Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.3 | 1.3 | 0.000 | 1.3 | 1.300 | 0.000 |
11W574 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : उत्तराखण्ड लो0नि0 अनुभाग-2 के शासनादेश संख्या - ई0 फाईल संख्या- 51071 लोक निर्माण अनुभाग-2 दिनांक 12.09.2023
TS Amount (lakhs) : 59.89 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
59.89
Resanction Cost :
59.89
Tentative Cost :
59.89
Exp. Upto Last Fy : 36.49
For CFY 2024-2025
Remaining : 23.40
Demand : 21.70
Allotment : 10.00
Exp in CFY : 0.00
Total Up to Date Exp : 36.49
Construction Started
Physical Progress:
At start of FY 2024-2025 : 45 %
Up to Date : 65 %
Sanction on :
10 months 5 days ago
12 Sep 2023
Tentative Completion date:
3 months 1 week from now
31 Oct 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
जी0 3 का कार्य पूर्ण। -- as on 04-May-2024
Physical Peramenters