19 years ago

on Monday, September 25th 2006, 6:30:00 pm
Work Sanctioned
कैंची हरतपा मोटर मार्ग के किमी0 4 से तितोली तक मोटर मार्ग का निर्माण

17 years ago

on Saturday, February 28th 2009, 6:30:00 pm
0.07%
Financial Progress

1st Expenditure
of ₹ 17000 (0.17 Lacs ) done.
Cummulative ₹ 0.17Lacs ( against 228.57Lacs )

16 years ago

on Sunday, February 28th 2010, 6:30:00 pm
0.81%
Financial Progress

2nd Expenditure
of ₹ 167085 (1.67 Lacs ) done.
Cummulative ₹ 1.84Lacs ( against 228.57Lacs )

15 years ago

on Tuesday, November 30th 2010, 6:30:00 pm
0.83%
Financial Progress

3rd Expenditure
of ₹ 5000 (0.05 Lacs ) done.
Cummulative ₹ 1.89Lacs ( against 228.57Lacs )

8 years ago

on Saturday, September 30th 2017, 6:30:00 pm
1.34%
Financial Progress

4th Expenditure
of ₹ 116942 (1.17 Lacs ) done.
Cummulative ₹ 3.06Lacs ( against 228.57Lacs )

8 years ago

on Tuesday, October 31st 2017, 6:30:00 pm
1.37%
Financial Progress

5th Expenditure
of ₹ 7500 (0.07 Lacs ) done.
Cummulative ₹ 3.14Lacs ( against 228.57Lacs )

8 years ago

on Sunday, December 31st 2017, 6:30:00 pm
1.81%
Financial Progress

6th Expenditure
of ₹ 101147 (1.01 Lacs ) done.
Cummulative ₹ 4.15Lacs ( against 228.57Lacs )

7 years ago

on Monday, April 23rd 2018, 6:30:00 pm

Technical Sanction
of ₹ 104.4 Lacs

1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. 1786/573C-02/17

7 years ago

on Saturday, June 30th 2018, 6:30:00 pm
1.84%
Financial Progress

7th Expenditure
of ₹ 6663 (0.07 Lacs ) done.
Cummulative ₹ 4.21Lacs ( against 228.57Lacs )

7 years ago

on Wednesday, October 31st 2018, 6:30:00 pm
2.12%
Financial Progress

8th Expenditure
of ₹ 62349 (0.62 Lacs ) done.
Cummulative ₹ 4.84Lacs ( against 228.57Lacs )

7 years ago

on Friday, November 30th 2018, 6:30:00 pm
6.37%
Financial Progress

9th Expenditure
of ₹ 972643 (9.73 Lacs ) done.
Cummulative ₹ 14.56Lacs ( against 228.57Lacs )

7 years ago

on Thursday, February 28th 2019, 6:30:00 pm
6.37%
Financial Progress

10th Expenditure
of ₹ 480 (0.00 Lacs ) done.
Cummulative ₹ 14.57Lacs ( against 228.57Lacs )

6 years ago

on Monday, September 30th 2019, 6:30:00 pm
12.26%
Financial Progress

11th Expenditure
of ₹ 1344471 (13.44 Lacs ) done.
Cummulative ₹ 28.01Lacs ( against 228.57Lacs )

6 years ago

on Friday, January 31st 2020, 6:30:00 pm
12.47%
Financial Progress

12th Expenditure
of ₹ 49350 (0.49 Lacs ) done.
Cummulative ₹ 28.51Lacs ( against 228.57Lacs )

5 years ago

on Sunday, May 31st 2020, 6:30:00 pm
20.10%
Financial Progress

13th Expenditure
of ₹ 1743546 (17.44 Lacs ) done.
Cummulative ₹ 45.94Lacs ( against 228.57Lacs )

5 years ago

on Tuesday, June 30th 2020, 6:30:00 pm
20.31%
Financial Progress

14th Expenditure
of ₹ 48725 (0.49 Lacs ) done.
Cummulative ₹ 46.43Lacs ( against 228.57Lacs )

5 years ago

on Thursday, December 31st 2020, 6:30:00 pm
20.50%
Financial Progress

15th Expenditure
of ₹ 42138 (0.42 Lacs ) done.
Cummulative ₹ 46.85Lacs ( against 228.57Lacs )

