineer Civil ,CD Baijro
Landmark : 2.100 km
Remark : P.c and crash barrier work completed
on Friday, April 4th 2025, 6:41:56 am
PWD UttarakahndPhoto (ID 66916) from Site Received
Uploader : Bharat Pal, Assistant Engineer Civil ,CD Baijro
Landmark : 1.700 km
Remark : Work is 95% completed
on Monday, April 7th 2025, 6:30:00 pm
93%
Physical Progress
Physical Progress Reported at 4th time
on Tuesday, May 27th 2025, 6:30:00 pm
91.40%
Financial Progress
14th Expenditure
of ₹ 1103248 (11.03 Lacs ) done.
Cummulative ₹ 144.72Lacs ( against 158.34Lacs )
on Thursday, June 26th 2025, 6:30:00 pm
93.25%
Financial Progress
15th Expenditure
of ₹ 292920 (2.93 Lacs ) done.
Cummulative ₹ 147.65Lacs ( against 158.34Lacs )