15 years ago

on Thursday, March 11th 2010, 6:30:00 pm
Work Sanctioned
अटल आदर्श ग्राम योजनान्तर्गत जनपद चमोली के विकासखण्ड जोशीमठ में न्याय पंचायत मुख्य ग्राम द्वींग को मोटर मार्ग से जोड़े जाने का कार्य

7 years ago

on Monday, December 31st 2018, 6:30:00 pm
8.28%
Financial Progress

1st Expenditure
of ₹ 2945000 (29.45 Lacs ) done.
Cummulative ₹ 29.45Lacs ( against 355.54Lacs )

4 years ago

on Sunday, February 28th 2021, 6:30:00 pm
9.17%
Financial Progress

2nd Expenditure
of ₹ 314000 (3.14 Lacs ) done.
Cummulative ₹ 32.59Lacs ( against 355.54Lacs )

4 years ago

on Sunday, April 4th 2021, 6:30:00 pm

Technical Sanction
of ₹ 330.74 Lacs

1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. CE Pauri Letter No- 1809/7(65) Yata

4 years ago

on Wednesday, June 9th 2021, 6:30:00 pm
13.07%
Financial Progress

3rd Expenditure
of ₹ 1389000 (13.89 Lacs ) done.
Cummulative ₹ 46.48Lacs ( against 355.54Lacs )

4 years ago

on Wednesday, September 29th 2021, 6:30:00 pm
18.93%
Financial Progress

4th Expenditure
of ₹ 2083260 (20.83 Lacs ) done.
Cummulative ₹ 67.31Lacs ( against 355.54Lacs )

4 years ago

on Saturday, November 13th 2021, 6:30:00 pm
25%

Physical Progress
Physical Progress Reported at 1st time

4 years ago

on Monday, November 29th 2021, 6:30:00 pm
24.71%
Financial Progress

6th Expenditure
of ₹ 1880194 (18.80 Lacs ) done.
Cummulative ₹ 87.86Lacs ( against 355.54Lacs )

4 years ago

on Monday, November 29th 2021, 6:30:00 pm
19.42%
Financial Progress

5th Expenditure
of ₹ 174876 (1.75 Lacs ) done.
Cummulative ₹ 69.06Lacs ( against 355.54Lacs )

4 years ago

on Thursday, December 30th 2021, 6:30:00 pm
24.88%
Financial Progress

7th Expenditure
of ₹ 61000 (0.61 Lacs ) done.
Cummulative ₹ 88.47Lacs ( against 355.54Lacs )

4 years ago

on Wednesday, January 26th 2022, 6:30:00 pm
40%

Physical Progress
Physical Progress Reported at 2nd time

4 years ago

on Thursday, January 27th 2022, 6:30:00 pm
45%

Physical Progress
Physical Progress Reported at 3rd time

4 years ago

on Tuesday, February 22nd 2022, 6:30:00 pm
25.73%
Financial Progress

8th Expenditure
of ₹ 300000 (3.00 Lacs ) done.
Cummulative ₹ 91.47Lacs ( against 355.54Lacs )

3 years ago

on Sunday, February 27th 2022, 6:30:00 pm
42.13%
Financial Progress

9th Expenditure
of ₹ 5832979 (58.33 Lacs ) done.
Cummulative ₹ 149.80Lacs ( against 355.54Lacs )

3 years ago

on Wednesday, March 30th 2022, 6:30:00 pm
46.40%
Financial Progress

10th Expenditure
of ₹ 1515827 (15.16 Lacs ) done.
Cummulative ₹ 164.96Lacs ( against 355.54Lacs )

3 years ago

on Sunday, April 3rd 2022, 6:30:00 pm
55%

Physical Progress
Physical Progress Reported at 4th time

3 years ago

on Saturday, July 30th 2022, 6:30:00 pm
47.94%
Financial Progress

11th Expenditure
of ₹ 549000 (5.49 Lacs ) done.
Cummulative ₹ 170.45Lacs ( against 355.54Lacs )

3 years ago

on Thursday, August 11th 2022, 6:30:00 pm
60%

Physical Progress
Physical Progress Reported at 5th time

3 years ago

on Tuesday, August 30th 2022, 6:30:00 pm
48.29%
Financial Progress

12th Expenditure
of ₹ 123546 (1.24 Lacs ) done.
Cummulative ₹ 171.69Lacs ( against 355.54Lacs )

3 years ago

on Thursday, September 29th 2022, 6:30:00 pm
48.57%
Financial Progress

13th Expenditure
of ₹ 100000 (1.00 Lacs ) done.
Cummulative ₹ 172.69Lacs ( against 355.54Lacs )

3 years ago

on Tuesday, November 29th 2022, 6:30:00 pm
48.65%
Financial Progress

14th Expenditure
of ₹ 27900 (0.28 Lacs ) done.
Cummulative ₹ 172.97Lacs ( against 355.54Lacs )

3 years ago

on Friday, December 30th 2022, 6:30:00 pm
49.02%
Financial Progress

15th Expenditure
of ₹ 133675 (1.34 Lacs ) done.
Cummulative ₹ 174.30Lacs ( against 355.54Lacs )

2 years ago

on Monday, February 27th 2023, 6:30:00 pm
49.12%
Financial Progress

16th Expenditure
of ₹ 33661 (0.34 Lacs ) done.
Cummulative ₹ 174.64Lacs ( against 355.54Lacs )

2 years ago

on Thursday, March 30th 2023, 6:30:00 pm
83.25%
Financial Progress

17th Expenditure
of ₹ 12133320 (121.33 Lacs ) done.
Cummulative ₹ 295.97Lacs ( against 355.54Lacs )

