Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.9 | 1.9 | 1.9 | 0 |
11W562 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : उत्तराखण्ड शासन लोक निर्माण अनुभाग-2 का ई-फाईल संख्या 50841 दिनांक 28.03.2023
TS Amount (lakhs) : 93.02 Lacs
Financial Detail
Sanction Cost : 93.02 Lacs
Resanction Cost : 93.02 Lacs
Exp. Upto Last Fy : 74.24 Lacs
For CFY 2024-2025
Remaining : 18.78 Lacs
Demand : 15.00 Lacs
Allotment : 15.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 74.24 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 92 %
Up to Date : 92 %
Sanction on :
1 year 1 month ago
28 Mar 2023
Tentative Completion date:
1 month 1 week from now
30 Jun 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
दीवारों का कार्य गतिमान हैं। -- as on 19-Jan-2024
Physical Peramenters