5 years ago

on Sunday, February 28th 2021, 6:30:00 pm
24.35%
Financial Progress

16th Expenditure
of ₹ 879785 (8.80 Lacs ) done.
Cummulative ₹ 55.65Lacs ( against 228.57Lacs )

4 years ago

on Monday, July 26th 2021, 6:30:00 pm
26.11%
Financial Progress

17th Expenditure
of ₹ 403426 (4.03 Lacs ) done.
Cummulative ₹ 59.68Lacs ( against 228.57Lacs )

4 years ago

on Saturday, September 25th 2021, 10:12:13 am

Technical Sanction
of ₹ 124.17 Lacs

2nd Technical Sanction of Work after survey,detailed design and analysis by Latter No. 4002/573C

4 years ago

on Wednesday, September 29th 2021, 6:30:00 pm
28.96%
Financial Progress

18th Expenditure
of ₹ 651771 (6.52 Lacs ) done.
Cummulative ₹ 66.20Lacs ( against 228.57Lacs )

4 years ago

on Thursday, December 30th 2021, 6:30:00 pm
29.37%
Financial Progress

19th Expenditure
of ₹ 92418 (0.92 Lacs ) done.
Cummulative ₹ 67.12Lacs ( against 228.57Lacs )

4 years ago

on Sunday, January 30th 2022, 6:30:00 pm
33.29%
Financial Progress

20th Expenditure
of ₹ 896890 (8.97 Lacs ) done.
Cummulative ₹ 76.09Lacs ( against 228.57Lacs )

4 years ago

on Sunday, February 27th 2022, 6:30:00 pm
33.41%
Financial Progress

21st Expenditure
of ₹ 27875 (0.28 Lacs ) done.
Cummulative ₹ 76.37Lacs ( against 228.57Lacs )

3 years ago

on Wednesday, March 30th 2022, 6:30:00 pm
36.44%
Financial Progress

22nd Expenditure
of ₹ 691284 (6.91 Lacs ) done.
Cummulative ₹ 83.28Lacs ( against 228.57Lacs )

3 years ago

on Friday, July 29th 2022, 6:30:00 pm
42.11%
Financial Progress

23rd Expenditure
of ₹ 1297296 (12.97 Lacs ) done.
Cummulative ₹ 96.26Lacs ( against 228.57Lacs )

3 years ago

on Thursday, September 22nd 2022, 10:31:49 am
<span class="4">Picture Id:8119</span>
PWD Uttarakahnd
Photo (ID 8119) from Site Received
Uploader : Deepak Gupta, Superintending Engineer Civil ,Engineer-in-Chief Office
Landmark : Km 3 Ch 2.5000 km
Remark : Hill side cutting

3 years ago

on Thursday, September 22nd 2022, 10:43:49 am
<span class="4">Picture Id:8120</span>
PWD Uttarakahnd
Photo (ID 8120) from Site Received
Uploader : Deepak Gupta, Superintending Engineer Civil ,Engineer-in-Chief Office
Landmark : Km 3 Ch 2.5000 km
Remark : Hill side cutting

3 years ago

on Thursday, September 29th 2022, 6:30:00 pm
49.03%
Financial Progress

24th Expenditure
of ₹ 1580726 (15.81 Lacs ) done.
Cummulative ₹ 112.07Lacs ( against 228.57Lacs )

3 years ago

on Friday, December 30th 2022, 6:30:00 pm
53.57%
Financial Progress

25th Expenditure
of ₹ 1038318 (10.38 Lacs ) done.
Cummulative ₹ 122.45Lacs ( against 228.57Lacs )

3 years ago

on Monday, February 27th 2023, 6:14:08 am
<span class="4">Picture Id:17671</span>
PWD Uttarakahnd
Photo (ID 17671) from Site Received
Uploader : Deepak Gupta, Superintending Engineer Civil ,Engineer-in-Chief Office
Landmark : Km 4 HM 0 to 2 , 3/3
Remark : New construction of road Construction of Culvert in progress

3 years ago

on Monday, February 27th 2023, 6:30:00 pm
64.03%
Financial Progress

26th Expenditure
of ₹ 2389680 (23.90 Lacs ) done.
Cummulative ₹ 146.35Lacs ( against 228.57Lacs )

