Work Profile Report [11W671]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : G.O. No. 1340 (1)/XXXVI(2)/24-87-2 (8)/2016 Date 18.11.2024
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : Deposit ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
618.87
Resanction Cost :
606.41
Tentative Cost :
606.41
Exp. Upto Last Fy :
0.00
For CFY 2025-2026
Remaining :
606.41
Demand :
200.00
Allotment :
242.56
Exp in CFY :
45.00
Total Up to Date Exp :
45.00
Construction Started
Sanction on : 1 year 2 months ago
18 Nov 2024
Physical Progress:
At start of FY 2025-2026 :
1 %
Up to Date :
35 %
Tentative Completion date on : 6 months 2 weeks from now
07 Aug 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
प्रथम तल में स्लैब कास्टिंग का कार्य पूर्ण। द्वितीय में लिंटल लेवल तक ब्रिक वर्क कार्य पूर्ण। -- as on 20-Jan-2026
Assets :
Work not linked with IM
Bridges on The Basis of AI: