on Wednesday, October 11th 2017, 6:30:00 pm
Work Sanctioned
जनपद चमोली के विधानसभा क्षेत्र बद्रीनाथ के विकासखण्ड जोशीमठ के अन्तर्गत गोविन्दघाट-पुलना मोटर मार्ग के किमी॰ 6 में भ्यूंूंडार तक मोटर मार्ग का निर्माण कार्य (प्रथम चरण)
on Wednesday, February 28th 2018, 6:30:00 pm
0.07%
Financial Progress
1st Expenditure
of ₹ 10000 (0.10 Lacs ) done.
Cummulative ₹ 0.10Lacs ( against 136Lacs )
on Monday, April 30th 2018, 6:30:00 pm
0.31%
Financial Progress
2nd Expenditure
of ₹ 32000 (0.32 Lacs ) done.
Cummulative ₹ 0.42Lacs ( against 136Lacs )
on Thursday, May 31st 2018, 6:30:00 pm
0.94%
Financial Progress
3rd Expenditure
of ₹ 86000 (0.86 Lacs ) done.
Cummulative ₹ 1.28Lacs ( against 136Lacs )
on Wednesday, March 30th 2022, 6:30:00 pm
2.23%
Financial Progress
4th Expenditure
of ₹ 175245 (1.75 Lacs ) done.
Cummulative ₹ 3.03Lacs ( against 136Lacs )
on Monday, May 30th 2022, 6:30:00 pm
2.32%
Financial Progress
5th Expenditure
of ₹ 12000 (0.12 Lacs ) done.
Cummulative ₹ 3.15Lacs ( against 136Lacs )
on Wednesday, December 28th 2022, 6:30:00 pm
20%
Physical Progress
Physical Progress Reported at 1st time
on Wednesday, November 29th 2023, 6:30:00 pm
82.44%
Financial Progress
6th Expenditure
of ₹ 10895962 (108.96 Lacs ) done.
Cummulative ₹ 112.11Lacs ( against 136Lacs )
on Friday, December 1st 2023, 6:30:00 pm
65%
Physical Progress
Physical Progress Reported at 2nd time
on Wednesday, March 27th 2024, 6:30:00 pm
84.75%
Financial Progress
7th Expenditure
of ₹ 315003 (3.15 Lacs ) done.
Cummulative ₹ 115.26Lacs ( against 136Lacs )
on Sunday, October 27th 2024, 6:30:00 pm
84.75%
Financial Progress
8th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 115.26Lacs ( against 136Lacs )
on Sunday, October 27th 2024, 6:30:00 pm
84.83%
Financial Progress
9th Expenditure
of ₹ 11000 (0.11 Lacs ) done.
Cummulative ₹ 115.37Lacs ( against 136Lacs )