2 years ago

on Thursday, March 30th 2023, 6:30:00 pm
72.00%
Financial Progress

27th Expenditure
of ₹ 1821743 (18.22 Lacs ) done.
Cummulative ₹ 164.56Lacs ( against 228.57Lacs )

2 years ago

on Sunday, July 30th 2023, 6:30:00 pm
72.39%
Financial Progress

28th Expenditure
of ₹ 89600 (0.90 Lacs ) done.
Cummulative ₹ 165.46Lacs ( against 228.57Lacs )

2 years ago

on Monday, September 18th 2023, 6:30:00 pm
72.41%
Financial Progress

29th Expenditure
of ₹ 5102 (0.05 Lacs ) done.
Cummulative ₹ 165.51Lacs ( against 228.57Lacs )

2 years ago

on Thursday, October 5th 2023, 6:30:00 pm
40%

Physical Progress
Physical Progress Reported at 1st time

2 years ago

on Monday, October 30th 2023, 6:30:00 pm
73.06%
Financial Progress

30th Expenditure
of ₹ 149315 (1.49 Lacs ) done.
Cummulative ₹ 167.00Lacs ( against 228.57Lacs )

2 years ago

on Tuesday, October 31st 2023, 6:30:00 pm
80%

Physical Progress
Physical Progress Reported at 2nd time

2 years ago

on Wednesday, November 29th 2023, 6:30:00 pm
75.26%
Financial Progress

31st Expenditure
of ₹ 502813 (5.03 Lacs ) done.
Cummulative ₹ 172.03Lacs ( against 228.57Lacs )

2 years ago

on Friday, December 15th 2023, 6:30:00 pm
79.68%
Financial Progress

32nd Expenditure
of ₹ 1008329 (10.08 Lacs ) done.
Cummulative ₹ 182.11Lacs ( against 228.57Lacs )

2 years ago

on Wednesday, January 31st 2024, 6:30:00 pm
85.74%
Financial Progress

33rd Expenditure
of ₹ 1385662 (13.86 Lacs ) done.
Cummulative ₹ 195.97Lacs ( against 228.57Lacs )

a year ago

on Wednesday, March 13th 2024, 6:30:00 pm
90.64%
Financial Progress

34th Expenditure
of ₹ 1121088 (11.21 Lacs ) done.
Cummulative ₹ 207.18Lacs ( against 228.57Lacs )

a year ago

on Wednesday, March 20th 2024, 6:30:00 pm
94.24%
Financial Progress

35th Expenditure
of ₹ 821828 (8.22 Lacs ) done.
Cummulative ₹ 215.40Lacs ( against 228.57Lacs )

a year ago

on Monday, April 1st 2024, 6:30:00 pm
100%

Physical Progress
Physical Progress Reported at 3rd time

a year ago

on Thursday, May 30th 2024, 6:30:00 pm
96.50%
Financial Progress

36th Expenditure
of ₹ 516081 (5.16 Lacs ) done.
Cummulative ₹ 220.56Lacs ( against 228.57Lacs )

a year ago

on Saturday, June 29th 2024, 6:30:00 pm
96.56%
Financial Progress

37th Expenditure
of ₹ 15576 (0.16 Lacs ) done.
Cummulative ₹ 220.72Lacs ( against 228.57Lacs )

a year ago

on Monday, July 29th 2024, 6:30:00 pm
96.64%
Financial Progress

38th Expenditure
of ₹ 18000 (0.18 Lacs ) done.
Cummulative ₹ 220.90Lacs ( against 228.57Lacs )

a year ago

on Sunday, September 29th 2024, 6:30:00 pm
96.70%
Financial Progress

39th Expenditure
of ₹ 12990 (0.13 Lacs ) done.
Cummulative ₹ 221.03Lacs ( against 228.57Lacs )

5 months ago

on Sunday, March 23rd 2025, 6:30:00 pm
99.38%
Financial Progress

40th Expenditure
of ₹ 613600 (6.14 Lacs ) done.
Cummulative ₹ 227.16Lacs ( against 228.57Lacs )

2 months ago

on Sunday, June 29th 2025, 6:30:00 pm
99.53%
Financial Progress

41st Expenditure
of ₹ 32392 (0.32 Lacs ) done.
Cummulative ₹ 227.49Lacs ( against 228.57Lacs )