Administrative Approval Detail : 2200/।।।(2)/16-57(एम0एल0ए0)/ 2016 दिं0 22.07.2016
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
72.50
Resanction Cost :
72.50
Tentative Cost :
72.50
Exp. Upto Last Fy :
3.38
For CFY 2025-2026
Remaining :
69.12
Demand :
35.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
3.38
Phase1 DPR Submitted
Sanction on : 9 years 2 weeks ago
22 Jul 2016
Physical Progress:
At start of FY 2025-2026 :
20 %
Up to Date :
20 %
Tentative Completion date on : 4 months 1 week ago
31 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Pending With-SG for verifying Compliance of Conditions -- as on 05-Aug-2025