Work Sanctioned
जिला योजना (पूल्ड आवास) वर्ष 2023-24 के अन्तर्गत जिला अधिकारी, चमोली के आवास में मरम्मत एवं रंग-रोगन तथा कलेक्ट्रट के अन्तर्गत मरम्मत एवं रंगरोगन का कार्य
on Thursday, March 14th 2024, 12:52:30 pm
Technical Sanction
of ₹ 0.8 Lacs
1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. 604/16 C
on Monday, April 1st 2024, 6:30:00 pm
50%
Physical Progress
Physical Progress Reported at 1st time
on Friday, May 3rd 2024, 6:30:00 pm
0.00%
Financial Progress
1st Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 0.00Lacs ( against 16.5Lacs )
on Friday, May 3rd 2024, 6:30:00 pm
4.82%
Financial Progress
2nd Expenditure
of ₹ 79472 (0.79 Lacs ) done.
Cummulative ₹ 0.79Lacs ( against 16.5Lacs )
on Monday, September 30th 2024, 6:30:00 pm
5.94%
Financial Progress
3rd Expenditure
of ₹ 18500 (0.18 Lacs ) done.
Cummulative ₹ 0.98Lacs ( against 16.5Lacs )
on Tuesday, October 29th 2024, 6:30:00 pm
7.41%
Financial Progress
4th Expenditure
of ₹ 24250 (0.24 Lacs ) done.
Cummulative ₹ 1.22Lacs ( against 16.5Lacs )
on Sunday, November 17th 2024, 6:30:00 pm
17.77%
Financial Progress
5th Expenditure
of ₹ 171000 (1.71 Lacs ) done.
Cummulative ₹ 2.93Lacs ( against 16.5Lacs )
on Wednesday, February 26th 2025, 6:30:00 pm
29.27%
Financial Progress
6th Expenditure
of ₹ 189734 (1.90 Lacs ) done.
Cummulative ₹ 4.83Lacs ( against 16.5Lacs )
on Wednesday, February 26th 2025, 6:30:00 pm
58.76%
Financial Progress
7th Expenditure
of ₹ 486650 (4.87 Lacs ) done.
Cummulative ₹ 9.70Lacs ( against 16.5Lacs )
on Friday, February 28th 2025, 6:30:00 pm
87.77%
Financial Progress
8th Expenditure
of ₹ 478661 (4.79 Lacs ) done.
Cummulative ₹ 14.48Lacs ( against 16.5Lacs )
on Monday, March 17th 2025, 6:30:00 pm
89.26%
Financial Progress
9th Expenditure
of ₹ 24600 (0.25 Lacs ) done.
Cummulative ₹ 14.73Lacs ( against 16.5Lacs )
on Monday, March 24th 2025, 6:30:00 pm
100%
Physical Progress
Physical Progress Reported at 2nd time
on Thursday, March 27th 2025, 6:30:00 pm
89.91%
Financial Progress
10th Expenditure
of ₹ 10620 (0.11 Lacs ) done.
Cummulative ₹ 14.83Lacs ( against 16.5Lacs )