Work Profile Report [10W398]
Tenders
Project Activities
alerts
Samples
Administrative Approval Detail : PWD2/BUD/ANBU/37/2022-III-2-PUBLIC WORKS DEPARTMENT E-FILE NO. 54192/57 DT. 17-12-2024
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
323.69
Resanction Cost :
323.69
Tentative Cost :
323.69
Exp. Upto Last Fy :
0.10
For CFY 2025-2026
Remaining :
323.59
Demand :
300.00
Allotment :
323.59
Exp in CFY :
330.92
Total Up to Date Exp :
331.02
Construction Started
Sanction on : 11 months 5 days ago
17 Dec 2024
Physical Progress:
At start of FY 2025-2026 :
1 %
Up to Date :
75 %
Tentative Completion date on : 4 months 5 days from now
28 Mar 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
जी0एस0बी0, जी2, जी3 का कार्य पूर्ण एवं पी0सी0 3.50 कि0मी0 में पूर्ण, शेष कार्य प्रगति में। -- as on 31-Oct-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: