Work Sanctioned
राज्य योजना के अन्तर्गत जनपद नैनीताल के विधानसभा क्षेत्र नैनीताल के नैनीताल कालाढूॅगी मोटर मार्ग के किमी0 20 से नलनी तक हल्का वाहन मार्ग का पुनः निर्माण कार्य
on Sunday, January 17th 2021, 6:30:00 pm
Technical Sanction
of ₹ 179.08 Lacs
1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. 239/575C-2/2020
on Sunday, February 28th 2021, 6:30:00 pm
9.11%
Financial Progress
1st Expenditure
of ₹ 1631718 (16.32 Lacs ) done.
Cummulative ₹ 16.32Lacs ( against 179.08Lacs )
on Monday, July 26th 2021, 6:30:00 pm
17.92%
Financial Progress
2nd Expenditure
of ₹ 1577993 (15.78 Lacs ) done.
Cummulative ₹ 32.10Lacs ( against 179.08Lacs )
on Monday, November 29th 2021, 6:30:00 pm
20.02%
Financial Progress
3rd Expenditure
of ₹ 375380 (3.75 Lacs ) done.
Cummulative ₹ 35.85Lacs ( against 179.08Lacs )
on Sunday, January 30th 2022, 6:30:00 pm
20.37%
Financial Progress
4th Expenditure
of ₹ 63066 (0.63 Lacs ) done.
Cummulative ₹ 36.48Lacs ( against 179.08Lacs )
on Sunday, February 27th 2022, 6:30:00 pm
31.50%
Financial Progress
5th Expenditure
of ₹ 1992190 (19.92 Lacs ) done.
Cummulative ₹ 56.40Lacs ( against 179.08Lacs )
on Friday, July 29th 2022, 6:30:00 pm
42.60%
Financial Progress
6th Expenditure
of ₹ 1987912 (19.88 Lacs ) done.
Cummulative ₹ 76.28Lacs ( against 179.08Lacs )
on Monday, August 29th 2022, 2:03:09 am
PWD UttarakahndPhoto (ID 8033) from Site Received
Uploader : Govind Singh Janoti, Assistant Engineer Civil ,PD Nainital
Landmark : 1.525
Remark : Testing of soling
on Tuesday, September 20th 2022, 1:32:48 am
PWD UttarakahndPhoto (ID 8058) from Site Received
Uploader : Deepak Gupta, Superintending Engineer Civil ,NH Div Dehradun
Landmark : Km 2 Chainage 1.525 Km
Remark : Improvement work collection of WBM G2
on Tuesday, September 20th 2022, 1:37:15 am
PWD UttarakahndPhoto (ID 8036) from Site Received
Uploader : Govind Singh Janoti, Assistant Engineer Civil ,PD Nainital
Landmark : .500
Remark : Inspection of top coat
on Thursday, September 29th 2022, 6:30:00 pm
42.85%
Financial Progress
7th Expenditure
of ₹ 46000 (0.46 Lacs ) done.
Cummulative ₹ 76.74Lacs ( against 179.08Lacs )
on Sunday, October 30th 2022, 6:30:00 pm
45.12%
Financial Progress
8th Expenditure
of ₹ 405319 (4.05 Lacs ) done.
Cummulative ₹ 80.80Lacs ( against 179.08Lacs )
on Tuesday, November 29th 2022, 6:30:00 pm
51.56%
Financial Progress
9th Expenditure
of ₹ 1153831 (11.54 Lacs ) done.
Cummulative ₹ 92.33Lacs ( against 179.08Lacs )
on Wednesday, December 7th 2022, 12:41:33 am
PWD UttarakahndPhoto (ID 14518) from Site Received
Uploader : Govind Singh Janoti, Assistant Engineer Civil ,PD Nainital
Landmark : Km 1 ch 150
Remark : Site inspection by se sir
on Tuesday, December 20th 2022, 12:10:44 am
PWD UttarakahndPhoto (ID 15681) from Site Received
Uploader : Deepak Gupta, Superintending Engineer Civil ,NH Div Dehradun
Landmark : Km 1 HM 0/2
Remark : Sample collection for WBM
on Tuesday, December 20th 2022, 1:20:25 am
PWD UttarakahndPhoto (ID 14516) from Site Received
Uploader : Deepak Gupta, Superintending Engineer Civil ,NH Div Dehradun
Landmark : Km 2 HM 6 to 8
Remark : Quality control check by SE sir 2nd circle, PWD Nainital
on Friday, December 30th 2022, 6:30:00 pm
51.62%
Financial Progress
10th Expenditure
of ₹ 9840 (0.10 Lacs ) done.
Cummulative ₹ 92.43Lacs ( against 179.08Lacs )
on Monday, January 30th 2023, 6:30:00 pm
51.73%
Financial Progress
11th Expenditure
of ₹ 19993 (0.20 Lacs ) done.
Cummulative ₹ 92.63Lacs ( against 179.08Lacs )
on Friday, February 24th 2023, 4:54:22 am
PWD UttarakahndPhoto (ID 19109) from Site Received
Uploader : Govind Singh Janoti, Assistant Engineer Civil ,PD Nainital
Landmark : Km 2 ch 400 to 500
Remark : PC work ower wbm
on Monday, February 27th 2023, 6:30:00 pm
60.22%
Financial Progress
12th Expenditure
of ₹ 1521100 (15.21 Lacs ) done.
Cummulative ₹ 107.84Lacs ( against 179.08Lacs )
on Thursday, March 30th 2023, 6:30:00 pm
76.03%
Financial Progress
13th Expenditure
of ₹ 2831788 (28.32 Lacs ) done.
Cummulative ₹ 136.16Lacs ( against 179.08Lacs )
on Friday, April 7th 2023, 12:28:28 am
PWD UttarakahndPhoto (ID 19113) from Site Received
Uploader : Deepak Gupta, Superintending Engineer Civil ,NH Div Dehradun
Landmark : Km 2 h m 6 to 8
Remark : P C work
on Sunday, July 30th 2023, 6:30:00 pm
92.46%
Financial Progress
14th Expenditure
of ₹ 2941240 (29.41 Lacs ) done.
Cummulative ₹ 165.57Lacs ( against 179.08Lacs )
on Wednesday, August 30th 2023, 6:30:00 pm
92.61%
Financial Progress
15th Expenditure
of ₹ 26883 (0.27 Lacs ) done.
Cummulative ₹ 165.84Lacs ( against 179.08Lacs )
on Thursday, October 5th 2023, 6:30:00 pm
100%
Physical Progress
Physical Progress Reported at 1st time
on Wednesday, February 28th 2024, 6:30:00 pm
93.99%
Financial Progress
16th Expenditure
of ₹ 247345 (2.47 Lacs ) done.
Cummulative ₹ 168.32Lacs ( against 179.08Lacs )
on Thursday, May 30th 2024, 6:30:00 pm
98.73%
Financial Progress
17th Expenditure
of ₹ 849327 (8.49 Lacs ) done.
Cummulative ₹ 176.81Lacs ( against 179.08Lacs )
on Friday, December 13th 2024, 6:30:00 pm
99.99%
Financial Progress
18th Expenditure
of ₹ 225851 (2.26 Lacs ) done.
Cummulative ₹ 179.07Lacs ( against 179.08Lacs )