Work Profile Report [10W26]

जनपद नैनीताल में ग्राम जैैना से चन्द्रकोट धूरा मोटर मार्ग का निर्माण
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Forest
  • Remarks
  • Tenders

  • Aggrements
  • Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : शा0सं0 547/।।।- (2)/09-44 (प्रा0आ0) /08 दि0 11/2/09

TS Amount (lakhs) : 175 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

175.00

Resanction Cost :

175.00

Tentative Cost :

125.00

Saving

50.00

Exp. Upto Last Fy :

114.59

For CFY 2024-2025

Remaining :

60.41

Demand :

5.43

Allotment :

3.93

Exp in CFY :

3.93

Total Up to Date Exp :

118.51

Construction Started

Sanction on : 15 years 10 months ago

11 Feb 2009

Physical Progress:

At start of FY 2024-2025 :

45 %

Up to Date :

45 %

Tentative Completion date on : 3 months 6 days from now

31 Mar 2025

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Road [Km]
5
2
2.000
0
0.000
0.000

Remark

view all

क्षतिपूरक वृक्षारोपण हेतु चयनित स्थल को वन संरक्षित घोषित किये जाने के लिये नोटिफिकेशन संबंधित कार्यवाही हेतु स्थल का संयुक्त निरीक्षण, जिलाधिकारी के आदेश पत्र एवं अमल दरामद की खतौनी की प्रतियों सहित आख्या इस कार्यालय के पत्रांक 1802/ 15 एम0जी0 दिनांक 07.09.2024 द्वारा कार्यालय प्रभागीय वनाधिकारी नैनीताल को विधिवत स्वीकृति प्राप्त किये जाने हेतु आवश्यक कार्यवाही के लिये प्रेषित। -- as on 18-Sep-2024

Rating : 70

Forest Case Pending At : 13: AIP DFO

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI: