Refresh data
on Thursday, February 28th 2013, 6:30:00 pm
0.26%
Financial Progress
1st Expenditure
of ₹ 9725 (0.10 Lacs ) done.
Cummulative ₹ 0.10Lacs ( against 37.8Lacs )
on Thursday, March 21st 2013, 6:30:00 pm
Work Sanctioned
जनपद नैनीताल में विधान सभा क्षेत्र कालाढूंगी में आमपड़ाव से चैपडा तक मोटर मार्ग का नव निर्माण का कार्य
on Wednesday, July 31st 2013, 6:30:00 pm
0.52%
Financial Progress
2nd Expenditure
of ₹ 10100 (0.10 Lacs ) done.
Cummulative ₹ 0.20Lacs ( against 37.8Lacs )
on Saturday, November 30th 2013, 6:30:00 pm
0.77%
Financial Progress
3rd Expenditure
of ₹ 9457 (0.09 Lacs ) done.
Cummulative ₹ 0.29Lacs ( against 37.8Lacs )
on Tuesday, December 31st 2013, 6:30:00 pm
0.85%
Financial Progress
4th Expenditure
of ₹ 2845 (0.03 Lacs ) done.
Cummulative ₹ 0.32Lacs ( against 37.8Lacs )