Work Profile Report [11W663]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शासनादेश संख्या ई-फाईल संख्या 56165/61 लोक निर्माण अनुभाग-2 दिनांक 20.01.2025
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
49.00
Resanction Cost :
49.00
Tentative Cost :
49.00
Exp. Upto Last Fy :
0.10
For CFY 2025-2026
Remaining :
48.90
Demand :
45.00
Allotment :
45.00
Exp in CFY :
2.43
Total Up to Date Exp :
2.53
Construction Started
Sanction on : 5 months 1 week ago
20 Jan 2025
Physical Progress:
At start of FY 2025-2026 :
1 %
Up to Date :
6 %
Tentative Completion date on : 2 months 3 days from now
31 Aug 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य प्रारंभ। -- as on 09-May-2025