19 years ago

on Wednesday, November 9th 2005, 6:30:00 pm
Work Sanctioned
सुराईथोटा- तोलमा मोटर मार्ग का विस्तार (किमी॰ 3 से 4.50)

16 years ago

on Saturday, February 28th 2009, 6:30:00 pm
2.45%
Financial Progress

1st Expenditure
of ₹ 53000 (0.53 Lacs ) done.
Cummulative ₹ 0.53Lacs ( against 21.6Lacs )

15 years ago

on Friday, April 30th 2010, 6:30:00 pm
2.69%
Financial Progress

2nd Expenditure
of ₹ 5000 (0.05 Lacs ) done.
Cummulative ₹ 0.58Lacs ( against 21.6Lacs )

10 years ago

on Friday, July 31st 2015, 6:30:00 pm
2.92%
Financial Progress

3rd Expenditure
of ₹ 5000 (0.05 Lacs ) done.
Cummulative ₹ 0.63Lacs ( against 21.6Lacs )

10 years ago

on Friday, July 31st 2015, 6:30:00 pm
18.89%
Financial Progress

4th Expenditure
of ₹ 345000 (3.45 Lacs ) done.
Cummulative ₹ 4.08Lacs ( against 21.6Lacs )

4 months ago

on Wednesday, October 23rd 2024, 6:30:00 pm
20%

Physical Progress
Physical Progress Reported at 1st time