Work Sanctioned
राज्य योजना के अन्तर्गत जनपद चमोली के विधानसभा क्षेत्र -बद्रीनाथ के अन्तर्गत पुलना-घांघरिया -श्री हेमकुण्ड साहिब पैदल मार्ग के किमी0 11 से किमी0 15 (हैलीपैड) के मध्य किये गये मोडों के सुधारों वाले स्थानो पर स्टोन सेट पेवमेंट एवं रेलिंग लगाने का कार्य

a year ago

on Tuesday, February 6th 2024, 9:26:58 am

Technical Sanction
of ₹ 279.78 Lacs

1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. CE Letter no. 456/07(295) Gopeshwar- Pauri/2024 DT. 06.02.2024

a year ago

on Wednesday, March 27th 2024, 6:30:00 pm
0.03%
Financial Progress

1st Expenditure
of ₹ 9997 (0.10 Lacs ) done.
Cummulative ₹ 0.10Lacs ( against 300.5Lacs )

10 months ago

on Thursday, June 27th 2024, 6:30:00 pm
0.14%
Financial Progress

2nd Expenditure
of ₹ 31800 (0.32 Lacs ) done.
Cummulative ₹ 0.42Lacs ( against 300.5Lacs )

10 months ago

on Monday, July 1st 2024, 3:29:34 am
<span class="4">Picture Id:49659</span>
PWD Uttarakahnd
Photo (ID 49659) from Site Received
Uploader : Anand Dimari, JE Civil (Samvida) ,PD Gopeshwar
Landmark : 10/23
Remark : Material collection work is going on for stoneset pavement at chainage 10/23

10 months ago

on Monday, July 1st 2024, 3:42:32 am
<span class="4">Picture Id:49660</span>
PWD Uttarakahnd
Photo (ID 49660) from Site Received
Uploader : Anand Dimari, JE Civil (Samvida) ,PD Gopeshwar
Landmark : Chainage 10/27-10/28
Remark : Stone set pavement work to be done on chainage 10/27-10/28

10 months ago

on Monday, July 1st 2024, 3:45:06 am
<span class="4">Picture Id:49661</span>
PWD Uttarakahnd
Photo (ID 49661) from Site Received
Uploader : Anand Dimari, JE Civil (Samvida) ,PD Gopeshwar
Landmark : 10/28
Remark : Material collection work is going on for stoneset pavement at chainage 10/28

10 months ago

on Monday, July 1st 2024, 3:55:04 am
<span class="4">Picture Id:49667</span>
PWD Uttarakahnd
Photo (ID 49667) from Site Received
Uploader : Anand Dimari, JE Civil (Samvida) ,PD Gopeshwar
Landmark : 10/20-10/23
Remark : Stone set pavement work to be done on chainage 10/20-10/23

10 months ago

on Wednesday, July 3rd 2024, 2:25:58 am
<span class="4">Picture Id:50132</span>
PWD Uttarakahnd
Photo (ID 50132) from Site Received
Uploader : Anand Dimari, JE Civil (Samvida) ,PD Gopeshwar
Landmark : Km. 13 - 12/20
Remark : Stoneset to be done between km 11 to 15

10 months ago

on Saturday, July 6th 2024, 6:30:00 pm
5%

Physical Progress
Physical Progress Reported at 1st time

9 months ago

on Friday, August 16th 2024, 6:30:00 pm
0.88%
Financial Progress

3rd Expenditure
of ₹ 221425 (2.21 Lacs ) done.
Cummulative ₹ 2.63Lacs ( against 300.5Lacs )

8 months ago

on Tuesday, September 24th 2024, 6:30:00 pm
0.98%
Financial Progress

4th Expenditure
of ₹ 31671 (0.32 Lacs ) done.
Cummulative ₹ 2.95Lacs ( against 300.5Lacs )

8 months ago

on Wednesday, September 25th 2024, 6:30:00 pm
0.98%
Financial Progress

5th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 2.95Lacs ( against 300.5Lacs )

7 months ago

on Sunday, September 29th 2024, 6:30:00 pm
10.15%
Financial Progress

6th Expenditure
of ₹ 2756439 (27.56 Lacs ) done.
Cummulative ₹ 30.51Lacs ( against 300.5Lacs )

6 months ago

on Sunday, October 27th 2024, 6:30:00 pm
10.24%
Financial Progress

7th Expenditure
of ₹ 24662 (0.25 Lacs ) done.
Cummulative ₹ 30.76Lacs ( against 300.5Lacs )

6 months ago

on Monday, October 28th 2024, 6:30:00 pm
10.71%
Financial Progress

8th Expenditure
of ₹ 141600 (1.42 Lacs ) done.
Cummulative ₹ 32.18Lacs ( against 300.5Lacs )

6 months ago

on Monday, November 4th 2024, 6:30:00 pm
15%

Physical Progress
Physical Progress Reported at 2nd time

5 months ago

on Wednesday, November 27th 2024, 6:30:00 pm
10.71%
Financial Progress

9th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 32.18Lacs ( against 300.5Lacs )

5 months ago

on Wednesday, November 27th 2024, 6:30:00 pm
15.71%
Financial Progress

10th Expenditure
of ₹ 1504500 (15.04 Lacs ) done.
Cummulative ₹ 47.22Lacs ( against 300.5Lacs )

5 months ago

on Monday, December 23rd 2024, 6:30:00 pm
22.78%
Financial Progress

12th Expenditure
of ₹ 2123357 (21.23 Lacs ) done.
Cummulative ₹ 68.45Lacs ( against 300.5Lacs )

5 months ago

on Monday, December 23rd 2024, 6:30:00 pm
15.71%
Financial Progress

11th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 47.22Lacs ( against 300.5Lacs )

4 months ago

on Tuesday, December 31st 2024, 6:30:00 pm
25%

Physical Progress
Physical Progress Reported at 3rd time

2 months ago

on Monday, March 17th 2025, 6:30:00 pm
61.36%
Financial Progress

13th Expenditure
of ₹ 11593500 (115.94 Lacs ) done.
Cummulative ₹ 184.39Lacs ( against 300.5Lacs )

2 months ago

on Tuesday, March 18th 2025, 6:30:00 pm
61.36%
Financial Progress

14th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 184.39Lacs ( against 300.5Lacs )

2 months ago

on Saturday, March 22nd 2025, 6:30:00 pm
61.53%
Financial Progress

16th Expenditure
of ₹ 25201 (0.25 Lacs ) done.
Cummulative ₹ 184.89Lacs ( against 300.5Lacs )

2 months ago

on Saturday, March 22nd 2025, 6:30:00 pm
61.44%
Financial Progress

15th Expenditure
of ₹ 24440 (0.24 Lacs ) done.
Cummulative ₹ 184.63Lacs ( against 300.5Lacs )

2 months ago

on Sunday, March 23rd 2025, 6:30:00 pm
61.61%
Financial Progress

17th Expenditure
of ₹ 24440 (0.24 Lacs ) done.
Cummulative ₹ 185.13Lacs ( against 300.5Lacs )

2 months ago

on Monday, March 24th 2025, 6:30:00 pm
61.69%
Financial Progress

18th Expenditure
of ₹ 25201 (0.25 Lacs ) done.
Cummulative ₹ 185.38Lacs ( against 300.5Lacs )

a month ago

on Wednesday, April 2nd 2025, 6:30:00 pm
50%

Physical Progress
Physical Progress Reported at 4th time

a month ago

on Monday, April 14th 2025, 6:30:00 pm
74%

Physical Progress
Physical Progress Reported at 5th time