2 years ago

on Wednesday, April 19th 2023, 6:30:00 pm
100%

Physical Progress
Physical Progress Reported at 6th time

2 years ago

on Thursday, June 29th 2023, 6:30:00 pm
83.25%
Financial Progress

18th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 295.97Lacs ( against 355.54Lacs )

2 years ago

on Thursday, June 29th 2023, 6:30:00 pm
84.00%
Financial Progress

19th Expenditure
of ₹ 268800 (2.69 Lacs ) done.
Cummulative ₹ 298.66Lacs ( against 355.54Lacs )

2 years ago

on Friday, September 29th 2023, 6:30:00 pm
84.09%
Financial Progress

20th Expenditure
of ₹ 31453 (0.31 Lacs ) done.
Cummulative ₹ 298.97Lacs ( against 355.54Lacs )

a year ago

on Monday, March 11th 2024, 6:30:00 pm
84.65%
Financial Progress

21st Expenditure
of ₹ 199879 (2.00 Lacs ) done.
Cummulative ₹ 300.97Lacs ( against 355.54Lacs )

a year ago

on Monday, March 18th 2024, 6:30:00 pm
84.70%
Financial Progress

24th Expenditure
of ₹ 5077 (0.05 Lacs ) done.
Cummulative ₹ 301.16Lacs ( against 355.54Lacs )

a year ago

on Monday, March 18th 2024, 6:30:00 pm
84.69%
Financial Progress

23rd Expenditure
of ₹ 8143 (0.08 Lacs ) done.
Cummulative ₹ 301.10Lacs ( against 355.54Lacs )

a year ago

on Monday, March 18th 2024, 6:30:00 pm
85.30%
Financial Progress

25th Expenditure
of ₹ 213788 (2.14 Lacs ) done.
Cummulative ₹ 303.29Lacs ( against 355.54Lacs )

a year ago

on Monday, March 18th 2024, 6:30:00 pm
84.67%
Financial Progress

22nd Expenditure
of ₹ 4921 (0.05 Lacs ) done.
Cummulative ₹ 301.02Lacs ( against 355.54Lacs )

a year ago

on Tuesday, March 19th 2024, 6:30:00 pm
85.32%
Financial Progress

26th Expenditure
of ₹ 5376 (0.05 Lacs ) done.
Cummulative ₹ 303.35Lacs ( against 355.54Lacs )

a year ago

on Sunday, March 24th 2024, 6:30:00 pm
86.00%
Financial Progress

27th Expenditure
of ₹ 243523 (2.44 Lacs ) done.
Cummulative ₹ 305.78Lacs ( against 355.54Lacs )

a year ago

on Sunday, March 24th 2024, 6:30:00 pm
86.70%
Financial Progress

28th Expenditure
of ₹ 246665 (2.47 Lacs ) done.
Cummulative ₹ 308.25Lacs ( against 355.54Lacs )

a year ago

on Monday, July 29th 2024, 6:30:00 pm
86.90%
Financial Progress

29th Expenditure
of ₹ 70800 (0.71 Lacs ) done.
Cummulative ₹ 308.96Lacs ( against 355.54Lacs )

a year ago

on Sunday, August 11th 2024, 6:30:00 pm
86.94%
Financial Progress

30th Expenditure
of ₹ 16200 (0.16 Lacs ) done.
Cummulative ₹ 309.12Lacs ( against 355.54Lacs )

10 months ago

on Monday, October 28th 2024, 6:30:00 pm
86.94%
Financial Progress

31st Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 309.12Lacs ( against 355.54Lacs )

10 months ago

on Monday, October 28th 2024, 6:30:00 pm
87.64%
Financial Progress

32nd Expenditure
of ₹ 246384 (2.46 Lacs ) done.
Cummulative ₹ 311.58Lacs ( against 355.54Lacs )

9 months ago

on Thursday, November 28th 2024, 6:30:00 pm
87.73%
Financial Progress

33rd Expenditure
of ₹ 32860 (0.33 Lacs ) done.
Cummulative ₹ 311.91Lacs ( against 355.54Lacs )

8 months ago

on Monday, December 23rd 2024, 6:30:00 pm
87.75%
Financial Progress

34th Expenditure
of ₹ 9236 (0.09 Lacs ) done.
Cummulative ₹ 312.00Lacs ( against 355.54Lacs )

7 months ago

on Tuesday, January 14th 2025, 6:30:00 pm
87.90%
Financial Progress

35th Expenditure
of ₹ 50000 (0.50 Lacs ) done.
Cummulative ₹ 312.50Lacs ( against 355.54Lacs )

5 months ago

on Tuesday, March 18th 2025, 6:30:00 pm
87.99%
Financial Progress

37th Expenditure
of ₹ 13924 (0.14 Lacs ) done.
Cummulative ₹ 312.85Lacs ( against 355.54Lacs )

5 months ago

on Tuesday, March 18th 2025, 6:30:00 pm
87.95%
Financial Progress

36th Expenditure
of ₹ 20886 (0.21 Lacs ) done.
Cummulative ₹ 312.71Lacs ( against 355.54Lacs )

5 months ago

on Friday, March 21st 2025, 6:30:00 pm
87.99%
Financial Progress

38th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 312.85Lacs ( against 355.54Lacs )

5 months ago

on Saturday, March 22nd 2025, 6:30:00 pm
88.69%
Financial Progress

39th Expenditure
of ₹ 246384 (2.46 Lacs ) done.
Cummulative ₹ 315.32Lacs ( against 355.54Lacs )